L-7 Designs, Inc. v. Old Navy, LLC., No. 10-573 (2d Cir. 2011)

Annotate this Case
Justia Opinion Summary

Plaintiff filed a suit against defendant alleging claims of wrongful termination ("Count I"), trade disparagement ("Count II"), breach of contract for failure to negotiate in good faith ("Count III"), breach of the implied covenant of good faith and fair dealing ("Count IV"), and fraud ("Count V") arising out of a Creative Services Agreement ("Agreement") entered into between the parties. At issue was whether the district court properly dismissed the five counts asserted by plaintiff's complaint with prejudice and granted defendant's motion for judgment on the pleadings. The court held that the district court erred in dismissing Count III against defendant for failure to negotiate in good faith an alleged agreement to develop and launch a Todd Oldham branded line of merchandise to be sold exclusively at defendant's stores where plaintiff alleged three plausible bases for the claim. The court also held that the district court erred in dismissing Count I for declaratory judgment that defendant wrongfully terminated the parties' Agreement, by failing to give notice of plaintiff's alleged breaches and 30 days' opportunity to cure, under which plaintiff's principal, Todd Oldham, was to provide design services to defendant. The court affirmed the district court's dismissal of the trade disparagement, common law fraud, and breach of the implied duty of good faith and fair dealing claims. Accordingly, the court affirmed in part and vacated in part the district court's judgment and remanded for further proceedings.

Download PDF
10-573-cv L-7 v. Old Navy 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT August Term, 2010 (Argued: February 7, 2011 Decided: June 1, 2011) Docket No. 10-573-cv - - - - - - - - - - - - - - - - - - - - -x L-7 DESIGNS, INC., Plaintiff-Appellant, - v.- 10-573-cv OLD NAVY, LLC, Defendant-Appellee. - - - - - - - - - - - - - - - - - - - -x 26 27 28 29 30 Before: 31 Plaintiff-Appellant L-7 Designs appeals from a judgment 32 on the pleadings of the United States District Court for the 33 Southern District of New York (Denny Chin, Judge), entered * DENNIS JACOBS, Chief Judge, PETER W. HALL, Circuit Judge, SHIRA A. SCHEINDLIN,* District Judge. The Honorable Shira A. Scheindlin, of the United States District Court for the Southern District of New York, sitting by designation. 1 on January 21, 2010, dismissing five counts asserted in L- 2 7's Complaint, each arising out of a Creative Services 3 Agreement entered into between L-7 Designs and Defendant- 4 Appellee Old Navy in September of 2007. 5 the District Court erred in dismissing two of those counts 6 outright because L-7 plausibly alleged three bases for 7 breach of contract for failure to negotiate in good faith 8 (Count III) and wrongful termination (Count I). 9 Accordingly, we affirm in part and vacate in part the 10 District Court s judgment, and we remand for further 11 proceedings; in so doing we reverse in part the order of the 12 District Court that dismissed the Complaint and reinstate 13 the Complaint to the extent provided in this Opinion. We conclude that 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 FOR PLAINTIFF-APPELLANT: VIRGINIA R. RICHARD (Lori J. Van Auken on the briefs) Winston & Strawn LLP 200 Park Avenue New York, NY 10166 FOR DEFENDANT-APPELLEE: BRUCE P. KELLER (Shannon R. Selden on the brief) Debevoise & Plimpton LLP 919 3rd Avenue New York, NY 10022 2 1 2 3 SHIRA A. SCHEINDLIN, District Court Judge: 4 judgment on the pleadings of the United States District 5 Court for the Southern District of New York (Denny Chin, 6 Judge), entered on January 21, 2010, dismissing five counts 7 asserted in L-7's Complaint (the Complaint or Compl. ), 8 each arising out of a Creative Services Agreement (the 9 Agreement ) entered into between L-7 and Defendant-Appellee Plaintiff-Appellant L-7 Designs ( L-7") appeals from a 10 Old Navy ( Old Navy ) in September of 2007. We conclude 11 that the District Court erred in dismissing Count III 12 against Old Navy for failure to negotiate in good faith an 13 alleged agreement to develop and launch a TODD OLDHAM 14 branded line of merchandise (the Branded Line ) to be sold 15 exclusively in Old Navy stores. 16 erred in dismissing Count I for declaratory judgment that 17 Old Navy wrongfully terminated the parties Agreement under 18 which L-7's principal, Todd Oldham, was to provide design 19 services to Old Navy. 20 vacate in part the District Court s judgment, and we remand 21 for further proceedings; in so doing we reverse in part the 22 order of the District Court that dismissed the Complaint and 23 reinstate the Complaint to the extent provided in this 24 Opinion. The District Court also Accordingly, we affirm in part and 3 BACKGROUND2 1 2 3 4 5 I. Materials Properly Considered on a Motion for Judgment on the Pleadings One of the critical issues in this appeal is whether 6 the District Court properly considered not only the 7 Complaint, Old Navy s Answer, and the written documents 8 attached to the Complaint in deciding Old Navy s Rule 12(c) 9 motion, but also five email exhibits to Old Navy s 10 Counterclaims exhibits that were attached to Old Navy s 11 Answer only by virtue of the fact that its Answer and 12 Counterclaims were filed in the same document. 13 the District Court improperly considered the exhibits 14 without converting Old Navy s 12(c) motion to one for 15 summary judgment, as required by Rule 12(d). L-7 argues 16 On a 12(c) motion, the court considers the complaint, 17 the answer, any written documents attached to them, and any 18 matter of which the court can take judicial notice for the 19 factual background of the case. 20 F.3d 418, 419 (2d Cir. 2009). 21 to include any written instrument attached to it as an 22 exhibit, materials incorporated in it by reference, and Roberts v. Babkiewicz, 582 A complaint is [also] deemed 2 We set forth the pleadings in great detail to demonstrate the unusual amount of material the District Court had before it on this 12(c) motion. 4 1 documents that, although not incorporated by reference, are 2 integral to the complaint. 3 67 (2d Cir. 2004) (citations omitted) (quoting Chambers v. 4 Time Warner, Inc., 282 F.3d 147, 153 (2d Cir. 2002)). 5 is no question that the email exhibits were attached to 6 Old Navy s Answer, even if they were only part of Old 7 Navy s Counterclaims. 8 a written instrument that is an exhibit to a pleading is a 9 part of the pleading for all purposes ) (emphasis added). Sira v. Morton, 380 F.3d 57, There See Fed. R. Civ. P. 10(c) ( a copy of 10 Moreover, these emails of which L-7 had notice well before 11 Old Navy attached them to its Answer (because L-7 sent or 12 received them) were integral to the negotiation exchange 13 that L-7 identified as the basis for its Complaint. 