El Paso Electric v. FERC, No. 18-60575 (5th Cir. 2023)
Annotate this Case
Seven years ago, the Fifth Circuit court vacated d, as arbitrary and capricious, the Federal Energy Regulatory Commission’s (“FERC”) cost allocation scheme for electrical grid improvements in the WestConnect region, which covers utility service to much of the American West. On remand, FERC was instructed to provide a more complete justification for its orders. The petition under review asserts that the reasons FERC gave on remand remain insufficient.
The Fifth Circuit granted the petition and reversed the orders. The court explained that FERC’s orders violate the Federal Power Act as a matter of law and, alternatively, the agency has again inadequately explained its actions. The cost causation principle that binds FERC does not authorize it to force its regulated jurisdictional utilities to assume the costs of providing service to non-jurisdictional utilities. The court explained that FERC’s compliance orders cannot “satisfy its statutory mandate—except by ignoring the benefits the non-jurisdictional utilities would receive.”
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.