2013 Oregon Revised Statutes
Volume : 13 - Water Resources, Agriculture and Food
Chapter 543 - Hydroelectric Projects
Section 543.220 - Notice of filing of application; waiting period.


OR Rev Stat § 543.220 (2013) What's This?

(1) If an application is made for a preliminary permit, after said application has been referred to hearing the Water Resources Commission shall give written notice of the filing of the application to:

(a) Any municipality or other person or corporation that, in the judgment of the commission, is likely to be interested in or affected by the proposed project; and

(b) The owner of any land that is:

(A) Adjacent to any portion of the stream in which the quantity of water will be decreased by the project; or

(B) Adjacent to the site of the proposed project.

(2) The commission shall also publish notice of the application once each week for at least two successive weeks and for such further time, if any, as the commission shall determine, in a newspaper of general circulation in each county in which the project covered by the application is located.

(3) No application for the appropriation or use of water for the development of 1,000 theoretical horsepower or more shall be granted until at least six months after the application for a preliminary permit has been filed. [Amended by 1961 c.224 §16; 1975 c.581 §27; 1985 c.569 §23; 2011 c.52 §9]

Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.