76-3307 Pipeline carrier; reclamation actions required within thirty days; exception.

NE Code § 76-3307 (2016) What's This?

76-3307. Pipeline carrier; reclamation actions required within thirty days; exception.

A pipeline carrier shall complete final grading, topsoil replacement, installation of erosion control structures, seeding, and mulching within thirty days after backfill except when weather conditions, extenuating circumstances, or unforeseen developments do not permit the work to be done within such thirty-day period.

Source

  • Laws 2012, LB845, ยง 4.

Disclaimer: These codes may not be the most recent version. Nebraska may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.