§ 12-605 - Electrical inspection certificates


MD Pub Safety Code § 12-605 (2013) What's This?

§12-605.

(a) Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut-in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.

(b) Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.

Disclaimer: These codes may not be the most recent version. Maryland may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.