2014 Virginia Code
Title 43 - Mechanics' and Certain Other Liens
§ 43-8. Sufficiency of memorandum, affidavit and notice required by § 43-7


VA Code § 43-8 (2014) What's This?

The memorandum, affidavit and notice required by § 43-7 shall be sufficient if substantially in form and effect as follows:

Memorandum for Mechanic's Lien Claimed by Subcontractor.

Name of owner:.........................................................…

Address of owner:......................................................…

Name of general contractor (if any):...................................…

Name of claimant:......................................................…

Address of claimant:...................................................…

Contractor license or certificate number of claimant
(if applicable):..............................................…

Issuance date of license or certificate
(if applicable):..............................................…

Expiration date of license or certificate
(if applicable):..............................................…

If no contractor license or certificate number is included, theclaimant
certifies that such a valid license or certificate is not required by law for
the work done for which the benefit of a lien is claimed.

1. Type of materials or services furnished:.........................…

..........................................................................…

2. Amount claimed: $.................................................…

3. Type of structure on which work done or materials furnished:.....…

..........................................................................…

4. Brief description and location of real property:.................…

..........................................................................…

5. Date from which interest on above amount is claimed:

Date: .....................…

It is the intent of the claimant to claim the benefit of a lien.

...............................(Name of claimant).

Affidavit.

State of Virginia,

County (or city) of ..............................… to wit:

I, .........................… (notary or other officer) for the county
(or city) aforesaid, do certify that .............., claimant, or
................, agent for claimant, this day made oath before me in my
county (or city) aforesaid that ......................… is justly indebted
to claimant in the sum of ..........… dollars, for the consideration stated
in the foregoing memorandum, and that the same is payable as therein stated.

Given under my hand this the ..… day of ............, 20…

...................… (Notary Public or
Magistrate, et cetera.)

Notice.

To ...................…(owner).

You are hereby notified that ................… (general contractor) is
indebted to me in the sum of ............… dollars ($..........) with
interest thereon from the ......… day of .........., 20..., for work done
(or materials furnished, as the case may be,) in and about the construction
(or removal, etc.,) of a ........................… (describe structure,
whether dwelling, store, or etc.,) which he has contracted to construct (or
remove, etc.,) for you or on property owned by you in the county (or city) of
............., and that I have duly recorded a mechanic's lien for the same.

Given under my hand this the ............… day of ..........., 20..…

........................… (Subcontractor).

Code 1919, § 6428; 1968, c. 568; 2007, c. 504; 2013, c. 293.

Disclaimer: These codes may not be the most recent version. Virginia may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.