350.445 Steep-slope strip mining -- Performance standards -- Conditions for
disturbing land above highwall for road construction.
The following performance standards shall be applicable to steep-slope strip mining and
shall be in addition to those general performance standards required by KRS 350.405 to
350.435; provided, however, that the provisions of this section shall not apply to those
situations in which a permittee or operator is mining on flat or gently rolling terrain, on
which an occasional steep slope is encountered through which the mining operation is to
proceed, leaving a plain or predominantly flat area, or where a permittee or operator is in
compliance with the provisions of KRS 350.450(2):
(1) The permittee or operator shall insure that when performing strip mining on steep
slopes, debris, abandoned or disabled equipment, spoil material, or waste mineral
matter not be placed on the downslope below the bench or mining cut; provided,
that spoil material in excess of that required for the reconstruction of the
approximate original contour under the provisions of KRS 350.410 or 350.445(2)
shall be permanently stored pursuant to KRS 350.440.
(2) The permittee or operator shall complete backfilling with spoil material and shall be
required to cover completely the highwall and return the site to the approximate
original contour, which material will maintain stability following mining and
reclamation.
(3) The permittee or operator may not disturb land above the top of the highwall unless
the cabinet finds that the disturbance will facilitate compliance with the
environmental protection standards of this subsection; provided, however, that the
land disturbed above the highwall shall be limited to that amount necessary to
facilitate compliance. The land above the highwall may be disturbed for
construction of a permanent road only where the applicant affirmatively
demonstrates, and the cabinet makes a detailed and written determination, that the
proposed disturbance facilitates compliance with this chapter and provided that the
land disturbed shall be limited to that amount necessary to facilitate such
compliance. The cabinet shall make this determination upon a demonstration by the
permittee that:
(a) The permittee will completely eliminate the production highwall and backfill
the mined areas to approximate original contour with no road remaining on
the bench;
(b) The road will be placed on a solid base rather than on fill material and
drainage will be diverted from the mining area;
(c) The road will comply with all applicable design criteria, including a drainage
plan for avoiding seepage or uncontrolled discharge of water into the
backfilled areas;
(d) The spoil calculations and spoil disposal plans include the road cut material
and the extent, if any, that road cut material will be used to eliminate a
production highwall;
(e) The road will connect to another road or roads and is necessary in order to
support the approved postmining land uses;
(f)
(4)
Where practical and feasible, an undisturbed barrier will be left between the
production highwall and the road itself. When an undisturbed barrier is not
feasible, witness monuments will be left at a minimum of two (2) locations
above the production highwall;
(g) The road will be constructed to a size and design appropriate to the proposed
post-mining land use;
(h) The proposed mine plan and sequencing of the road construction in relation to
the mining activity will minimize placement of spoil material into valley or
hollow fills and will maximize permanent retention of mined spoil on the
mine bench;
(i) There will be no coal removal from the construction of the permanent road
except for incidental nonmerchantable coal that is disposed of in an approved
manner; and
(j) All other performance standards of the chapter are met.
For the purposes of this section, the term "steep slope" is any slope above twenty
(20) degrees or such lesser slope as may be defined by the cabinet, by regulation,
after consideration of soil, climate, and other characteristics of the region.
Effective: July 12, 2006
History: Amended 2006 Ky. Acts ch. 37, sec. 5, effective July 12, 2006. -- Amended
2000 Ky. Acts ch. 367, sec. 1, effective July 14, 2000. -- Amended 1992 Ky. Acts
ch. 429, sec. 32, effective July 14, 1992. -- Created 1978 Ky. Acts ch. 330, sec. 10,
effective May 3, 1978.
Disclaimer: These codes may not be the most recent version. Kentucky may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.