Section 6131.45 - Extending the contract time.


Ohio Rev Code § 6131.45 (2013) What's This?

The time fixed in a contract for the performance of any work or the furnishing of any material, on good cause shown by affidavit, may be extended by the board of county commissioners with the approval of the county engineer for any definite period that it finds is reasonably necessary to complete the work or furnish the material under the contract. In case of such extensions the contractor's bond and any sureties thereon shall remain liable as if the extended time had been originally named in the bond or contract. The board shall not extend the contract time of furnishing any material to be used by a contractor unless by consent of the contractor the time for performance of his contract is correspondingly extended. Any order extending or refusing to extend the contract time shall be by resolution entered on the journal of the board. The affidavit shall be filed in the proceedings.

Upon the recommendations of the county engineer, the board of county commissioners may deduct the costs of engineering and inspection incurred by the county during the tenure of the authorized extensions of time as liquidated damages from any money due or to become due the contractor or his bondsmen unless the extension of time is due to an unforeseeable cause beyond the control and without the fault or negligence of the contractor.

Effective Date: 04-09-1981

Disclaimer: These codes may not be the most recent version. Ohio may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.