D2 Excavating, Inc. v. Thompson Thrift Construction, Inc., No. 19-40745 (5th Cir. 2020)
Annotate this Case
D2 filed suit for breach of contract, quantum meruit, violations of the Texas prompt pay statute, and to foreclose on a statutory and constitutional lien. Thompson, in turn, alleged that D2 breached the excavation contract between the parties. The district court held in D2's favor on all claims and ordered Thompson to pay for unpaid work and for "excess" excavating work, as well as interest and attorneys' fees.
The Fifth Circuit held that the district court did not clearly err by finding that management of the site was so deficient that D2 had to regrade the same areas as many as six times and was unable to complete its work in other parts of the site, justifying D2's cessation of work. Therefore, the court affirmed the district court's judgment for the $81,068 in unpaid work and the related prompt payment statute and lien remedies for that breach of contract. However, the court held that neither breach of contract nor quantum meruit allows D2 to recover for "excavation of unanticipated excess soil." Thus, the court reversed the district court's judgment of $257,588.53 for the "excavation of unanticipated excess soil" and rendered judgment for Thompson on those breach of contract and quantum meruit claims. The court remanded for modification of the judgment.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.