The Resource Group International Limited v. Chishti, No. 23-286 (2d Cir. 2024)
Annotate this Case
The United States Court of Appeals for the Second Circuit has decided an appeal from The Resource Group International Limited, TRG Pakistan Limited, Mohammed Khaishgi, and Hasnain Aslam against Muhammad Ziaullah Khan Chishti. The appellants sought to avoid arbitration proceedings initiated by the appellee, arguing that a later-executed release agreement superseded the arbitration agreement in the original Stock Purchase Agreement. The appellants also sought a preliminary injunction to halt the ongoing arbitration, but the District Court denied their request, asserting that they failed to show a likelihood of success on their claims and that they would suffer irreparable harm without the injunction.
On appeal, the Circuit Court held that it had jurisdiction over the case, finding that the parties had chosen New York law to govern the arbitration proceedings, thereby bypassing the restrictions on appellate review under the Federal Arbitration Act. The court also held that the District Court had relied on an erroneous view of the law in concluding that the appellants failed to show a likelihood of success on the merits of their claims and that they would suffer irreparable harm. The court found that the release agreement, which contained a forum selection clause, superseded the Stock Purchase Agreement's arbitration clause. The court also clarified that being forced to arbitrate a non-arbitrable claim could constitute irreparable harm, particularly where attorneys' fees and arbitration costs could not adequately compensate the harm.
As a result, the court vacated the District Court's decision and remanded the case for further proceedings.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.