In 2010, the Army Corps of Engineers awarded ECCI a contract to design and build a military compound in Afghanistan. In 2014, ECCI sought compensation for construction delays allegedly attributable to the government. After six years of unsuccessful settlement discussions, followed by a nine-day hearing before the Armed Services Board of Contract Appeals, the government—three months after the hearing—successfully moved to dismiss ECCI’s claim for lack of subject-matter jurisdiction for failure to state a “sum certain.”
The Federal Circuit reversed. The requirement, established by the Federal Acquisition Regulation, that claims submitted under the Contract Disputes Act (CDA), 41 U.S.C. 7101–7109, state a “sum certain”—i.e., specify the precise dollar amount sought as relief—is not jurisdictional and is subject to forfeiture. The court noted the Supreme Court’s direction to “police this jurisdictional line.” Congress did not clearly state that a claim submitted under the CDA must include a sum certain: the sum-certain requirement is not even in the CDA itself. A claim that does not state a sum certain has not sufficiently pleaded the elements of a claim under the CDA and may be denied by the contracting officer and dismissed on appeal for failure to state a claim. If a party challenges a deficient sum certain after litigation has far progressed, however, that defense may be deemed forfeited.