14 Sira, 380 F.3d at 67 (document not expressly cited in 15 complaint was incorporated into the pleading because [it] 16 was integral to [plaintiff s] ability to pursue his cause 17 of action); Chambers, 282 F.3d at 153 (document integral 18 to complaint where complaint relie[d] heavily upon its 19 terms and effect ) (quotation marks omitted); Cortec Indus., 20 Inc. v. Sum Holding L.P., 949 F.2d 42, 48 (2d Cir. 1991) 21 (necessity of translating motion into one under Rule 56 22 largely dissipated where plaintiff had actual notice of 23 information in documents and relied upon [them] in framing 5 See 1 the complaint ). Plaintiffs failure to include matters of 2 which as pleaders they had notice and which were integral to 3 their claim and that they apparently most wanted to avoid 4 may not serve as a means of forestalling the district 5 court's decision on [a 12(b)(6)] motion. 6 at 44. 7 motion for judgment on the pleadings, we draw all facts 8 which we assume to be true unless contradicted by more 9 specific allegations or documentary evidence from the Cortec, 949 F.2d For these reasons, in reviewing de novo Old Navy s 10 Complaint and from the exhibits attached thereto,3 and we 11 also consider the emails attached to Old Navy s 12 Counterclaims. 13 Starwood Hotels & Resorts Worldwide, Inc., 369 F.3d 212, 222 14 (2d Cir. 2004) (discrediting allegation belied by letters 15 attached to the complaint); Hirsch v. Arthur Andersen & Co., 16 72 F.3d 1085, 1092 (2d Cir. 1995) ( General, conclusory 17 allegations need not be credited . . . when they are belied 18 by more specific allegations of the complaint. ). 19 thus derived, viewed in the light most favorable to L-7, are 20 as follows. See Blue Tree Hotels Inv. (Canada), Ltd. v. The facts 21 3 All exhibits cited herein are exhibits to the Complaint unless otherwise noted. 6 1 2 II. The Parties L-7's principal, Todd Oldham, is a world famous artist, 3 fashion and graphic designer, photographer, writer, and 4 television personality. 5 design services and intellectual property rights, including 6 eight U.S. federal registrations for the mark TODD OLDHAM. 7 [A] luminary in the fashion and design industry for over 8 twenty years, Oldham is considered one of the most 9 important designers of fashion and home furnishings working 10 today and the singular talent behind the internationally 11 famous TODD OLDHAM brand. 12 decade, Oldham and L-7 have collaborated on a variety of 13 TODD OLDHAM branded merchandise.4 14 He formed L-7 in 1989 to manage his Compl. ¶ 8. For more than a Old Navy, a subsidiary of Gap Inc., operates a chain of 15 retail apparel stores, with more than a thousand stores 16 throughout the United States and Canada. 17 last five years, Old Navy has been suffering declining 18 sales. 19 to increase its appeal to younger consumers. For at least the One of its strategies for increasing sales has been 20 4 For example, Oldham entered into a licensing agreement with Mattel, Inc. for a special collector s edition of a Barbie doll. 7 1 2 III. The Agreement In the spring of 2007, L-7 approached Old Navy to 3 discuss the possibility of entering into a relationship with 4 L-7, and Old Navy, enthusiastic about this possibility, 5 ultimately requested that Oldham become the company s new 6 Design Creative Director. 7 Oldham to join Old Navy s design team, Old Navy proposed to 8 introduce a TODD OLDHAM branded line of clothing, and to pay 9 royalties to L-7 in the form of five percent of the Branded Id. ¶ 26. In order to induce 10 Line s sales. 11 Navy pushed Oldham to enter into an agreement quickly so 12 that it could publicly announce both Oldham s appointment as 13 Old Navy s Design Creative Director and also the launching 14 of the Branded Line. 15 Faced with continuing declining sales, Old On September 21, 2007, the parties entered into the 16 Agreement,5 under which L-7 was to perform certain 17 Services and provide certain Deliverables, as set forth 18 in a Scope of Work (the SOW ) attached to the Agreement. 19 Agreement § 1. 20 services for Old Navy for three years in exchange for an 21 annual fee of $2 million; in addition, Oldham would 5 Under the SOW, Oldham would provide design By its terms, the Agreement is governed by New York law. 8 1 receive a guaranteed bonus of $0.5 million in year one and, 2 in years two and three, 1.25 percent of the year s 3 incremental sales (not to exceed $6 million). 4 Section 5 provided that during the term of the Agreement, 5 either party may terminate this Agreement, effective 6 immediately upon notice thereof, in the event of a material 7 breach of this Agreement that remains uncured after thirty 8 (30) days written notice of the breach to the other party. 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 IV. SOW §§ 1, 2. The Licensing Agreement Section 5 of the SOW, entitled Todd Oldham Branded Line, provided as follows: a. In September 2007, the parties will announce publicly that Todd Oldham/[L-7] shall be serving as Design Creative Director of Old Navy and that it is the intent of the parties to develop and launch a line of products that will bear TODD OLDHAM Marks to be sold exclusively at Old Navy stores at a future time. b. [L-7] and Old Navy acknowledge and agree that the specific terms and conditions related to this proposed line of products bearing TODD OLDHAM Marks are to be negotiated and agreed upon by the parties in a separate agreement. The parties plan to enter into a separate agreement related to these products by October 1, 2008. c. The parties agree that this separate agreement will contain at least the following: (1) royalty fees paid to [L-7] of 5% of Old Navy s retail sales for this particular line only (not all Old Navy products) and (2) agreement and final approval by both Old Navy 9 1 2 3 4 and [L-7] as to the collections and products to be sold by Old Navy. On September 21, 2007, Old Navy announced via a press 5 release that it intended to launch the Branded Line. 6 October 3, 2007, Monika Fahlbusch (the Old Navy executive 7 assigned to the Branded Line) emailed Vital Vayness (L-7's 8 representative) to recommend we plan to begin [discussion 9 on the license agreement for the Branded Line] in our new On 10 fiscal year say in April? 11 is no rush . . . . 12 performed their obligations under the Agreement, and Old 13 Navy executives publicly and privately praised Oldham s 14 performance as Design Creative Director. 15 V. Ex. 19. We have until October so there Thereafter, L-7 and Oldham April-October 2008 Negotiations 16 On April 2, 2008, L-7 (Vayness) initiated negotiations 17 to finalize the licensing agreement for the Branded Line by 18 emailing Fahlbusch (Old Navy) L-7's standard form license 19 agreement and a term sheet that outlined a three-year 20 initial term and annual guaranteed minimum royalties (the 21 April Proposal ). 