McCann v. City of San Diego
Annotate this CaseIn the first appeal arising from Plaintiff-respondent Margaret McCann’s dispute with the City of San Diego over the City’s environmental review process of a project to convert overhead utility wires to an underground system in several neighborhoods, she alleged the City violated the California Environmental Quality Act (CEQA) by failing to properly consider the environmental impact of two underground projects. The Court of Appeal concluded the City’s review process was incomplete as to one project (MND Project) because the City failed to analyze whether they were consistent with the City’s Climate Action Plan. The judgment was reversed and the case remanded for the trial court to issue a peremptory writ of mandate ordering the City of set aside three resolutions that approved the projects. After remand, the trial court also ordered it would retain jurisdiction over the matter until the City complied with the relevant provisions of the CEQA. The City rescinded the project approvals and asked the court to discharge the writ. McCann objected to the City’s return and argued the trial court should not discharge the writ because the City did not perform the relevant analysis or affirmatively indicate it abandoned the projects. The trial court sustained McCann’s objection and declined to discharge the writ. The City then appealed, arguing it fully complied with the courts’ mandates. After review, the Court of Appeal determined the City satisfied the writ, and therefore held the writ had to be discharged.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.