2015 Revised Code of Washington
Title 39 - PUBLIC CONTRACTS AND INDEBTEDNESS
39.10 Alternative public works contracting procedures.
39.10.320 Design-build procedure—Project management and contracting requirements.

WA Rev Code § 39.10.320 (2015) What's This?

RCW 39.10.320 Design-build procedure—Project management and contracting requirements.

(1) A public body utilizing the design-build contracting procedure shall provide:

(a) Reasonable budget contingencies totaling not less than five percent of the anticipated contract value;

(b) Staff or consultants with expertise and prior experience in the management of comparable projects;

(c) Contract documents that include alternative dispute resolution procedures to be attempted prior to the initiation of litigation;

(d) Submission of project information, as required by the board; and

(e) Contract documents that require the contractor, subcontractors, and designers to submit project information required by the board.

(2) A public body utilizing the design-build contracting procedure may provide incentive payments to contractors for early completion, cost savings, or other goals if such payments are identified in the request for proposals.

[2013 c 222 § 10; 2007 c 494 § 203; 1994 c 132 § 7. Formerly RCW 39.10.070.]

NOTES:

Sunset Act application: See note following chapter digest.

Effective date—2013 c 222: See note following RCW 39.10.210.

Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.