2012 Maine Revised Statutes
TITLE 35-A: PUBLIC UTILITIES (HEADING: PL 1987, c. 141, Pt. A, @6 (new))
Chapter 45: NATURAL GAS PIPELINE UTILITIES
35-A §4503. Filing certificate of public convenience


35-A ME Rev Stat § 4503 (2012 through 125th Legis) What's This?

Part 4: GAS HEADING: PL 1987, C. 141, PT. A, §6 (NEW)

§4503. Filing certificate of public convenience

At least 30 days before beginning construction of an interstate natural gas pipeline within this State, the corporation shall file with the Secretary of State a certified copy of the certificate of public convenience and necessity issued to it under the Federal Natural Gas Act or, if the pipeline is intrastate, a certificate exhibiting the commission's authorization. [1987, c. 141, Pt. A, §6 (NEW).]

SECTION HISTORY

1987, c. 141, §A6 (NEW).

Disclaimer: These codes may not be the most recent version. Maine may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.