DANIEL L. HEER v. DEBORAH GAMBLIN TOMBERLIN AND RICHARD TOMBERLIN
Annotate this Case
Download PDF
RENDERED: MAY 16, 2003; 10:00 a.m.
NOT TO BE PUBLISHED
C ommonwealth O f K entucky
C ourt O f A ppeals
NOS.
2002-CA-000650-MR & 2002-CA-000941-MR
DANIEL L. HEER
v.
APPELLANT/CROSS-APPELLEE
APPEAL AND CROSS-APPEAL FROM CHRISTIAN CIRCUIT COURT
HONORABLE JOHN ATKINS, JUDGE
ACTION NO. 97-CI-01143
DEBORAH GAMBLIN TOMBERLIN AND
RICHARD TOMBERLIN
APPELLEES/CROSS-APPELLANTS
OPINION
AFFIRMING
** ** ** ** **
BEFORE:
DYCHE, HUDDLESTON, AND KNOPF, JUDGES.
KNOPF, JUDGE:
In August 1996, Daniel Heer purchased a house and
lot in Hopkinsville from Deborah Gamblin (now Deborah
Tomberlin).
The purchase agreement included Gamblin’s promise
to correct a moisture problem in the basement crawl space as
well as her warrant that the house was free of defects in
materials and workmanship.
September 6, 1996.
The parties closed their transaction
Because at that time the crawl space still
leaked and did not drain well, Gamblin renewed her promise to
fix it “no later than September 15, 1996.”
Gamblin was relying
for repairs on the builder of the house, Richard Tomberlin, from
whom she had purchased it.
In mid-October 1996, with the crawl-
space problem still not resolved, Tomberlin himself promised
Heer to address it as well as other problems Heer had discovered
since moving in.
The crawl-space problem proved intractable,
however, and Heer was dissatisfied with other of Tomberlin’s
repairs, so on December 11, 1997, he filed suit against both
Gamblin and Tomberlin and sought an order compelling them to
provide the house they had allegedly contracted to provide.
On February 18, 1999, the trial court canceled the
upcoming jury trial and referred the parties to arbitration.
Construction Arbitration Services convened a hearing at the Heer
residence on July 8, 1999.
in the house.
Heer alleged some fifty-four defects
The arbitrator viewed the alleged defects and in
early August ordered some twenty-four repairs, including repair
of the crawl space, of improperly installed foundation anchor
bolts, of the improperly graded patio, and of the entryway’s
poorly-finished and ill-fitting hardwood floor.
Tomberlin
objected to certain aspects of the arbitrator’s award, and by
letter dated September 17, 1999, the arbitrator overruled the
objections pertinent to this appeal.
On October 27, 1999, Heer moved the circuit court to
confirm the award.
He also requested leave to hire someone
2
other than Tomberlin to make the repairs.
The court confirmed
the award, but assigned the repairs to Tomberlin, which
assignment the award seems to contemplate.
There ensued nearly
two years of bickering over the adequacy of Tomberlin’s efforts.
The upshot was a hearing on December 10, 2001, at which Heer
sought damages to effect repairs awarded at arbitration but, he
claimed, never provided by Tomberlin.
By judgment entered
February 28, 2002, the circuit court awarded Heer a total of
$16,500.00, including $5,000.00 for attorney fees.
Both parties
have appealed; Heer contends that the award is inadequate,
Tomberlin that it is excessive.
For the reasons that follow, we
affirm.
KRS 417.180 provides that once an arbitration award
has been confirmed, it may be enforced like a judgment.
We
shall assume, inasmuch as the parties have not raised the
question, that a monetary award such as the one at issue is an
appropriate means to enforce an award of specific performance
that the defendant has proved either unable or unwilling to
satisfy.1
This Court’s review of damage awards, of course, is
deferential.
We attempt not to reweigh the evidence, but only
1
See CR 70 and cf. Columbia Gas Transmission Corporation v.
Mangione Enterprises of Turf Valley, 964 F. Supp. 199 (D.C. D.
Md. 1996).
3
to ensure that substantial evidence supports the fact-finder’s
determinations.2
The trial court’s findings meet this standard.
Heer contends that the court erred by awarding
$7,500.00 to correct the crawl-space problem when one of his
experts testified that it would cost nearly twice as much to
install a subsurface exterior drain system guaranteed to keep
water out.
The same expert testified, however, that a less
expensive interior system would more than adequately control
moisture in the crawl space.
Heer’s other expert testified,
moreover, that exterior drains would not help much because
Heer’s problem was surface-water drainage, not sub-surface
infiltration.
This evidence substantially supports the trial
court’s finding that Heer can meaningfully address the crawlspace problem for $7,500.00.
Heer next contends that the court awarded too little
for repairs to the wood floor.
The arbitrator referred only to
mis-spaced boards in the entry way, but Heer maintains that,
since the arbitration, excessive moisture in the crawl space has
essentially ruined the entire floor.
He sought nearly $4,000.00
to have both the floor and the subfloor replaced.
awarded $1,500.00.
The court
There was testimony contrary to Heer’s that
repairs to the subfloor would not be required and that $1,500.00
2
Cole v. Gilvin, Ky. App., 59 S.W.3d 468 (2001).
4
would purchase ample replacement flooring for the entryway and
other damaged areas.
This testimony adequately sustains the
court’s award.
The arbitrator noted that foundation anchor bolts
along the back of the house had been mis-installed between the
foundation and the brick facia rather than within the foundation
wall.
Tomberlin addressed this problem by installing nineteen
metal straps within the back foundation wall and attaching them
to a new sill plate.
