In re Vermont Electric Power Co., Inc.

Annotate this Case
In Vermont Electric Power Co. (2005-164); 179 Vt. 370; 895 A.2d 226

2006 VT 69

[Filed 10-Mar-2006]

  NOTICE:  This opinion is subject to motions for reargument under
  V.R.A.P. 40 as well as formal revision before publication in the Vermont
  Reports.  Readers are requested to notify the Reporter of Decisions,
  Vermont Supreme Court, 109 State Street, Montpelier, Vermont 05609-0801 of
  any errors in order that corrections may be made before this opinion goes
  to press.


                                 2006 VT 21

                                No. 2005-164


In re Petitions of Vermont Electric Power Company, Inc.  Supreme Court
and Green Mountain Power Corporation
                                                         On Appeal from
                                                         Public Service Board


                                                         November Term, 2005 


  Michael H. Dworkin, Chair

  Joseph S. McLean and Robert E. Fletcher of Stitzel, Page & Fletcher, P.C.,
  and Thomas A. Little of Little & Cicchetti, P.C., Burlington, for Appellant
  Town of Shelburne.

  James A. Dumont, Bristol, for Appellants Town of New Haven, Town of
  Middlebury and  Addison County Regional Planning Commission.

  David L. Grayck of Cheney, Brock & Saudek, P.C., Montpelier, for Appellant
  Meach Cove Real Estate Trust.

  Aaron Adler and Dixie Henry, Special Counsel, Montpelier, for Appellee
  Department of Public Service. 

  Kimberly K. Hayden and Elijah D. Emerson of Primmer & Piper, P.C., St.
  Johnsbury, for Appellees Vermont Electric Power Company and Green Mountain
  Power Corporation.


  PRESENT:     Reiber, C.J., Skoglund and Burgess, JJ., and Gibson, J.
               (Ret.) and Bryan, Supr. J. (Ret.), Specially Assigned

        
       ¶  1.     SKOGLUND, J.   In this case we consider three appeals from a
  Public Service Board order granting a certificate of public good for a
  proposal by Vermont Electric Power Company (VELCO) and Green Mountain Power
  (GMP) to construct a series of electric transmission upgrades known
  collectively as the Northwest Reliability Project.  Appellants the Town of
  New Haven, the Town of Middlebury, and the Addison County Regional Planning
  Commission (FN1) jointly contend the Board erroneously: (1) approved a
  345-kilovolt (kv) transmission line for a portion of the project instead of
  a less intrusive but allegedly adequate 115-kv line; (2) misstated and
  ignored relevant evidence concerning electromagnetic fields generated by
  the 345-kv transmission line; (3) failed to consider a proposal to
  underground the line in an environmentally sensitive location in the Town
  of New Haven; and (4) prejudiced landowners in future eminent domain
  proceedings by approving VELCO's specific plans. Appellant Town of
  Shelburne (Shelburne) claims that the Board improperly failed to: (1)
  identify a specific southerly route for the proposed transmission line
  through the Town; (2) address the aesthetic impacts of the proposed line;
  (3) consider land conservation measures in the Town plan; and (4) make a
  final determination of VELCO's responsibility to underground a portion of
  the line.  Appellant Meach Cove Real Estate Trust (Meach Cove) argues that
  the Board violated statutory requirements and settled case law by: (1)
  mandating a specific route for the proposed transmission line over its
  property; (2) depriving it of the opportunity to contest key issues in
  future eminent domain proceedings; (3) denying its request for a
  declaration that issuance of the certificate of public good will not have a
  preclusive effect in subsequent eminent domain proceedings; and (4) failing
  to consider alternative sites for construction of the proposed line.  For
  the reasons set forth below, we affirm the Board's decision.  
   
       ¶  2.     In June 2003, VELCO and GMP (hereafter, collectively
  "VELCO") filed petitions with the Board seeking a certificate of public
  good (CPG) for a set of transmission upgrades in the northwestern portion
  of the State.  See 30 V.S.A. § 248(a) (providing that no electric company
  may begin site preparation or construction of electric generation or
  transmission facility, or exercise the right of eminent domain in
  connection therewith, unless the Board "first finds that the same will
  promote the general good and issues a certificate to that effect").  In its
  petition, VELCO asserted that projected increases in electric demand in
  northwestern Vermont, measured against certain national and regional
  operating standards, made it imperative to strengthen the transmission grid
  serving the area in order to maintain desirable levels of reliability.  To
  this end, VELCO proposed five basic upgrades: (1) the construction of a new
  35.5-mile, 345-kv transmission line from West Rutland to New Haven,
  parallel to an existing 115-kv line passing through a number of towns,
  including appellants Middlebury and New Haven; (2) replacement of existing
  34.5-kv and 46-kv subtransmission lines with a new 27-mile, 115-kv line
  between New Haven and South Burlington passing though portions of several
  additional towns, including appellant Shelburne; (3) the reconductoring of
  VELCO's existing 5.6-mile, 115-kv transmission line between Williamstown
  and Barre; (4) upgrades to, or reconstruction of, a number of substations
  throughout the northwest region; and (5) construction of a new substation
  and associated 1.6-mile subtransmission line in Vergennes. 
   