22 Old Navy formulate [its] initial thoughts, needs and 23 objectives and then present to [Oldham] in [M]ay while Compl. ¶ 44. 10 The email suggested that 1 Fahlbusch (Old Navy), Vayness (L-7), and Old Navy s attorney 2 begin work on the language of the contract. Ex. 17. 3 Commencing in May 2008, Old Navy made material 4 representations that were false, as [L-7] subsequently 5 learned. 6 of 2008, Fahlbusch (Old Navy) assured Vayness (L-7) that she 7 was already working with our legal team on the licensing 8 agreement template. 9 spring and summer of 2008, L-7 repeatedly followed up with 10 Fahlbusch and Old Navy s Executive Vice President, Douglas 11 Howe, seeking feedback on the April Proposal and on a 12 redirection Old Navy was taking in its approach, with 13 little or no followup. 14 June of 2008 at which Oldham (L-7), Howe (Old Navy), and Tom 15 Wyatt (another Old Navy executive) were present, Old Navy 16 proposed postponing discussions of the Branded Line. 17 Nevertheless, on June 12, 2008, Vayness (L-7) indicated to 18 Fahlbusch (Old Navy) that things are proceeding in the 19 right direction with the branded line. Compl. ¶ 47; accord Ex. 19. Ex. 19. For example in May But throughout the late Exs. 19-20. During one meeting in Ex. 19. 20 In a late July 2008 email, Fahlbusch (Old Navy) 21 suggested that the reason for Old Navy s delay in getting 22 back to L-7 was that next steps on the Branded Line 23 license would be impacted by who is named President. 11 Id. 1 Vayness (L-7) responded the same day, reminding Fahlbusch 2 (Old Navy) that we have a provision in the contract calling 3 for the license agreement to be entered into by October 4 1st. 5 Id. On September 2, 2008, Vayness (L-7) emailed Fahlbusch 6 (Old Navy) seeking Old Navy s feedback on the terms set 7 forth in L-7's April 2008 email, indicating that L-7 was 8 ready to discuss [11 points] as early as possible. 9 20. Ex. L-7 followed up with emails and telephone calls to 10 Fahlbusch (Old Navy) on September 7, 9, and 10, 2008. On 11 September 10, 2008, Fahlbusch (Old Navy) recommended that 12 Oldham start working directly with Howe as it seems we 13 all have a different understanding of the numerous 14 conversations in recent months related to the branded line. 15 Id. 16 On September 30, 2008, Wyatt (Old Navy) advised L-7 in 17 a telephone call for the first time that Old Navy wished to 18 postpone the signing of a license for the Branded Line 19 indefinitely. Compl. ¶ 52 (quoting Wyatt).6 6 In The Complaint alleges that Howe, Old Navy s thenexecutive vice president, expressed this to L-7. See Compl. ¶ 52. An October 7, 2008 email from Vayness (L-7) to Wyatt, however, indicates that Wyatt made the statement. See Ex. 23. 12 1 response, L-7 stated that it expected Old Navy to provide it 2 with definitive dates to restart negotiations, enter into 3 the licensing agreement, and launch the Branded Line, and 4 compensation for the postponement of the initial October 1, 5 2008 signing date. 6 within a week as promised. 7 VI. 8 9 Old Navy failed to provide a response Fall 2008 Notice of Breach and Demand for Damages On October 7, 2008, L-7 advised Old Navy s in-house counsel that Old Navy was in material breach of the 10 Agreement for failing to negotiate in good faith. See Ex. 11 23. 12 Old Navy s view that the Agreement does not obligate Old 13 Navy to enter into a separate license agreement for Todd 14 Oldham branded products and that although Old Navy did not 15 foreclose the possibility of engaging in discussions about 16 Todd Oldham branded products in the future if business 17 conditions permit, [Old Navy is] not currently in a position 18 to make a commitment to any such future discussions. 19 24. 20 Oldham that Old Navy was very, very sorry but because of 21 economic conditions, Old Navy could not follow through with 22 the promised license for a TODD OLDHAM branded line of Counsel for Old Navy responded a week later, stating Ex. The next day, Wyatt, then President of Old Navy, told 13 1 apparel to be carried exclusively in Old Navy stores. 2 Compl. ¶ 55. 3 After waiting thirty days from Old Navy s receipt of L- 4 7's October 7th notice of breach, outside counsel for L-7 5 sent a letter to Old Navy requesting that Old Navy remedy 6 the damage to L-7 caused by Old Navy s breach by (1) 7 compensating L-7 for lost royalties and reputational damages 8 (estimated at $75 million) and (2) paying Oldham his 9 expected fees for the second and third years of the 10 Agreement ($4 million). 11 12 VII. Old Navy s December 2008 Response On December 3, 2008, counsel for Old Navy responded, 13 denying that Old Navy was obligated to enter into a license 14 agreement or had failed to negotiate in good faith. 15 for Old Navy explained that, in the course of their 16 negotiations, Counsel 17 18 19 20 21 22 23 24 25 differences emerged in the parties positions, including on such essential issues as the types of products to be included in the line, how many stores would be included in a launch, the staffing necessary to support such a line, and, most importantly, the timing of any such launch. Ex. 26. 26 circumstances made an extensive launch in the immediate near 27 term unfeasible. According to Old Navy s counsel, business Id. Thereafter, from December 15, 2008 14 1 to February 6, 2009, Old Navy engaged in sham 2 negotiations, falsely representing that it fully intended 3 to enter into a license agreement. 4 5 VIII. Compl. ¶ 124. The Old Navy January 2009 Proposal The parties met once in December 2008 and several times 6 in January 2009 to work out the details of the license 7 agreement, a further draft of which L-7 supplied to Old 8 Navy on December 15, 2008. 9 2009, one hour before a scheduled conference call, Old Navy 10 proposed a launch at 100 Old Navy stores ( As you know, our 11 history of presenting third party-branded product in our 12 stores is relatively short . . . ); a one-year commitment 13 beginning in the spring of 2010; no additional personnel 14 resources; and a one-year projected royalty of $1.5 million 15 ( . . . our previous discussions have never contemplated any 16 royalty minimum guarantees, and, as a general rule, our 17 company has not and will not agree to minimum guarantees. 18 This has been consistent in all of our recent agreements. ) 19 (the January Proposal ). 20 IX. Compl. ¶ 60. On January 8, Ex. 27. January 2009 Discussions7 7 L-7's Complaint and exhibits attached thereto largely omit reference to the parties January 2009 discussions. The facts set forth below are primarily drawn from the five email exhibits to Old Navy s 15 1 2 Oldham responded immediately by email to Old Navy s January Proposal: 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Counterclaims Ex. A. 19 asked for a minimum guarantee of $37.5 million for a 20 three-year term and then reduced the request to $20 million 21 for a two-year term. 22 Old Navy whether it had made any changes to any of its 23 positions as stated [in the January Proposal]. 