§ 7-207 - Generating stations or transmission lines -- General certification procedure


MD Pub Util Code § 7-207 (2013) What's This?

§7-207.

(a) (1) (i) In this section and § 7-208 of this subtitle, “construction” means:

1. any physical change at a site, including fabrication, erection, installation, or demolition; or

2. the entry into a binding agreement or contractual obligation to purchase equipment exclusively for use in construction in the State or to undertake a program of actual construction in the State which cannot be canceled or modified without substantial loss to the owner or operator of the proposed generating station.

(ii) “Construction” does not include a change that is needed for the temporary use of a site or route for nonutility purposes or for use in securing geological data, including any boring that is necessary to ascertain foundation conditions.

(2) In this section, “qualified generator lead line” means an overhead transmission line that is designed to carry a voltage in excess of 69,000 volts and would allow an out-of-state Tier 1 or Tier 2 renewable source to interconnect with a portion of the electric system in Maryland that is owned by an electric company.

(b) (1) (i) Unless a certificate of public convenience and necessity for the construction is first obtained from the Commission, a person may not begin construction in the State of:

1. a generating station; or

2. a qualified generator lead line.

(ii) If a person obtains Commission approval for construction under § 7-207.1 of this subtitle, the Commission shall exempt a person from the requirement to obtain a certificate of public convenience and necessity under this section.

(iii) Notwithstanding subparagraph (i) of this paragraph, a person may not apply to obtain a certificate of public convenience and necessity for construction of a qualified generator lead line unless:

1. at least 90 days before the filing of an application for a certificate of public convenience and necessity, the person had in good faith offered the electric company that owns that portion of the electric grid in Maryland to which the qualified generator lead line would interconnect a full and fair opportunity for the electric company to construct the qualified generator lead line; and

2. at any time at least 10 days before the filing of an application for a certificate of public convenience and necessity, the electric company:

A. did not accept from the person a proposal or a negotiated version of the proposal under which the electric company would construct the qualified generator lead line; or

B. stated in writing that the electric company did not intend to construct the qualified generator lead line.

(2) Unless a certificate of public convenience and necessity for the construction is first obtained from the Commission, and the Commission has found that the capacity is necessary to ensure a sufficient supply of electricity to customers in the State, a person may not exercise a right of condemnation in connection with the construction of a generating station.

(3) (i) Except as provided in paragraph (4) of this subsection, unless a certificate of public convenience and necessity for the construction is first obtained from the Commission, an electric company may not begin construction of an overhead transmission line that is designed to carry a voltage in excess of 69,000 volts or exercise a right of condemnation with the construction.

(ii) For construction related to an existing overhead transmission line, the Commission may waive the requirement in subparagraph (i) of this paragraph for good cause.

(4) (i) Except as provided in subparagraph (ii) of this paragraph, for construction related to an existing overhead transmission line designed to carry a voltage in excess of 69,000 volts, the Commission shall waive the requirement to obtain a certificate of public convenience and necessity if the Commission finds that the construction does not:

1. require the electric company to obtain new real property or additional rights-of-way through eminent domain; or

2. require larger or higher structures to accommodate:

A. increased voltage; or

B. larger conductors.

(ii) 1. For construction related to an existing overhead transmission line, including repairs, that is necessary to avoid an imminent safety hazard or reliability risk, an electric company may undertake the necessary construction.

2. Within 30 days after construction is completed under subsubparagraph 1 of this subparagraph, an electric company shall file a report with the Commission describing the work that was completed.

(c) (1) On receipt of an application for a certificate of public convenience and necessity under this section, the Commission shall provide notice to the Department of Planning and to all other interested persons.

(2) The Department of Planning shall forward the application to each appropriate State unit and unit of local government for review, evaluation, and comment regarding the significance of the proposal to State, area-wide, and local plans or programs.

(d) (1) The Commission shall provide an opportunity for public comment and hold a public hearing on the application for a certificate of public convenience and necessity in each county and municipal corporation in which any portion of the construction of a generating station, an overhead transmission line designed to carry a voltage in excess of 69,000 volts, or a qualified generator lead line is proposed to be located.

(2) The Commission shall hold the public hearing jointly with the governing body of the county or municipal corporation in which any portion of the construction of the generating station, overhead transmission line, or qualified generator lead line is proposed to be located, unless the governing body declines to participate in the hearing.

(3) Once in each of the 4 successive weeks immediately before the hearing date, the Commission shall provide weekly notice of the public hearing and an opportunity for public comment by advertisement in a newspaper of general circulation in the county or municipal corporation affected by the application.

(4) (i) The Commission shall ensure presentation and recommendations from each interested State unit, and shall allow representatives of each State unit to sit during hearing of all parties.

(ii) The Commission shall allow each State unit 15 days after the conclusion of the hearing to modify the State unit’s initial recommendations.

