Section 141.1514a — Consent agreement; continuing operations plan; form; approval; compliance reports; recovery plan; annual updates; terms and provisions; appointment of local auditor or inspector; effect on budget and general appropriations ordinance; grant of certain powers to local government officers; retention of consultant; release from requirements.


MI Comp L § 141.1514a (2012 through Reg Sess) What's This?

LOCAL GOVERNMENT AND SCHOOL DISTRICT FISCAL ACCOUNTABILITY ACT (EXCERPT)
Act 4 of 2011

***** THIS SECTION IS SUSPENDED PENDING THE VOTE OF THE ELECTORS REGARDING PROPOSAL 1 AT THE NOVEMBER 2012 ELECTION *****



141.1514a Consent agreement; continuing operations plan; form; approval; compliance reports; recovery plan; annual updates; terms and provisions; appointment of local auditor or inspector; effect on budget and general appropriations ordinance; grant of certain powers to local government officers; retention of consultant; release from requirements.

Sec. 14a.

(1) A consent agreement as provided in section 13(1)(c) may require a continuing operations plan or a recovery plan if required by the state financial authority.

(2) If the state treasurer requires that a consent agreement include a continuing operations plan, the local government shall prepare and file the continuing operations plan with the state treasurer as provided for in the consent agreement. The state financial authority shall approve or reject the initial continuing operations plan within 14 days of receiving it from the local government. If a plan is rejected, the local government shall refile an amended plan within 30 days of the rejection addressing any concerns raised by the state financial authority. If the amended plan is rejected, then the local government is considered to be in material breach of the consent agreement. The local government is required to file annual updates to its continuing operations plan. The annual updates shall be included with the annual filing of the local government's audit report with the state financial authority as long as the continuing operations plan remains in effect.

(3) The continuing operations plan shall be in a form prescribed by the state financial authority, but shall, at a minimum, include all of the following:

(a) A detailed projected budget of revenues and expenditures over not less than 3 fiscal years which demonstrates that the local government's expenditures will not exceed its revenues and that any existing deficits will be eliminated during the projected budget period.

(b) A cash flow projection for the budget period.

(c) An operating plan for the budget period that assures fiscal accountability for the local government.

(d) A plan showing reasonable and necessary maintenance and capital expenditures so as to assure the local government's fiscal accountability.

(e) An evaluation of the costs associated with pension and postemployment health care obligations for which the local government is responsible and a plan for how those costs will be addressed within the budget period.

(f) A provision for submitting quarterly compliance reports to the state financial authority demonstrating compliance with the continuing operations plan.

(4) If a continuing operations plan is approved for a municipal government, the municipal government shall amend the budget and general appropriations ordinance adopted by the municipal government under the uniform budgeting and accounting act, 1968 PA 2, MCL 141.421 to 141.440a, to the extent necessary or advisable to give full effect to the continuing operations plan. If a continuing operations plan is approved for a school district, the school district shall amend the budget adopted by the school district under the uniform budgeting and accounting act, 1968 PA 2, MCL 141.421 to 141.440a, to the extent necessary or advisable to give full effect to the continuing operations plan. The chief administrative officer, the chief financial officer, the governing body, and other officials of the local government shall take and direct such actions as may be necessary or advisable to maintain the local government's operations in compliance with the continuing operations plan.

(5) If the state financial authority requires that a consent agreement include a recovery plan, the state financial authority shall develop and adopt, in consultation with the review team if desired by the state financial authority, a recovery plan. If a recovery plan is developed and adopted for the local government, the local government thereafter is required to file annual updates to its recovery plan. The annual updates shall be included with the annual filing of the local government's audit report with the state financial authority as long as the recovery plan remains in effect.

(6) A recovery plan may include terms and provisions as may be approved in the discretion of the state treasurer, including, but not limited to, any 1 or more of the following:

(a) A detailed projected budget of revenues and expenditures over not less than 3 fiscal years which demonstrates that the local government's expenditures will not exceed its revenues and that any existing deficits will be eliminated during the projected budget period.

(b) A cash flow projection for the budget period.

(c) An operating plan for the budget period that assures fiscal accountability for the local government.

(d) A plan showing reasonable and necessary maintenance and capital expenditures so as to assure the local government's fiscal accountability.

(e) An evaluation of costs associated with pension and postemployment health care obligations for which the local government is responsible and a plan for how those costs will be addressed to assure that current obligations are met and that steps are taken to reduce future unfunded obligations.

(f) Procedures for cash control and cash management, including, but not limited to, procedures for timely collection, securing, depositing, balancing, and expending of cash, and may include the designation of appropriate fiduciaries.

(g) A provision for submitting quarterly compliance reports to the state financial authority and the chief administrative officer of the local government that demonstrates compliance with the recovery plan.

(7) The recovery plan may include the appointment of a local auditor or local inspector, or both, in accordance with section 19(1)(p).

(8) If a recovery plan is developed and adopted by the state financial authority for a local government, the recovery plan shall supersede the budget and general appropriations ordinance adopted by the local government under the uniform budgeting and accounting act, 1968 PA 2, MCL 141.421 to 141.440a, and the budget and general appropriations ordinance is considered amended to the extent necessary or advisable to give full effect to the recovery plan. In the event of any inconsistency between the recovery plan and the budget or general appropriations ordinance, the recovery plan shall control. The chief administrative officer, the chief financial officer, the governing body, and other officers of the local government shall take and direct actions as may be necessary or advisable to bring and maintain the local government's operations in compliance with the recovery plan.

(9) Except as otherwise provided in this subsection, the consent agreement may include a grant to the chief administrative officer, the chief financial officer, the governing body, or other officers of the local government by the state treasurer of 1 or more of the powers prescribed for emergency managers in section 19 for such periods and upon such terms and conditions as the state treasurer considers necessary or convenient, in the state treasurer's discretion to enable the local government to achieve the goals and objectives of the consent agreement. However, the consent agreement shall not include a grant to the chief administrative officer, the chief financial officer, the governing body, or other officers of the local government of the powers prescribed for emergency managers in section 19(1)(k).

(10) Unless the state treasurer determines otherwise, beginning 30 days after the date a local government enters into a consent agreement under this act, that local government is not subject to section 15(1) of 1947 PA 336, MCL 423.215, for the remaining term of the consent agreement.

(11) The consent agreement may provide for the required retention by the local government of a consultant for the purpose of assisting the local government to achieve the goals and objectives of the consent agreement.

(12) A local government is released from the requirements under this section upon compliance with the consent agreement as determined by the state financial authority.


History: 2011, Act 4, Imd. Eff. Mar. 16, 2011


Disclaimer: These codes may not be the most recent version. Michigan may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.