Section 42-2942 - COMMENCEMENT AND PROGRESS OF WORK.


ID Code § 42-2942 (2012) What's This?

42-2942. Commencement and progress of work. The work on said improvement shall begin at a point or at points to be determined by said commissioners, and said work shall be completed with all expedition possible, and said board of commissioners of such drainage district, or any contractor thereunder, shall have no power whatever to change such route or system of improvements or the manner of doing the work therein so as to make any radical changes in said improvements, without the written consent of all of the landowners to be benefited thereby, and of the landowners who may be damaged thereby.


History:

[(42-2942) 1913, ch. 16, part of sec. 19, p. 58; reen. C.L. 168:39; C.S., sec. 4533; I.C.A., sec. 41-2542.]

Disclaimer: These codes may not be the most recent version. Idaho may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.