For purposes of ORS 468.155 to 468.190, the construction or installation of a facility is commenced when the person constructing or installing the facility has obtained all necessary preliminary approvals and has begun continuous on-site modification, construction, installation or other activity, the completion of which will cause the person to be able to obtain certification under ORS 468.155 to 468.190. Interruptions and delays resulting from natural disasters, strikes, litigation or other matters beyond the control of the owner shall be disregarded in determining whether the actions undertaken by the person are continuous. The burden of demonstrating that construction or installation of a facility is commenced shall be borne by the person filing an application for certification under ORS 468.165. [2001 c.928 §8a]

Disclaimer: These codes may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.