48-5-2. Procedure to obtain lien.

Any person entitled to a lien under this chapter [48-5-1 to 48-5-3 NMSA 1978], shall within ten days after the threshing is completed, file in the office of the county clerk of the county in which the grain was grown a statement in writing, verified by oath, showing the amount and quantity of grain threshed, the price agreed upon for threshing the same, the name of the person for whom the threshing was done and a description of the land upon which the grain was grown. Unless the person entitled to the lien shall file such statement within the time aforesaid he shall be deemed to have waived his right thereto.

Disclaimer: These codes may not be the most recent version. New Mexico may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.