2015 Revised Code of Washington
Title 39 - PUBLIC CONTRACTS AND INDEBTEDNESS
39.08 Contractor's bond.
39.08.010 Bond required—Conditions—Retention of contract amount in lieu of bond.

WA Rev Code § 39.08.010 (2015) What's This?

RCW 39.08.010 Bond required—Conditions—Retention of contract amount in lieu of bond.

(1)(a) Whenever any board, council, commission, trustees, or body acting for the state or any county or municipality or any public body must contract with any person or corporation to do any work for the state, county, or municipality, or other public body, city, town, or district, such board, council, commission, trustees, or body must require the person or persons with whom such contract is made to make, execute, and deliver to such board, council, commission, trustees, or body a good and sufficient bond, with a surety company as surety, conditioned that such person or persons must:

(i) Faithfully perform all the provisions of such contract;

(ii) Pay all laborers, mechanics, and subcontractors and material suppliers, and all persons who supply such person or persons, or subcontractors, with provisions and supplies for the carrying on of such work; and

(iii) Pay the taxes, increases, and penalties incurred on the project under Titles 50, 51, and 82 RCW on: (A) Projects referred to in RCW 60.28.011(1)(b); and/or (B) projects for which the bond is conditioned on the payment of such taxes, increases, and penalties.

(b) The bond, in cases of cities and towns, must be filed with the clerk or comptroller thereof, and any person or persons performing such services or furnishing material to any subcontractor has the same right under the provisions of such bond as if such work, services, or material was furnished to the original contractor.

(2) The provisions of RCW 39.08.010 through 39.08.030 do not apply to any money loaned or advanced to any such contractor, subcontractor, or other person in the performance of any such work.

(3) On contracts of thirty-five thousand dollars or less, at the option of the contractor the respective public entity may, in lieu of the bond, retain fifty percent of the contract amount for a period of thirty days after date of final acceptance, or until receipt of all necessary releases from the department of revenue, the employment security department, and the department of labor and industries and settlement of any liens filed under chapter 60.28 RCW, whichever is later.

(4) For contracts of one hundred thousand dollars or less, the public entity may accept a full payment and performance bond from an individual surety or sureties.

(5) The surety must agree to be bound by the laws of the state of Washington and subjected to the jurisdiction of the state of Washington.

[2013 c 113 § 2. Prior: 2007 c 218 § 88; 2007 c 210 § 3; 1989 c 145 § 1; 1982 c 98 § 5; 1975 1st ex.s. c 278 § 23; 1967 c 70 § 2; 1915 c 28 § 1; 1909 c 207 § 1; RRS § 1159; prior: 1897 c 44 § 1; 1888 p 15 § 1.]

NOTES:

Intent—Finding—2007 c 218: See note following RCW 1.08.130.

Construction—Severability—1975 1st ex.s. c 278: See notes following RCW 11.08.160.

State highway construction and maintenance, bond and surety requirements: Chapter 47.28 RCW.

Disclaimer: These codes may not be the most recent version. Washington may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.