2015 Nevada Revised Statutes
Chapter 704 - Regulation of Public Utilities Generally
NRS 704.751 - Order accepting plan or amendment to plan or specifying inadequacies; recovery of costs from customers; criteria for accepting transmission plan.

NV Rev Stat § 704.751 (2015) What's This?

1. After a utility has filed the plan required pursuant to NRS 704.741, the Commission shall issue an order accepting the plan as filed or specifying any portions of the plan it deems to be inadequate:

(a) Within 135 days for any portion of the plan relating to the energy supply plan for the utility for the 3 years covered by the plan; and

(b) Within 180 days for all portions of the plan not described in paragraph (a).

2. If a utility files an amendment to a plan, the Commission shall issue an order accepting the amendment as filed or specifying any portions of the amendment it deems to be inadequate:

(a) Within 135 days after the filing of the amendment; or

(b) Within 180 days after the filing of the amendment for all portions of the amendment which contain an element of the emissions reduction and capacity replacement plan.

3. All prudent and reasonable expenditures made to develop the utility’s plan, including environmental, engineering and other studies, must be recovered from the rates charged to the utility’s customers.

4. The Commission may accept a transmission plan submitted pursuant to subsection 4 of NRS 704.741 for a renewable energy zone if the Commission determines that the construction or expansion of transmission facilities would facilitate the utility meeting the portfolio standard, as defined in NRS 704.7805.

5. The Commission shall adopt regulations establishing the criteria for determining the adequacy of a transmission plan submitted pursuant to subsection 4 of NRS 704.741.

6. Any order issued by the Commission accepting an element of an emissions reduction and capacity replacement plan must include provisions authorizing the electric utility to construct or acquire and own electric generating plants necessary to meet the capacity amounts approved in, and carry out the provisions of, the plan. As used in this subsection, “capacity” means an amount of firm electric generating capacity used by the electric utility for the purpose of preparing a plan filed with the Commission pursuant to NRS 704.736 to 704.754, inclusive.

(Added to NRS by 1983, 887; A 1989, 1014; 2007, 1774; 2009, 994; 2013, 3085)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.