24 Old Navy responded the next day: 25 26 27 28 29 30 31 [Your projections] seem EXTREMELY uncommitted to me. This feels like an effort to absolve old navy's contractual responsibilities and not a commitment to build a new brand that was made to me when i joined and what you reiterated to me last month. 100 stores will not work. the 1 million in launch dollars will not be effective. the one year commitment is too brief as there are so many hiccups in launching a brand . . . . i hope that we can get this resolved but we are very far away from a reasonable plan. the volume of work necessary to bring a project of this scale to bloom is at great odds with your financial projections. In the discussions that followed, L-7 On January 16, 2009, L-7 inquired of Id. Ex. E. To date, we have not been presented with any comprehensive counteroffer and instead there has been a [sic] insistence on large guaranteed minimum payments that we have explained are unacceptable and inconsistent with our business plans and practices . . . . Counterclaims. 16 1 Id. Ex. D. 2 29, 2009, the parties held a conference call, during which 3 they agreed to talk again after speaking with their 4 respective principals. 5 Old Navy a revised proposal reflecting Oldham s input on 6 the points discussed during the call. 7 Additional emails were exchanged, and on January X. Ex. 28. The same day, L-7 emailed Id. February 2009 Communications 8 Four days later, on February 2, 2009, Old Navy 9 responded to L-7's January 29th email, advising L-7 that 10 despite our best efforts to negotiate an agreement that 11 would be reasonable and mutually acceptable, we have not 12 reached and will not be able to reach common ground on key 13 business terms, reiterating that minimum guaranteed 14 payments were inconsistent with our business plans and 15 practices. 16 explaining his surprise at Old Navy s email given that the 17 January 29, 2009 call was completely amicable, polite, 18 professional, and [] friendly and that none of the points 19 discussed during that call was left off as a deal breaker. 20 Id. 21 contended there was agreement ( number of stores, 22 products, timeline and term, marketing, royalty 23 rate, and territory ); items that it was now prepared to Id. Vayness (L-7) responded the same day, The email went on to list items as to which L-7 17 1 accept, including no minimum guaranteed royalties; two 2 points that needed clarification ( personnel and 3 development budget ); and one issue to be agreed to, 4 namely ownership of designs. 8 5 Old Navy advised L-7 that material open issues remained, 6 and that, in light of the nature of the negotiations, Old 7 Navy did not believe that a collaborative partnership 8 could be established. 9 XI. 10 Id. On February 6, 2009, Compl. ¶ 62. Old Navy s Termination of the Agreement On February 18, 2009, L-7 commenced this lawsuit 11 against Old Navy, filing under seal a complaint alleging 12 breach of contract, breach of the implied duty of good faith 13 and fair dealing, and fraud. 14 20, 2009, counsel for Old Navy sent L-7 a letter terminating 15 the Agreement ( Termination Letter ) on the grounds that L-7 16 had 17 18 19 20 21 Two days later, on February materially breached the [Agreement] by filing a lawsuit against Old Navy, by failing to provide meaningful input on design processes and procedures, by failing to participate meaningfully in meetings with the Old Navy 8 Citing this email, L-7 alleges in the Complaint that [o]n February 2, 2009, L-7 . . . accepted Old Navy's January 8, 2009 proposal in its entirety. Compl. ¶ 61. As the text of the email makes clear, however, this was not quite so. 18 1 2 3 4 creative team and by otherwise failing to perform its obligations under the [Agreement]. Ex. 29. 5 cure its alleged breaches. 6 Termination Letter, Old Navy had voiced no complaints about 7 Oldham s performance under the Agreement; instead, he was 8 continuously praised. Old Navy did not provide L-7 with an opportunity to Prior to the February 20th 9 10 11 PROCEDURAL HISTORY L-7 filed its first complaint in the District Court on 12 February 18, 2009, under seal. On April 17, 2009, L-7 filed 13 under seal the amended Complaint at issue in this appeal, 14 adding claims for (I) wrongful termination and (II) trade 15 disparagement to its claims for (III) breach of contract, 16 (IV) breach of the implied covenant of good faith and fair 17 dealing, and (V) fraud. 18 Counterclaims on May 1, 2009, and L-7 filed a Reply on May 19 8, 2009. 20 was fully submitted on August 21, 2009. 21 2009, the District Court stayed depositions and ruled that 22 a new discovery cut-off will be set after the pending [Rule 23 12(c)] motion is decided. 24 Appellate Brief ( L-7 App. Brief ) at 66. Old Navy filed its Answer and Old Navy s motion for judgment on the pleadings On September 9, Special Appendix to L-7 19 In an opinion 1 dated January 19, 2010, it granted Old Navy s motion, 2 dismissing L-7's Complaint with prejudice. 3 slightly amended opinion on January 21, 2010. 4 amend the judgment and replead two weeks later. 5 District Court denied L-7's motion in an opinion dated 6 February 16, 2010. 7 8 9 10 11 I. A. It issued a L-7 moved to The Motion for Judgment on the Pleadings Count III: Breach of Contract for Failure to Negotiate in Good Faith The District Court first dismissed L-7's claim for 12 breach of contract for Old Navy s failure to enter into the 13 licensing agreement.9 14 5 of the SOW undoubtedly did create [an] obligation on the 15 part of the parties to negotiate a license agreement in good 16 faith, 17 1432, 2010 WL 157494, at *8 (S.D.N.Y. Jan. 19, 2010). 18 However, it found that the record of the detailed 19 documentation of the negotiations between Old Navy and L-7 20 over the anticipated license agreement, combined with the 21 detailed allegations of the Complaint, show, unequivocally, 22 that L-7's claim that Old Navy failed to negotiate in good It nonetheless concluded that Section L-7 Designs, Inc. v. Old Navy, LLC, No. 09 Civ. 9 We affirm this portion of the District Court s dismissal of Count III. 20 1 faith is not plausible. 2 the parties exchanged numerous telephone calls and emails 3 and, as L-7 acknowledged, progress in the negotiations was 4 made, it concluded that Old Navy negotiated for some ten 5 months. 6 impasse and negotiations broke down in the fall of 2008, 7 the parties resumed talks and met several times in December 8 2008 and January 2009 before L-7 rejected Old Navy s 9 January Proposal. 