Linear v. Village of University Park, No. 17-1940 (7th Cir. 2018)

Annotate this Case
Justia Opinion Summary

University Park hired Linear as its Village Manager through May 2015, concurrent with the term of its Mayor. In October 2014 the Village extended Linear’s contract for a year. In April 2015 Mayor Covington was reelected. In May, the Board of Trustees decided that Linear would no longer be Village Manager. His contract provides for six months’ severance pay if the Board discharges him for any reason except criminality. The Village argued that the contract’s extension was not lawful and that it owes Linear nothing. The district court agreed and rejected Linear’s suit under 42 U.S.C. 1983, reasoning that 65 ILCS 5/3.1-30-5; 5/8-1-7 prohibit a village manager's contract from lasting beyond the end of a mayor’s term. The Seventh Circuit affirmed on different grounds. State courts should address the Illinois law claims. Linear’s federal claim rests on a mistaken appreciation of the role the Constitution plays in enforcing state-law rights. Linear never had a legitimate claim of entitlement to remain as Village Manager. His contract allowed termination without cause. His entitlement was to receive the contracted-for severance pay. Linear could not have a federal right to a hearing before losing his job; he has at most a right to a hearing to determine his severance pay--a question of Illinois law.

Download PDF
In the United States Court of Appeals For the Seventh Circuit ____________________ No. 17-1940 LAFAYETTE LINEAR, Plaintiff-Appellant, v. VILLAGE OF UNIVERSITY COVINGTON, MAYOR, PARK, ILLINOIS, and VIVIAN Defendants-Appellees. ____________________ Appeal from the United States District Court for the Northern District of Illinois, Eastern Division. No. 15 C 7653 — Harry D. Leinenweber, Judge. ____________________ ARGUED FEBRUARY 14, 2018 — DECIDED APRIL 17, 2018 ____________________ Before EASTERBROOK and ROVNER, Circuit Judges, and GRIESBACH, District Judge.* EASTERBROOK, Circuit Judge. University Park hired LafayeZe Linear as its Village Manager under a four-year contract that ran through May 2015, concurrent with the term of * Of the Eastern District of Wisconsin, sitting by designation. 2 No. 17-1940 the Village’s Mayor. In October 2014 the Village extended Linear’s contract for a year. But by spring 2015 relations between Linear and the Village’s elected o cials had soured. In April 2015 Mayor Covington was reelected, and her new term began in May. That month the Board of Trustees decided that Linear would no longer be Village Manager. His contract provides for six months’ severance pay if the Board discharges him for any reason except criminality. But the Village has taken the position that the contract’s extension was forbidden by Illinois law and that it owes Linear nothing, because his only valid term expired in May 2015. Linear contends in this federal suit under 42 U.S.C. §1983 that the Board violated the Due Process Clause of the Fourteenth Amendment by not giving him a hearing before his discharge. The Village replies that he has not been discharged; it just declined to renew his contract—and Linear does not contend that he had a legitimate claim of entitlement to a renewal. Compare Board of Regents v. Roth, 408 U.S. 564 (1972), with Perry v. Sindermann, 408 U.S. 593 (1972). The district court decided that, as a maZer of Illinois law, the extension past May 2015 was invalid. The judge understood 65 ILCS 5/3.1-30-5 and 5/8-1-7 to prohibit any contract for a village manager from lasting beyond the end of a mayor’s term of o ce. As a result, the district court held, the Village did not deprive Linear of a property interest, and without a property interest he had no federal right to a hearing. The parties’ briefs debate the meaning of these two state statutes and whether other statutes (such as those giving the Village home-rule powers) create exceptions to them. But if the core dispute concerns state law, why is this case in federal court? Linear and the Village are citizens of Illinois; the No. 17-1940 3 absence of diversity means that only a claim arising under federal law allows adjudication. Linear has of course asserted a federal theory: that the Due Process Clause entitles him to a hearing. But that seems to be a makeweight, a way of geZing a state-law dispute resolved by a federal judge. Sometimes a statute or established practice creates a legitimate claim of entitlement to keep one’s job, which amounts to a property interest that under Roth and its successors requires a hearing before the employee can be red. But Linear has never had a legitimate claim of entitlement to remain as Village Manager. His contract allowed the Village to re him without cause. His entitlement was not to stay in a policy-making job—no unit of government can contract away its right to have the voters and their elected representatives set public policy—but to receive the contracted-for severance pay. So Linear could not have a federal right to a hearing before someone else took his job; he has at most a right to a hearing to determine whether he gets six months’ severance pay. And that’s a question of Illinois law only. A contractual right to severance