28-6806. Toll road construction and completion
A. Construction of the toll road shall begin within thirty days after the date of the order approving the application and shall continue with all reasonable dispatch until completed.
B. When the road is completed, the owner of the franchise shall file with the county recorder a certificate that the road is completed and conforms to the requirements of law.
Disclaimer: These codes may not be the most recent version. Arizona may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.