Centerplan Construction Co. v. Hartford
Annotate this Case
The Supreme Court reversed the judgment of the trial court finding Plaintiffs responsible for failing to complete a project by the parties' agreed-upon deadline and awarding Defendant $335,000 in liquidated damages on its counterclaim, holding that the trial court's pretrial interpretation of various agreements between the parties was erroneous.
At issue was which party was responsible for delays in constructing Dunkin Donuts Park in the City of Hartford. Plaintiffs, the project's developer and the design-builder, sued the City claiming breach of contract, and the City counterclaimed for breach of contract. The trial court concluded, as a matter of law, that Plaintiffs controlled the architect and were therefore liable for changes to and mistakes in the ballpark's design. Thereafter, the jury found Plaintiffs responsible for failing to complete the stadium by the agreed-upon deadline. The Supreme Court reversed, holding that the parties' contracts did not unambiguously grant Plaintiffs legal control of the architect and the stadium's design across all relevant time periods.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.