In a dispute involving a power grid operator, PJM Interconnection, L.L.C., and the Federal Energy Regulatory Commission (FERC), the United States Court of Appeals for the Sixth Circuit ruled that the Chairman of FERC exceeded his authority by seeking a remand of a ratemaking challenge without the support of other Commission members.
The case originated when PJM filed a request to modify its existing rates for electricity reserves, arguing that the existing rates were unjust and unreasonable. Initially, FERC agreed and approved the new rates. However, after a change in FERC's composition and a unilateral decision by the Chairman to request a voluntary remand from the D.C. Circuit for reconsideration, FERC reversed its decision and found PJM's evidence insufficient.
The Sixth Circuit's ruling focused on the procedural irregularity, specifically the Chairman's unilateral decision to seek a remand, which it deemed exceeded his administrative authority. The court stated that a quorum majority must decide the Commission’s policy and dealings with the outside world, and the Chairman acting alone does not meet this requirement. As such, the court vacated the part of FERC's rehearing order that claimed the Chairman had this unilateral authority and remanded the matter back to FERC to address this issue.
The court did not address the substantive issue of whether FERC's reversal on the ratemaking decisions was arbitrary and capricious. It noted that any interested party may renew a petition to challenge that decision after FERC resolves the procedural issue.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.