10 Id. Id. First, based on the fact that Although the parties seemed to reach an Id. Second, the District Court concluded that because L-7 11 was making extraordinarily high demands, it was not 12 surprising that Old Navy resisted these demands, noting 13 that at the agreed-upon five percent royalty rate some $200 14 million in sales of Todd Oldham branded products would had 15 to have been generated in one year to generate even the 16 reduced royalty request proposed by L-7 ($20 million over 17 two years). 18 Id. Third, L-7's only non-conclusory, specific allegation 19 was its assertion that Old Navy decided to renege on its 20 own January 8, 2009, proposal, and that this decision is 21 itself damning evidence of [Old Navy s] bad faith. 22 *9 (quoting L-7's Memorandum of Law in Opposition to Old 23 Navy s Motion for Judgment on the Pleadings ( L-7 12(c) 21 Id. at 1 Opp. ) at 23). 2 emails attached to Old Navy s Counterclaims rendered this 3 assertion not plausible because they showed that L-7's 4 purported acceptance of the January 8th proposal on February 5 2, 2009, clearly was not [] an acceptance of the proposal 6 in its entirety. 7 But, the District Court concluded, the Id. (quoting Compl. ¶ 61). Fourth, because insisting on terms to the point of 8 impasse [is] not sufficient to show bad faith, L-7 could 9 not argue that Old Navy s refusal to agree to a minimum 10 guarantee [was] evidence of bad faith. 11 Assocs. Corp. v. Zenith Data Sys. Corp., 96 F.3d 275, 279 12 (7th Cir. 1996)).10 13 14 B. Id. (citing Venture Count I: Wrongful Termination The District Court also dismissed Count I a request 15 for declaratory judgment (1) that Old Navy failed to provide 16 (i) written notice of its claims of breach or (ii) 30 days 17 opportunity to cure any claimed breach; (2) that the 18 Termination Letter did not effect a termination of the 10 The District Court then concluded that, because Count IV (breach of the implied duty of good faith and fair dealing) was essentially identical to Count III as both are based on the allegation that Old Navy failed to negotiate a license agreement in good faith, Count IV failed to state a claim [f]or the [same] reasons. 2010 WL 157494, at *9. 22 1 Agreement; and (3) that Old Navy wrongfully terminated the 2 Agreement in retaliation for L-7's lawsuit against it. 3 District Court offered three reasons why the claim fails as 4 a matter of law, 2010 WL 157494, at *9. 5 did provide written notice of termination. 6 (citing the Termination Letter). 7 acknowledging Old Navy s admission that it failed to provide 8 a 30-day cure period, the District Court found that it was 9 relieved of this obligation because, for two reasons, notice The First, Old Navy Id. at *10 Second, while 10 of cure would have been futile. 11 Court reasoned, [i]t is difficult to imagine that Oldham 12 could perform [his] duties after he sued Old Navy. 13 (citing Allbrand Discount Liquors, Inc. v. Times Square 14 Stores Corp., 399 N.Y.S.2d 700, 701 (2d Dep t 1977), for the 15 proposition that when one party will not live up to the 16 contract, the aggrieved party is relieved from the 17 performance of futile acts ). 18 19 20 21 22 23 24 25 26 27 28 Initially, the District Id. In particular, Oldham could not very well continue to help Old Navy creatively, including with respect to public relations matters, while pursuing a lawsuit against Old Navy. ([Agreement] § 1). Among other things, Oldham was supposed to, under the [Agreement], [m]otivate, inspire, coach, and share vision, insight and passion with Old Navy s creative team, and he was supposed to [p]rovide input to Old Navy s president and leadership team. ( Id.). 23 1 Id. 2 District Court reasoned, because [e]ven a withdrawal of the 3 complaint and it is highly unlikely that L-7 would have 4 withdrawn the complaint if Old Navy had sent L-7 a notice to 5 cure would not have undone the harm caused by the public 6 filing of a lawsuit against Old Navy. 7 failed because even assuming the failure to give a cure 8 period was a breach, in the context here it surely was not a 9 material one. 10 Notice of breach would also have been futile, the Id. Third, Count I Id. After then dismissing Counts II and V of the Complaint 11 for trade disparagement and fraud, the District Court 12 granted Old Navy s motion for judgment on the pleadings and 13 dismissed L-7's claims with prejudice. 14 in favor of Old Navy on January 21, 2010. 15 16 II. Judgment was entered Motion to Amend and Replead L-7 filed a motion to amend the judgment and replead on 17 February 5, 2010 based on information contained in 18 documents produced by Old Navy following the close of 19 briefing on the Rule 12(c) motion. 20 Replead at 1. 21 reasoning that L-7 had already had two bites at the apple, 22 as it has already filed two complaints ; the request is 23 untimely, as L-7 has had the documents for months yet L-7 Motion to Amend and The District Court denied the motion, 24 1 never indicated a desire to amend its amended complaint 2 prior to the granting of the motion for judgment on the 3 pleadings ; and, because the additional documents L-7 now 4 seeks to rely on would not change the District Court s 5 conclusions, the proposed amendment therefore would be 6 futile. 7 1432, 2010 WL 532160, at *2 (S.D.N.Y. Feb. 16, 2010). 8 filed a timely notice of appeal on February 17, 2010. L-7 Designs, Inc. v. Old Navy, LLC, No. 09 Civ. L-7 9 10 DISCUSSION 11 I. Motion for Judgment on the Pleadings 12 13 A. Standard of Review We review de novo a district court s decision to grant 14 a motion for judgment on the pleadings pursuant to Rule 15 12(c). See Hayden v. Paterson, 594 F.3d 150, 160 (2d Cir. 16 2010). In deciding a Rule 12(c) motion, we employ[] the 17 same . . . standard applicable to dismissals pursuant to 18 [Rule] 12(b)(6). 19 allegations in the [C]omplaint as true and draw all 20 reasonable inferences in [Plaintiff s] favor. Thus, we will accept all factual 25 Johnson v. 1 Rowley, 569 F.3d 40, 43 (2d Cir. 2009) (quotation marks and 2 citation omitted).11 3 In Ashcroft v. Iqbal, the Supreme Court set forth a 4 two-pronged approach to evaluate the sufficiency of a 5 complaint. 6 must accept as true all of the allegations contained in a 7 complaint, that tenet is inapplicable to legal conclusions, 8 and threadbare recitals of the elements of a cause of 9 action, supported by mere conclusory statements, do not 129 S. Ct. at 1949-50. First, although a court 10 suffice. Harris v. Mills, 572 F.3d 66, 72 (2d Cir. 2009) 11 (quotation marks and alterations omitted). 12 complaint that states a plausible claim for relief survives 13 a motion to dismiss, and determining whether a complaint 14 states a plausible claim for relief will . . . be a 11 Second, only a We note that, as plaintiffs carefully heed the admonition to support legal conclusions with factual allegations lest they be deemed conclusory and therefore denied a presumption of truthfulness, Ashcroft v. Iqbal, 129 S. Ct. 1937, 1950 (2009) trial judges, and appellate judges who review their determinations, are constantly faced with the task of evaluating competing inferences to be drawn from those facts. In this sense, Iqbal and Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 586 (2007), have rendered even more important (and more difficult) both trial judges adherence to the most fundamental pleading principles namely, accepting as true all factual allegations and drawing all reasonable inferences from those facts in plaintiffs favor and appellate judges subsequent de novo review of the decisions of the district courts. 