§7-202.

(a) If the Commission determines that a site is needed, the Commission, on its own motion, may request the Secretary of Natural Resources to purchase a power plant site as provided in Title 3, Subtitle 3 of the Natural Resources Article.

(b) In determining whether a need exists for the State to purchase a power plant site, the Commission shall consider:

(1) the suitability of sites owned by an electric company, both within and outside the State;

(2) the anticipated growth of electric power demand and the alternative means and locations for meeting that demand, both within and outside the State; and

(3) any other factors required by law.

(c) (1) The Commission may determine that a power plant site is needed only after the Commission gives public notice and holds a public hearing.

(2) The hearing shall be held in the legislative district in which the site under consideration is located.

Disclaimer: These codes may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.