pay is a form of property interest, but this does not imply that a hearing must precede the municipality’s decision to have a new Village Manager. Severance pay cannot be transmuted to a sinecure, and elected o cials’ ability to replace high o cials frustrated, by the fact that pre-termination hearings take time. If Congress promised Cabinet o cers six months’ pay if red by the President without cause, that would not entitle the o cer to keep the job while disputes about “cause” were resolved. Cf. Myers v. United States, 272 U.S. 52 (1926). Many years ago we held that, for someone who relies on a property interest created by a contract with a public body, 4 No. 17-1940 the process due when the government arguably has broken its promise is the opportunity to seek damages from a state court. Mid-American Waste Systems, Inc. v. Gary, 49 F.3d 286 (7th Cir. 1995). That conclusion has been repeated many times since. See, e.g., Kay v. Board of Education, 547 F.3d 736 (7th Cir. 2008); Blackout Sealcoating, Inc. v. Peterson, 733 F.3d 688 (7th Cir. 2013). Linear has not contended that he would be unable to obtain a hearing from a state court, which could award severance pay or another appropriate remedy. As long as the state courts are open, they provide the right forum for the parties’ dispute about whether the extension past May 2015 was valid. Linear resists this conclusion by contending that both his contract and an ordinance entitle him to a hearing before his removal, despite the Village’s entitlement to re him for any reason (that is, without cause). The problem with that argument is that procedural rights based on a contract or an ordinance have nothing to do with the Due Process Clause, which protects substantive interests—rights in life, liberty, or property—rather than state-created procedures. The Supreme Court made that clear in Olim v. Wakinekona, 461 U.S. 238, 250 (1983), and HewiK v. Helms, 459 U.S. 460, 471 (1983), which rejected the kind of argument that Linear makes: that procedures required by state law create property interests and hence lead to a federal requirement that the state procedures be used. State-law rights can’t be bootstrapped into federal rights so easily. Countless times the Justices have rejected contentions that the federal Constitution requires states to follow their own law. See, e.g., Snowden v. Hughes, 321 U.S. 1, 11–13 (1944) (an argument that a failure to follow procedures established by state law thereby violates the Constitution is so insubstantial that it does not establish fed- No. 17-1940 5 eral jurisdiction); Beck v. Washington, 369 U.S. 541, 554–55 (1962); Rivera v. Illinois, 556 U.S. 148, 158 (2009); Swarthout v. Cooke, 562 U.S. 216, 220–22 (2011). We regularly disparage arguments of the sort that Linear advances. See, e.g., Babchuk v. Indiana University Health, Inc., 809 F.3d 966, 970 (7th Cir. 2016); Sung Park v. Indiana University School of Dentistry, 692 F.3d 828, 832 (7th Cir. 2012); Weinstein v. University of Illinois, 811 F.2d 1091, 1097–98 (7th Cir. 1987). The state-procedurerequires-federal-procedure theme fares no beZer today. In another decision released today, we conclude that a di erent public employee asserting a right to a hearing before discharge is entitled to litigate in federal court. Breuder v. Board of Trustees, No. 17-1577 (7th Cir. Apr. 17, 2018). The reasons for the disparate outcomes bear emphasis. First, Breuder had a contractual right to keep his job unless he commiZed misconduct; Linear lacks such a right, so that a hearing was not required to protect an entitlement to the job (as opposed to an entitlement to receive damages). Second, accusations of misconduct accompanied Breuder’s termination, creating a federal right to a name-clearing hearing independent of any contractual rights under state law. See Codd v. Velger, 429 U.S. 624 (1977). Third, the right to a hearing for Breuder rested on federal law, while Linear locates that right in the contract and state law, subjects on which only a state court can be authoritative. Linear’s complaint presents claims under state as well as federal law. For the reasons we have explained, the federal claim rests on a mistaken appreciation of the role the Constitution plays in enforcing state-law rights. The district court relinquished supplemental jurisdiction of Linear’s state-law claims. The state judiciary is free to address those claims 6 No. 17-1940 from scratch; the district judge’s conclusions about the e ects of 65 ILCS 5/3.1-30-5 and 5/8-1-7 lack both preclusive and precedential e ect. AFFIRMED
Primary Holding

Village Manager, fired and denied severance pay, did not state a federal civil rights claim, but only claims under state law.


Disclaimer: Justia Annotations is a forum for attorneys to summarize, comment on, and analyze case law published on our site. Justia makes no guarantees or warranties that the annotations are accurate or reflect the current state of law, and no annotation is intended to be, nor should it be construed as, legal advice. Contacting Justia or any attorney through this site, via web form, email, or otherwise, does not create an attorney-client relationship.

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.