26 1 context-specific task that requires the reviewing court to 2 draw on its judicial experience and common sense. 3 (quotation marks and alteration omitted). 4 standard is not akin to a probability requirement, but it 5 asks for more than a sheer possibility that a defendant has 6 acted unlawfully. 7 marks omitted). 8 considerations: the full factual picture presented by the 9 complaint, the particular cause of action and its elements, Id. The plausibility Iqbal, 129 S. Ct. at 1949 (quotation Plausibility thus depends on a host of 10 and the existence of alternative explanations so obvious 11 that they render plaintiff s inferences unreasonable. 12 id. at 1947-52. 13 B. 14 See Counts II, IV, and V We affirm the District Court s dismissal of the trade 15 disparagement and common law fraud claims substantially for 16 the reasons articulated by the District Court. 17 affirm dismissal of the claim for breach of the implied duty 18 of good faith and fair dealing, but for a different reason. 19 See infra note 18. 20 21 22 23 24 C. We also Count III: Breach of Contract for Failure to Negotiate in Good Faith 1. Applicable Law 27 1 Under New York law parties who enter into binding 2 preliminary agreements, such as Section 5 of the SOW, 3 accept a mutual commitment to negotiate together in good 4 faith in an effort to reach final agreement . . . . 5 Teachers Ins. & Annuity Ass n of Am. v. Tribune Co., 670 F. 6 Supp. 491, 498 (S.D.N.Y. 1987). 7 commit the parties to reach their ultimate contractual 8 objective; instead, such agreements create an obligation to 9 negotiate the open issues in good faith in an attempt to 10 reach the . . . objective within the agreed framework. 11 Adjustrite Sys., Inc. v. GAB Bus. Servs., Inc., 145 F.3d 12 543, 548 (2d Cir. 1998) (quotation marks omitted). 13 obligation bars a party from renouncing the deal, 14 abandoning the negotiations, or insisting on conditions that 15 do not conform to the preliminary agreement. 16 F. Supp. at 498. These agreements do not This Tribune, 670 17 In effect, an agreement to agree buys a party an 18 assurance that the transaction will falter only over a 19 genuine disagreement, thus allowing a party strapped for 20 time or money to go ahead with arrangements with a 21 sufficient degree of confidence in the outcome. 22 Bergner & Co. v. Martinez, 823 F. Supp. 151, 156 (S.D.N.Y. 23 1993); see also Penguin Grp. (USA) Inc. v. Steinbeck, No. 06 28 P.A. 1 CV 2438, 2009 WL 857466, at *2 (S.D.N.Y. Mar. 31, 2009) 2 ( The linchpin of negotiation is not that one side 3 capitulates to the other, but that there is a good faith, 4 honest, articulation of interests, positions, or 5 understandings. ); Venture Assocs. Corp., 96 F.3d at 278 6 ( The parties may want assurance that their investments in 7 time and money and effort will not be wiped out by the other 8 party s foot-dragging or change of heart or taking advantage 9 of a vulnerable position created in the negotiation. ). 10 [T]he parties may abandon the transaction as long as they 11 have made a good faith effort to close the deal and have not 12 insisted on conditions that do not conform to the 13 preliminary writing. 14 Adjustrite, 145 F.3d at 548. To state a claim for breach of contract for failure to 15 negotiate in good faith, a plaintiff must allege the 16 specific instances or acts that amounted to the breach ; 17 generalized allegations and grievances will not suffice to 18 survive a motion for judgment on the pleadings. 19 rel. Smith v. New York Presbyterian Hosp., No. 06 Civ. 4056, 20 2007 WL 2142312, at *16 (S.D.N.Y. July 18, 2007); accord 21 Prospect St. Ventures I, LLC v. Eclipsys Solutions Corp., 22 804 N.Y.S.2d 301, 302 (1st Dep t 2005). 29 U.S. ex 1 Although lost profits are not available where no 2 agreement is reached, see Goodstein Constr. Corp. v. City of 3 New York, 80 N.Y.2d 366, 374 (1992), out-of-pocket costs 4 incurred in the course of good faith partial performance are 5 appropriate, see Arcadian Phosphates, Inc. v. Arcadian 6 Corp., 884 F.2d 69, 74 n.2 (2d Cir. 1989). 7 2. Application 8 L-7 stated a plausible claim that Old Navy breached its 9 obligation to negotiate the license agreement in good faith. 10 The three bases alleged for this claim were that Old Navy 11 (1) failed to participate in negotiations from April 2008 12 to December 15, 2008 and never provided a single substantive 13 comment with respect to the draft license at any time in 14 2008, L-7 12(c) Opp. at 5;12 (2) made repeated material 15 representations that it would negotiate the terms of the 16 license agreement in good faith, which L-7 subsequently 17 learned were false, Compl. ¶ 47; and (3) proposed terms 18 it knew to be in bad faith and economically unfair to [L-7], 19 believing they would be rejected, and then reneged when [L- 20 7] did accept, L-7 12(c) Opp. at 23. 12 These are legally See also L-7 12(c) Opp. at 23 (Old Navy fail[ed] to engage [L-7] in negotiations on the licence with [L-7] for more than one year. ). 30 1 cognizable theories for breach of the duty to negotiate in 2 good faith. 3 L-7's favor, the non-conclusory allegations in L-7's 4 Complaint, combined with the exhibits attached thereto, 5 render each one plausible.13 6 Moreover, drawing all reasonable inferences in First, L-7 plausibly alleged that Old Navy who in 7 June of 2008 proposed postponing negotiations was engaged 8 in dilatory tactics from April 2008 until December 15, 2008, 9 during which time it failed to provide any substantive 10 comments on L-7's draft license agreement. 11 exchanged between Vayness (L-7) and Fahlbusch (Old Navy) 12 from April 2008 until September 10, 2008 when Fahlbusch 13 finally recommend[ed] that Vayness and Oldham work 14 directly with [Howe] in terms of the branded line, Ex. 21 15 support the plausible inference that Fahlbusch was 16 repeatedly putting L-7 off for undisclosed or pretextual 13 The emails Citing Adjustrite, 145 F.3d at 548, Defendant argues that the District Court could find, as a matter of law based on Old Navy s proposal of terms consistent with Section 5 of the SOW, that it negotiated in good faith. However, the only term specified in the September 2007 agreement with which Old Navy s proposal could have conform[ed] was the five percent royalty fee. That the January Proposal included this royalty provision does not establish as a legal matter that it acted in good faith, especially in light of L-7 s well-pled allegations that the January negotiations were designed to induce L-7's rejection. 