Section 68-411 Partial payment on contracts; regulations for withholding.


KS Stat § 68-411 (2012) What's This?

68-411. Partial payment on contracts; regulations for withholding. The secretary of transportation shall make partial payment to a contractor performing any road or bridge work under contract with it, as the work may progress, said partial payment not to be less than ninety percent (90%) of the contract price of the material delivered and work done and accepted. The secretary shall provide by regulation, to be made a part of all specifications, for the withholding of not more than ten percent (10%) of the full contract price of any such work until the work is satisfactorily completed and approved by the secretary and the provisions of the contract and bond therefor have been fully satisfied.

Disclaimer: These codes may not be the most recent version. Kansas may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.