2011 Nevada Revised Statutes
Chapter 704 - Regulation of Public Utilities Generally
NRS 704.746 - Public hearing on adequacy of plan; determination by Commission.


NV Rev Stat § 704.746 (2011) What's This?

1. After a utility has filed its plan pursuant to NRS 704.741, the Commission shall convene a public hearing on the adequacy of the plan.

2. The Commission shall determine the parties to the public hearing on the adequacy of the plan. A person or governmental entity may petition the Commission for leave to intervene as a party. The Commission must grant a petition to intervene as a party in the hearing if the person or entity has relevant material evidence to provide concerning the adequacy of the plan. The Commission may limit participation of an intervener in the hearing to avoid duplication and may prohibit continued participation in the hearing by an intervener if the Commission determines that continued participation will unduly broaden the issues, will not provide additional relevant material evidence or is not necessary to further the public interest.

3. In addition to any party to the hearing, any interested person may make comments to the Commission regarding the contents and adequacy of the plan.

4. After the hearing, the Commission shall determine whether:

(a) The forecast requirements of the utility are based on substantially accurate data and an adequate method of forecasting.

(b) The plan identifies and takes into account any present and projected reductions in the demand for energy that may result from measures to improve energy efficiency in the industrial, commercial, residential and energy producing sectors of the area being served.

(c) The plan adequately demonstrates the economic, environmental and other benefits to this State and to the customers of the utility, associated with the following possible measures and sources of supply:

(1) Improvements in energy efficiency;

(2) Pooling of power;

(3) Purchases of power from neighboring states or countries;

(4) Facilities that operate on solar or geothermal energy or wind;

(5) Facilities that operate on the principle of cogeneration or hydrogeneration;

(6) Other generation facilities; and

(7) Other transmission facilities.

5. The Commission may give preference to the measures and sources of supply set forth in paragraph (c) of subsection 4 that:

(a) Provide the greatest economic and environmental benefits to the State;

(b) Are consistent with the provisions of this section; and

(c) Provide levels of service that are adequate and reliable.

6. The Commission shall:

(a) Adopt regulations which determine the level of preference to be given to those measures and sources of supply; and

(b) Consider the value to the public of using water efficiently when it is determining those preferences.

7. The Commission shall:

(a) Consider the level of financial commitment from developers of renewable energy projects in each renewable energy zone, as designated pursuant to subsection 2 of NRS 704.741; and

(b) Adopt regulations establishing a process for considering such commitments including, without limitation, contracts for the sale of energy, leases of land and mineral rights, cash deposits and letters of credit.

(Added to NRS by 1983, 887; A 1989, 1607; 1991, 524; 2007, 1773; 2009, 993, 1323)

Disclaimer: These codes may not be the most recent version. Nevada may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.