31 1 reasons (discussed further below). The mere exchange of 2 telephone calls and emails most of which were initiated by 3 L-7 (according to L-7's exhibits) and some of which Old Navy 4 did not respond to (according to L-7's uncontradicted 5 allegations) does not make the inference that Old Navy 6 negotiated for some ten months, 2010 WL 157494, at *8, so 7 obvious that L-7's opposing inference of dilatory tactics is 8 rendered implausible.14 9 Similarly, whether or not L-7 agreed to Old Navy s 10 alleged request to postpone discussions in June of 2008 a 11 question of fact left open by the pleadings15 that would 14 Nor is the inference that progress in the negotiations was made, 2010 WL 157494, at *8, so obvious from L-7's June 12th email that things are proceeding in the right direction with the branded line that L-7's reasonable, opposing inference must be discredited. Drawing all reasonable inferences in L-7's favor, and taking into account its allegations that Old Navy was stalling, the June 12th email suggests that L-7, frustrated with Old Navy s non-responsiveness, was politely encouraging Old Navy to entertain L-7's proposals, while communicating its view that the parties still had a long way to go. 15 In the Facts section of its opinion, the District Court stated that Old Navy wanted to postpone the launch [of the Branded Line] and L-7 was prepared to do so, from October 1, 2008, to February 1, 2009. 2010 WL 157494, at *2. However, in making this factual determination, it cited a draft email from Vayness (L-7) to Howe (Old Navy) on Oldham s behalf. See Ex. 22 (entitled 2nd draft e mail to [Howe] ). The email Vayness (L-7) actually sent states only his underst[anding] that Howe thought that [Oldham] had agreed to postpone the finalizing of an agreement. Id. 32 1 not defeat L-7's allegations that Old Navy was engaged in 2 dilatory tactics. 3 and read[ing those facts] in [L-7's] favor, 4 Sepúlveda-Villarini v. Dep t of Educ. of Puerto Rico, 628 5 F.3d 25, 30 (1st Cir. 2010) (Souter, J.), it suggests the 6 converse that L-7, eager to execute the licensing 7 agreement on terms as favorable to it as possible, and 8 trusting that its negotiating partner in good faith believed 9 a postponement of discussions would be mutually [A]ssuming the pleaded facts to be true 10 advantageous, was negotiating in good faith. It is 11 reasonable to infer that, once L-7 became suspicious of what 12 it believed to be dilatory tactics on Old Navy s part, it 13 took a firmer stance, clarifying that while Old Navy may 14 have thought that [Oldham] agreed to postpone the 15 finalizing of an agreement, the idea of postponing 16 immediate discussions was merely discussed, and that the 17 parties should work to ensure that the Agreement did not 18 become breached, Ex. 22. (emphasis added). The draft email written by Oldham s representative about a June meeting for which he (the representative) was not present and where the idea of postponing the discussion . . . was discussed does not establish, at the motion for judgment on the pleadings stage, that L-7 was prepared to postpone the launch of the Branded Line by four months, 2010 WL 157494, at *2. 33 1 Second, L-7 plausibly alleged that, commencing in May 2 2008, Old Navy made repeated material representations that 3 L-7 subsequently learned were false, such as Fahlbusch s 4 (Old Navy s) assurances to Oldham that she was already 5 working with Old Navy s legal team on the licensing 6 agreement template, or her multiple promises to get back to 7 L-7, which either never happened or only occurred after 8 substantial delay.16 9 instead of revealing its true purpose, which was to avoid 10 entering into the license agreement as required under the 11 [Agreement], Compl. ¶ 121 (emphasis added), Old Navy 12 advanced pretextual reasons for its decision to delay 13 negotiations (economic conditions) and, ultimately, to cut 14 off negotiations (L-7's insistence on minimum guaranteed 15 royalties). 16 Butler, 626 F. Supp. 1229, 1233-34 (S.D.N.Y. 1986) 17 (upholding a finding of bad faith, after a six-day non-jury 18 trial, where evidence suggested that defendant deliberately 19 intended not to close on an agreement that was no longer L-7's Complaint also suggests that, See Teachers Ins. & Annunity Assoc. of Am. v. 16 A reasonable inference to draw from Old Navy s lack of communication and failure to supply counterproposals or comments on a draft license agreement that Old Navy s legal team was supposedly already working on as early as May 2008 is that Fahlbusch s (Old Navy s) representation was false. 34 1 economically favorable to it due to a decline in interest 2 rates, seiz[ing] on other terms of the agreement as a 3 pretext for not going forward with it at the eleventh 4 hour). 5 negotiating at all can be inferred from the fact that Old 6 Navy informed L-7 (1) that it wished to postpone the signing 7 of a license indefinitely, (2) that it could not make a 8 commitment to any discussions, and, ultimately, (3) that it 9 could not follow through with the promised license, Compl. 10 11 That Old Navy s true purpose was to avoid ¶ 55. Moreover, L-7's Complaint and the exhibits attached 12 thereto support the inference that Old Navy s purported 13 reasons for withdrawing from negotiations i.e., that 14 minimum guaranteed royalties were inconsistent with [Old 15 Navy s] business plans and practices, Ex. 28 were 16 pretextual. 17 royalties were not one of the four essential issues on 18 which differences [had] emerged in the parties positions 19 according to Old Navy, Ex. 26 (describing the timing of 20 [the] launch as the most important[] issue); and assuming 21 the truth of L-7's uncontradicted documentary evidence, none 22 of the points that had yet to be resolved after the 23 January 29th conference call including minimum guaranteed As of December 3, 2008, minimum guaranteed 35 1 2 royalties was left off as a deal breaker to L-7, Ex. 28. Third, L-7 plausibly alleged that Old Navy s January 3 Proposal was designed to be economically unfair to L-7 so 4 that L-7 would reject it, pointing to Old Navy s reneging 5 on its offer when L-7 ultimately signaled after several 6 counteroffers that it would accept the bulk of the January 7 Proposal. 8 Court concluded as a matter of law that L-7 did not accept 9 Old Navy s January Proposal, we are inclined to see a fact See L-7 12(c) Opp. at 23. While the District 10 question as to whether L-7 plausibly alleged that Old Navy s 11 January Proposal was designed to elicit L-7's rejection. 12 See Venture Assocs., 96 F.3d at 280 (business owner would be 13 acting in bad faith if its purpose in demanding more than 14 prospective buyer would pay was to induce [prospective 15 buyer] to back out of the deal ). 