2012 Idaho Statutes
Title 45 - LIENS, MORTGAGES AND PLEDGES
Chapter 5 - LIENS OF MECHANICS AND MATERIALMEN
Section 45-507 - CLAIM OF LIEN.
(2) The claim shall be filed within ninety (90) days after the completion of the labor or services, or furnishing of materials.
(3) The claim shall contain:
(4) Such claim must be verified by the oath of the claimant, his agent or attorney, to the effect that the affiant believes the same to be just.
(5) A true and correct copy of the claim of lien shall be served on the owner or reputed owner of the property either by delivering a copy thereof to the owner or reputed owner personally or by mailing a copy thereof by certified mail to the owner or reputed owner at his last known address. Such delivery or mailing shall be made no later than five (5) business days following the filing of said claim of lien.
History:
[(45-507) 1893, p. 49, ch. 1, sec. 6; am. 1895, p. 48, ch. 1, sec. 6; reen. 1899, p. 147, ch. 1, sec. 6; reen. R.C. & C.L., sec. 5115; C.S., sec. 7346; I.C.A., sec. 44-507; am. 1971, ch. 91, sec. 5, p. 196; am. 1983, ch. 127, sec. 1, p. 324; am. 1993, ch. 378, sec. 1, p. 1387; am. 2001, ch. 152, sec. 5, p. 552; am. 2002, ch. 307, sec. 1, p. 876.]
Disclaimer: These codes may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.