(e) The Commission shall take final action on an application for a certificate of public convenience and necessity only after due consideration of:

(1) the recommendation of the governing body of each county or municipal corporation in which any portion of the construction of the generating station, overhead transmission line, or qualified generator lead line is proposed to be located; and

(2) the effect of the generating station, overhead transmission line, or qualified generator lead line on:

(i) the stability and reliability of the electric system;

(ii) economics;

(iii) esthetics;

(iv) historic sites;

(v) aviation safety as determined by the Maryland Aviation Administration and the administrator of the Federal Aviation Administration;

(vi) when applicable, air and water pollution; and

(vii) the availability of means for the required timely disposal of wastes produced by any generating station.

(f) For the construction of an overhead transmission line, in addition to the considerations listed in subsection (e) of this section, the Commission shall take final action on an application for a certificate of public convenience and necessity only after due consideration of the need to meet existing and future demand for electric service.

(g) (1) The Commission may not authorize, and an electric company may not undertake, the construction of an overhead transmission line that is aligned with and within 1 mile of either end of a public airport runway, unless:

(i) the Federal Aviation Administration determines that the construction of an overhead transmission line will not constitute a hazard to air navigation; and

(ii) the Maryland Aviation Administration concurs in that determination.

(2) A privately owned airport runway shall qualify as a public airport runway under this subsection only if the runway has been on file with the Federal Aviation Administration for at least 2 years as being open to the public without restriction.

§ 7-207 - 1. Generating stations or transmission lines -- On-site generated electricity; approval process

(a) Application. -- This section applies to a person who:

(1) constructs a generating station:

(i) designed to provide on-site generated electricity if:

1. the capacity of the generating station does not exceed 70 megawatts; and

2. the electricity that may be exported for sale from the generating station to the electric system is sold only on the wholesale market pursuant to an interconnection, operation, and maintenance agreement with the local electric company; or

(ii) that produces electricity from wind if:

1. the generating station is land-based;

2. the capacity of the generating station does not exceed 70 megawatts;

3. the electricity that may be exported for sale from the generating station to the electric system is sold only on the wholesale market pursuant to an interconnection, operation, and maintenance agreement with the local electric company;

4. the Commission provides an opportunity for public comment at a public hearing as provided in subsection (e) of this section; and

5. the generating station's wind turbines are not located within a distance from the Patuxent River Naval Air Station that is determined by regulations adopted by the Commission in coordination with the Commander, Naval Air Warfare Center Aircraft Division, provided that the distance requirement under the regulation is:

A. not greater than is necessary to encompass an area in which utility scale wind turbines could create Doppler radar interference for missions at the Patuxent River Naval Air Station;

B. not greater than 46 miles, measured from location 38.29667N, 76.37668W; and

C. subject to modification if necessary to reflect changes in missions or technology at the Patuxent River Naval Air Station or changes in wind energy technology; or

(2) constructs a generating station if:

(i) the capacity of the generating station does not exceed 25 megawatts;

(ii) the electricity that may be exported for sale from the generating station to the electric system is sold only on the wholesale market pursuant to an interconnection, operation, and maintenance agreement with the local electric company; and

(iii) at least 10% of the electricity generated at the generating station each year is consumed on-site.

(b) Requirements. --

(1) The Commission shall require a person that is exempted from the requirement to obtain a certificate of public convenience and necessity to obtain approval from the Commission under this section before the person may construct a generating station described in subsection (a) of this section.

(2) An application for approval under this section shall:

(i) be made to the Commission in writing on a form adopted by the Commission;

(ii) be verified by oath or affirmation; and

(iii) contain information that the Commission requires, including:

1. proof of compliance with all applicable requirements of the independent system operator; and

2. a copy of an interconnection, operation, and maintenance agreement between the generating station and the local electric company.

(c) Review of applications. -- When reviewing an application for approval under this section, the Commission shall:

(1) ensure the safety and reliability of the electric system;

(2) require the person constructing the generating station to notify the Commission 2 weeks before the first export of electricity from a generating station approved under this section; and

(3) conduct its review and approval in an expeditious manner.

(d) Waiver. -- The Commission may waive an element of the approval process under this section if the Commission determines that the waiver is in the public interest.

(e) Public comment, notice, and hearing. --

(1) The Commission shall provide an opportunity for public comment and hold a public hearing as provided under this subsection on an application for approval made under subsection (a)(1)(ii) of this section in each county and municipal corporation in which any portion of the construction of a generating station is proposed to be located.

(2) Upon the request of the governing body of a county or municipal corporation in which any portion of the construction of a generating station is proposed to be located, the Commission shall hold the public hearing jointly with the governing body.

(3) Once in each of 2 successive weeks immediately before the hearing date, the Commission, at the expense of the applicant, shall provide weekly notice of the public hearing and opportunity for public comment by advertisement in a newspaper of general circulation in the county or municipal corporation affected by the application.

Disclaimer: These codes may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.