2014 Connecticut General Statutes
Title 4a - Administrative Services
Chapter 58 - Purchases and Printing
Section 4a-60j - (Formerly Sec. 32-9h). Time for payment of contractors.

CT Gen Stat § 4a-60j (2014) What's This?

A small contractor shall receive payment on a contract awarded to him under the provisions of sections 4a-60g to 4a-60i, inclusive, no later than thirty days from the due date of any such payment on such contract.

(P.A. 77-425, S. 4.)

History: Sec. 32-9h transferred to Sec. 4a-60j in 2001.

Disclaimer: These codes may not be the most recent version. Connecticut may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.