       ¶  3.     During thirty-seven days of public and technical hearings
  that spanned most of a year, the Board took extensive and wide-ranging
  testimony and documentary evidence concerning the project from expert and
  lay witnesses representing several dozen parties.  See id. § 248(a)(4)
  (requiring the Board to hold both "nontechnical" public hearings in
  counties affected by the proposal and "technical" hearings at locations of
  its choice).  The hearings addressed both general and site-specific issues
  relating to the statutory criteria for issuance of a CPG under § 248(b),
  including the project's consistency with "land conservation measures"
  contained in local municipal plans, id. § 248(b)(1); its necessity to meet
  present and future demand for service that could not otherwise be met "in a
  more cost effective manner through energy conservation programs and
  measures and energy efficiency and load management measures," id. §
  248(b)(2); its "economic benefit to the state and its residents," id. §
  248(b)(4); and whether it would "have an undue adverse effect on esthetics,
  historic sites, air and water purity, the natural environment and the
  public health and safety, with due consideration having been given to"
  several of the statutory criteria for protection of the environment set
  forth in Act 250, id. § 248(b)(5).   Appellants participated actively in
  the hearings, offering evidence to support their views on the best means to
  protect the aesthetic, health, environmental, and economic interests of
  their communities.(FN2)
   
       ¶  4.     At the conclusion of the process, the Board issued a written
  order spanning over 240 pages, including appendices, and containing over
  640 findings in support of its conclusions.  In brief, the Board determined
  that: the current bulk transmission system fails to meet reliability
  standards; the proposed project will enable the system to satisfy Vermont's
  reasonably projected reliability needs; and "there is no cost-effective
  alternative to the proposed Project that is reasonably assured of timely
  implementation."(FN3)  While finding that the project will have adverse
  aesthetic impacts in certain areas, the Board concluded that mitigation
  measures, such as careful pole placement, screening, the relocation of the
  New Haven substation, and undergrounding the line in at least one location
  in Shelburne, will ensure that the impact is not undue.  With respect to
  health and safety concerns, the Board heard substantial testimony and
  reviewed numerous studies concerning electric and magnetic field (EMF)
  exposure.  The Board concluded that the scientific evidence of any health
  risk was weak to nonexistent and provided no justification for imposing
  significant mitigation measures, such as undergrounding the line. 
  Nevertheless, as part of the post-certification process, the Board ordered
  VELCO to identify areas of relatively high EMF levels near residences and
  propose measures to mitigate exposure at those locations, and to monitor
  and regularly report to the Board the scientific evidence regarding the
  health effects of EMF. 

       ¶  5.     In short, the Board concluded that, with certain enumerated
  conditions and alterations, the project would promote the general good of
  the State "without undue adverse impacts on Vermont's natural and built
  environment and without presenting a risk to Vermonters' health and
  safety."  Consistent with these findings, the Board issued a CPG containing
  twenty separate conditions, including a graduated post-certification
  process that will require: (1) the identification of areas of high EMF
  levels near residences, together with measures to mitigate the exposure of
  those residences; (2) the filing of detailed construction plans, with
  associated environmental mitigation measures as identified in the Board's
  order; (3) the filing of all required zoning, construction, and other
  permits with the Board; and (4) a showing that consideration has been given
  to all measures identified in the Board's order for the mitigation of
  adverse aesthetic impacts.  Meach Cove and New Haven filed separate motions
  to alter or amend the order, and VELCO filed a request for clarification. 
  The Board ordered several relatively minor language changes and
  clarifications to the decision, but otherwise denied the motions.  Separate
  appeals by New Haven, Shelburne, and Meach Cove followed.  We address each
  in turn.

                                     I.

   
       ¶  6.     We note at the outset the limited nature of our review.  "In
  a § 248 proceeding, the Board 'is engaged in a legislative, policy-making
  process.' " In re Twenty-Four Vt. Utils., 159 Vt. 339, 357, 618 A.2d 1295,
  1306 (1992) (quoting Auclair v. Vt. Elec. Power Co., 133 Vt. 22, 26, 329 A.2d 641, 644 (1974)).  The Board must employ "its discretion to weigh
  alternatives presented to it, utilizing its particular expertise and
  informed judgment." Id.  We "give great deference" to that expertise and
  judgment and accord a "strong presumption" of validity to the Board's
  orders.  In re E. Georgia Cogeneration Ltd. P'ship, 158 Vt. 525, 531, 614 A.2d 799, 803 (1992).  Findings of fact adopted by the Board to support its
  decision must be accepted by the Court unless they are shown to be clearly
  erroneous.  Id.  "The burden of demonstrating clear error is the
  appellant's, and that burden is not a light one."  In re Adelphia Bus.
  Solutions of Vt., Inc., 2004 VT 82, ¶ 7, 177 Vt. 136, 861 A.2d 1078.   
   
