Carmel provided design and construction work for a luxury subdivision, Monterra, in Monterey County for more than 10 years under an oral contract with property owner Mills, the principal of Monterra LLC. Carmel recorded a mechanic’s lien and a site improvement lien against certain lots in Monterra after being informed that Monterra LLC would be unable to continue paying for the work. Carmel sued several of Monterra LLC’s investors with property interests in unsold lots in the development and Monterra LLC, alleging breach of contract and foreclosure of the mechanic’s and site improvement liens. Monterra stipulated to liability before trial; the investor defendants contested liability in a lengthy bench trial.
The court of appeal reversed. Carmel applied the payments it received from Monterra LLC to debt that was not subject to liens, in effect increasing the amounts of the Water Lien and Site Improvement Lien. It was improper to allocate a water infrastructure lien only to certain benefited lots; the liens could not accrue contractual interest greater than the reasonable value of the improvements. The trial court applied an incorrect rate to calculate prejudgment interest. The court remanded with instructions to remove contractual interest from both liens, reapportion the water infrastructure lien, and recalculate prejudgment interest.
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.