Credos Industrial v. Targa Pipeline, No. 22-20480 (5th Cir. 2023)
Annotate this Case
In 2017, KP Engineering entered into a contract with Appellee to engineer and build a natural gas processing plant. KP Engineering hired Appellant as a subcontractor. Midway through the project, KP Engineering stopped paying its subcontractors, including Appellant, resulting in $2,329,830.86 in outstanding invoices. Appellee then ended its contract with KP Engineering but asked Appellant to stay on and complete the project. In exchange, Appellee promised that it would pay Appellant any unpaid invoices. Appellee paid nine of eleven outstanding invoices. Several weeks later, and after Appellant had substantially completed work on the project, Appellee informed Appellant that it would not pay the final two invoices.
KP Engineering then filed for bankruptcy in 2019. Appellant filed an adversary proceeding against Appellee in KP Engineering’s bankruptcy proceeding, seeking to recover amounts for the unpaid invoices. The bankruptcy court dismissed Appellant's claim.
On appeal, the Fifth Circuit affirmed, rejecting Appellant's quantum meruit claim, finding that it was barred by the existence of an express contract that covered the services at issue. The Fifth Circuit also rejected Appelant's unjust enrichment and breach of contract claims.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.