16 rejected key terms of Old Navy s January Proposal or made 17 a series of counter-demands before attempting to resurrect 18 it, 2010 WL 157494, at *9,17 the well-pled fact remains 17 Whether or not L-7 The District Court concluded that L-7's requests for minimum guaranteed royalties constituted extraordinarily high demands to which Old Navy s resistence was not surprising, 2010 WL 157494, at *8. But L-7 argues, and we are inclined to agree, that this factual determination was made without the benefit of discovery or expert testimony. 36 1 that, when L-7 finally acquiesced to Old Navy s insistence 2 on no minimum guaranteed royalties and appeared willing to 3 accept an offer substantially on Old Navy s terms, Old Navy 4 balked. 5 Navy s first proposal for the Branded Line did not come 6 until January of 2009, after the intervention of outside 7 counsel; (2) allegations that Old Navy s sluggish 8 negotiations from December 15, 2008 to February 6, 2009 were 9 a sham, Compl. ¶ 124; (3) documentary evidence that L-7 In light of the (1) documentary evidence that Old 10 was slowly retreating from and ultimately abandoned its 11 insistence on minimum guaranteed royalties, a supposed 12 sticking point for Old Navy; and (4) allegations that, under 13 new management and in a deteriorating retail environment, 14 Old Navy had decided it did not want to close any deal with 15 Oldham, the Complaint raised the plausible inference that 16 Old Navy s January Proposal was designed to elicit L-7's 17 rejection. 18 breach of contract for failure to negotiate in good faith.18 For all of these reasons, L-7 stated a claim for 18 Because L-7's claim for breach of the implied covenant of good faith and fair dealing (Count IV) is based on the same facts as its claim for breach of contract, it should have been dismissed as redundant. See Harris v. Provident Life & Accident Ins. Co., 310 F.3d 73, 81 (2d Cir. 2002); Fasolino Foods Co. v. Banca Nazionale del Lavoro, 961 F.2d 1052, 1056 (2d Cir. 1992) ( [B]reach of [the duty of good faith and fair dealing] is merely a breach of the 37 1 2 D. Count I: Wrongful Termination L-7 stated a claim for declaratory judgment for all 3 three prongs of Count I. First, L-7 stated a claim for 4 declaratory judgment that Old Navy failed to comply with the 5 notice and cure provisions of the Agreement. 6 party could terminate the Agreement, section 5 required (1) 7 notice of a material breach, (2) 30 days opportunity to 8 cure, (3) failure to cure the material breach, and (4) 9 notice of termination. See Agreement § 5. Before either But Old Navy s 10 Termination Letter provided only notice of termination 11 effective immediately without providing L-7 with notice of 12 its alleged breaches and 30 days opportunity to cure. 13 Navy conceded as much in its motion for judgment on the 14 pleadings. 15 Motion for Judgment on the Pleadings at 23. 16 claim should have survived. 17 Old See Old Navy s Memorandum of Law in Support of Therefore, this Second, for the same reasons, L-7's claim for 18 declaratory judgment that the Termination letter did not 19 effect a termination of the Agreement should have survived. 20 21 Third, L-7 stated a claim for declaratory judgment that Old Navy wrongfully terminated the Agreement. underlying contract. ). 38 Old Navy 1 notified L-7 that it had materially breached the 2 [Agreement] by [(1)] filing a lawsuit against Old Navy and 3 (2) by failing to satisfy certain unspecified performance 4 obligations. 5 meaning of an agreement is not a breach of that agreement 6 absent some explicit contractual provision that the party 7 will not bring suit. 8 Ajamie, 538 F. Supp. 2d 605, 611-12 (S.D.N.Y. 2008). 9 Moreover, as L-7 explained to the District Court, none of 10 the vague, unspecified issues mentioned in the Termination 11 Letter had been previously raised with L-7. . . . 12 contrary, Mr. Oldham had been repeatedly and widely praised 13 by Gap and Old Navy executives and staff throughout his Old 14 Navy tenure. 15 allegations in, and documentary evidence supporting, the 16 Complaint). 17 evidence, contradicting these well-pled facts. 18 accepting L-7's allegations as true and drawing every 19 inference in its favor, L-7 plausibly alleged that it was in 20 compliance with the Agreement, which was therefore 21 wrongfully terminated. 22 23 Ex. 29. [B]ringing suit to determine the Prudential Equity Grp., LLC v. To the L-7 App. Brief at 50 (citing multiple Old Navy made no argument, and pointed to no Therefore, The District Court dismissed Count I upon its determination that Old Navy had no duty to provide L-7 with 39 1 an opportunity to cure because such cure would have been 2 futile. 3 termination did not constitute breach or material breach, 4 then it is irrelevant whether L-7 could have cured. ) 5 Thus, the District Court concluded that Oldham was unlikely 6 to have been able to perform [his] duties after he sued Old 7 Navy and unlikely to have withdrawn his complaint if Old 8 Navy had sent a notice of breach. 9 speculative. (Of course, if the alleged grounds for L-7's But this appears to be That conclusion, and the conclusion that 10 withdrawal of the complaint could not have undone the harm 11 caused by the public filing of a lawsuit against Old Navy, 12 2010 WL 157494, at *10 (emphasis added), rests on the public 13 nature of the litigation. 14 both of L-7's complaints were filed under seal. 15 these reasons, Count I survives Old Navy s 12(c) motion as a 16 matter of law. 17 18 II. However, it is undisputed that For all of Motion to Amend the Judgment and Replead We generally review motions for reconsideration under 19 an abuse of discretion standard. 20 Commc n Int l Union, 175 F.3d 121, 131-32 (2d Cir. 1999). 21 However, a denial of leave to amend that is based on a legal 22 interpretation, such as for futility, is reviewed de novo. 23 See Gorman v. Consol. Edison Corp., 488 F.3d 586, 592 (2d 40 See Devlin v. Transp. 1 Cir. 2007); Littlejohn v. Artuz, 271 F.3d 360, 362 (2d Cir. 2 2001). 3 The District Court erred in denying L-7's motion for 4 leave to replead its bad faith negotiation claim based on 5 futility.19 6 stated a claim for relief, this error was harmless because 7 that Count of L-7's April 17, 2009 Complaint is reinstated. 8 CONCLUSION 9 However, in light of our finding that Count III For the foregoing reasons, we affirm in part and vacate 10 in part the District Court s judgment, and we remand for 11 further proceedings; in so doing we reverse in part the 12 order of the District Court that dismissed the Complaint and 13 reinstate Count I and Count III (on the three bases 14 discussed in this Opinion). 19 We affirm the District Court s denial of L-7 s motion for leave to replead trade disparagement and fraud. 41

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.