Annotate this CaseIn February, 2002, the Navy awarded GM&W a contract for floor coating at a military base. GM&W subcontracted with FloorPro, which completed the work on February 27, 2002 and billed GM&W. On March 8, the Navy informed GM&W that the work was completed satisfactorily. On April 17, FloorPro informed the Navy’s contracting officer that it had not been paid. GM&W had claims pending and was not sure whether funds that the Navy directly deposited would be available to FloorPro. In April 2002, the Navy and GM&W entered into contract modification providing for mailing to FloorPro of a check payable to GM&W and Floor-Pro. The Navy paid GM&W directly by electronic transfer and informed FloorPro that its recourse was to sue GM&W. In December 2002, FloorPro submitted a claim to the Navy’s contracting officer. On March 27, 2003, FloorPro filed at the Armed Services Board of Contract Appeals, which awarded $37,500. The Federal Circuit reversed, holding that under the Contract Disputes Act, 41 U.S.C. 7101, ASBCA has no jurisdiction over a claim by a subcontractor. In 2009, FloorPro filed in the Court of Claims, which ruled in favor of FloorPro. The Federal Circuit vacated, ordering dismissal under the six-year limitations period of 28 U.S.C. 2501.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.