Midship Pipeline v. FERC, No. 22-60225 (5th Cir. 2022)
Annotate this Case
Midship Pipeline Company, L.L.C. challenged part of a Federal Energy Regulatory Commission (FERC) order directing an administrative law judge to determine the “reasonable cost” for Midship to complete remediation activities at Sandy Creek Farms in Oklahoma.
The Fifth Circuit disagreed with the FERC, finding that the matter was ripe for appeal. Further, the Fifth Circuit determined that the FERC order directing an administrative law judge to determine the “reasonable cost” of remediation activities was ultra vires because the FERC lacked authority under the Natural Gas Act (NGA) to do so. Thus, the court held that the FERC's action was ultra vires and vacated that portion of the Commission's order. The court remanded the remaining portion of the order to the FERC for further proceedings.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.