The trial court deemed this repair
adequate and so awarded Heer nothing for anchor bolts.
Heer
contends that anchor bolts would have been better than straps
and that Tomberlin mis-installed the straps as well.
Heer did
not introduce expert testimony on this issue or in any other way
adequately establish that the strap installation violated local
standards.
He conceded that straps sometimes substitute for
anchor bolts, and it was apparent that anchor bolts could not be
installed without first breaking holes in the foundation wall or
attaching them to the floor in an unconventional manner.
The
trial court did not err by deeming the straps an acceptable
response to the arbitration order.
Finally, Heer contends that the trial court awarded
too small an attorney fee.
He bases his claim on a “reasonable
fee” provision of the purchase agreement.
Heer sought a fee of
approximately $20,000.00, but the court awarded $5,000.00.
5
Not
only was the award too small, Heer contends, but the court did
not adequately account for it despite Heer’s motion pursuant to
CR 52.04 for additional explanation.
Heer correctly notes that
CR 52.01 requires the court, on issues tried without a jury, to
“find the facts specifically and state separately its
conclusions of law thereon.”
The trial court’s conclusory
attorney-fee ruling made no pretense of complying with this
rule.
Nevertheless, we are mindful that a principal reason
for CR 52.01 is to ensure an adequate record for subsequent
review.
When meaningful review is possible notwithstanding a
trial court’s noncompliance with the rule, the reviewing court
may waive the requirement.3
Meaningful review is possible here
notwithstanding the lack of findings in large part because the
scope of our review is limited.
A trial court enjoys broad
discretion to determine a “reasonable” attorney fee; its award
will not be overturned if there is any reasonable basis for it.4
Although the amount of attorney fees need not in all
circumstances bear any particular relationship to the
3
Clark Mechanical Contractors v. KST Equipment Company, Ky., 514
S.W.2d 680 (1974).
4
Capitol Cadillac Olds, Inc. v. Roberts, Ky., 813 S.W.2d 287
(1991).
6
plaintiff’s recovery,5 the size of the recovery is an important
factor the trial court is entitled to consider, especially
where, as here, the parties are of roughly equal standing and no
public policy favors the plaintiff’s access to litigation.
The
trial court’s fee award amounted to about a third of Heer’s
total recovery.
Limiting the fee to a third of the benefit the
attorney provided was not an abuse of the trial court’s
discretion.
By way of cross-appeal, Tomberlin contends that the
court should have awarded Heer nothing to repair the hardwood
floor.
Following the arbitration, Tomberlin applied filler to
gaps in the flooring, and that, he maintains, is all the
arbitration award required.
Heer insists that the gaps in the
floor are still unsightly and that in several areas the finish
has deteriorated and the surface has detached from the subfloor.
The trial judge visited the residence and determined that the
floor did not yet satisfy the arbitrator’s award.
This Court is
in no position to gainsay that determination.
Tomberlin also contends that the court erred by
awarding Heer an amount to replace the patio.
Apparently the
patio drains toward the foundation and thus is apt to contribute
to the crawl space problem.
Tomberlin maintains that even if
the patio does drain into the crawl space, installation of the
5
Meyers v. Chapman Printing Company, Ky., 840 S.W.2d 814 (1992).
7
contemplated crawl-space drainage system will make the patio
problem moot.
We agree with the trial court, however, that Heer
is entitled to a properly installed patio, one that works for,
not against, a dry house.
At one point during the struggle to solve the crawlspace problem, the trial court ordered Tomberlin to consult an
engineer.
The court assigned the engineer’s fee to Tomberlin as
part of the action’s costs.
Tomberlin contends, without
citation to a legal standard, that the fee is excessive and that
the court abused its discretion by upholding it.
We disagree.
The trial court has discretion to make use of extraordinary
services and to include their expense in the award of costs.6
The court did not abuse its discretion by ordering Tomberlin to
get help with the crawl-space problem, when, after nearly four
years of trying, he had proved incapable of solving it alone.
Testifying at the December 10, 2001, hearing, the engineer
described his efforts inspecting and conducting tests at the
Heer residence and drafting his report.
The fee awarded,
considerably less than the fee the engineer sought, is
consistent with that testimony.
The trial court did not abuse
its discretion by assigning this fee to Tomberlin.
Finally, Heer claimed that Tomberlin’s failure to make
timely repairs resulted in various consequential or supplemental
6
CR 54.04.
8
damages.
The trial court essentially dismissed this portion of
the claim as “not countenanced in our case or statutory law.”
Tomberlin asks us to rule that this dismissal precludes Heer
from seeking similar damages in a companion suit predicated on
Tomberlin’s alleged fraud.
This we may not do.
The general
rule, of course, is that courts are not authorized to give
advisory opinions.7
The preclusive effect, if any, of the trial
court’s ruling in this case will be for the trial court to
determine when and if it is confronted by a subsequent claim, a
claim concrete rather than hypothetical.
This Court will then
be available for review of that determination.
Neither party having shown that the Christian Circuit
Court erred or abused its discretion in enforcing the
appellant’s arbitration award, we affirm that court’s judgment
of February 28, 2002.
ALL CONCUR.
BRIEFS FOR APPELLANT/CROSSAPPELLEE:
BRIEF FOR APPELLEES/CROSSAPPELLANTS:
Kenneth W. Humphries
Hopkinsville, Kentucky
David L. Cotthoff
Fletcher, Cotthoff, Willen &
Redd
Hopkinsville, Kentucky
7
Philpot v. Patton, Ky., 837 S.W.2d 491 (1992); Sullivan v.
Tucker, Ky. App., 29 S.W.3d 805 (2000).
9
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.