The New Jersey Board of Public Utilities (BPU) ordered Altice, a cable service provider, to prorate its bills for the month in which a cable customer cancels his service, as required by New Jersey law. In federal court, Altice argued that the Proration Requirement is preempted by the Cable Communications Policy Act of 1984.
The district court granted Altice judgment on the pleadings, concluding that “Younger” abstention was not warranted and that the Proration Requirement was preempted. The Third Circuit vacated. The Younger ruling was incorrect. BPU’s civil enforcement proceeding was quasi-criminal in nature and, thus, the type of proceeding to which Younger applies. BPU commenced the action against Altice by filing a formal complaint, a Show Cause Order with attributes similar to the filing of formal charges, and did so in its sovereign capacity. The proceeding was judicial in nature and ongoing when the federal complaint was filed; the proceeding implicates important state interests; and Altice has an adequate opportunity to raise its federal claims in the state proceeding.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.