       ¶  7.     With these standards in mind, we turn first to New Haven's
  claims on appeal.  New Haven  contends principally that the Board erred in
  approving VELCO's proposal to construct a new 345-kv line from West Rutland
  to New Haven parallel to an existing 115-kv line, instead of approving a
  second 115-kv line along the same route.  The record discloses that the
  Board considered a number of "transmission-only alternatives" to the VELCO
  proposal, including the second 115-kv line, and engaged in a comparative
  analysis of this and other transmission options.  The Board concluded that
  the 115-kv alternative was inferior to the VELCO proposal for several
  reasons.  First, it noted that the 115-kv alternative provided less
  capacity than the 345-kv line to protect against a potential voltage
  collapse resulting from contingencies elsewhere in the transmission system. 
  Second, the 115-kv alternative would produce significantly higher
  "impedance," or conductive losses and inefficiency, than the 345-kv line. 
  Third, the 115-kv line would require adding a second, sixteen-mile, 115-kv
  line from Granite to Middlesex to increase the reliability of the
  alternative to the same reliability as the 345-kv proposal, with associated
  potential environmental impacts to this additional transmission corridor. 
  Finally, the Board found that the 115-kv line would not be compatible with
  VELCO's long-term expansion plans for extending 345-kv lines from New Haven
  to Williston and to a future substation in Essex. 

       ¶  8.     The Board recognized that the transmission poles required
  for a 345-kv line would be higher, and the right-of-way wider, than those
  required for a 115-kv line, and found that these requirements would create
  adverse aesthetic effects at several locations along the route.  The Board
  further found, however, that any undue impacts could be avoided through a
  variety of site-specific mitigation measures, including pole placement,
  planting of hedgerows and trees, and relocation of the line in certain
  areas, and ordered VELCO to incorporate these mitigation measures into the
  project. 

       ¶  9.     Despite these findings, New Haven contends the Board erred
  in failing to conduct a more detailed comparison between the environmental
  and aesthetic impacts of the 345-kv proposal and the 115-kv alternative. 
  This argument is unpersuasive.  Under the two-part "Quechee test" utilized
  by the Board and approved by this Court for reviewing issues of aesthetics
  under § 248(b), a determination must first be made as to whether a project
  will have an adverse impact on the aesthetics and the scenic and natural
  beauty of an area.  In re Halnon, 174 Vt. 514, 515, 811 A.2d 161, 163
  (2002) (mem.).  If the answer is in the affirmative, the inquiry advances
  to the second prong-whether the impact would be "undue."  Id.  This is
  determined by assessing whether it violates a clear community standard, it
  offends the sensibilities of the average person, or the applicant has
  failed to take generally available mitigating steps that a reasonable
  person would take to improve the harmony of the proposed project with its
  surroundings.  Id.  
   
       ¶  10.     New Haven argues that the Board deviated from this
  standard, citing our decision in Halnon, where we upheld a decision by the
  Board to deny a CPG for a proposed wind turbine based, in part, on the
  applicant's failure to take adequate steps to mitigate the adverse impact
  on a neighbor's view or analyze alternative sites that would have provided
  more effective screening.  Id.  at 517, 811 A.2d  at 165.  The record here
  is markedly different.  VELCO proposed a number of measures to mitigate the
  adverse aesthetic effects of the 345-kv line, and the Board found that
  these and other supplemental mitigation measures would negate any undue
  impacts from the line.  Furthermore, unlike in Halnon, where the applicant
  provided no evidence to support his claim that alternative locations would
  cause ancillary problems undermining the project, id., VELCO here adduced
  substantial evidence that the 115-kv line would not adequately accomplish
  the project's goal of providing long-term and reliable energy sufficiency,
  and the Board so found.  Accordingly, we find no legal or factual basis to
  conclude that the Board abused its discretion by failing to conduct an
  adequate comparative analysis of the 115-kv alternative.(FN4)
   
       ¶  11.     New Haven also specifically challenges the Board's reliance
  on evidence that the 115-kv alternative would not be compatible with
  VELCO's long-term plans for extending the proposed 345-kv line from New
  Haven to Williston and to a future substation in Essex, asserting that it
  was error to rely on potential energy needs twenty years in the future. 
  Forecasting future energy needs and the optimal means of addressing those
  needs, however, falls squarely within the Board's informed judgment and
  expertise, and we discern no basis to conclude that the Board's finding in
  this regard was unreasonable or clearly erroneous. In re E. Georgia, 158
  Vt. at 531-32, 614 A.2d  at 803.

       ¶  12.     New Haven also claims that the Board abused its discretion
  in applying a least-cost analysis to the project as a whole, rather than to
  each separate project component, including the proposed 345-kv line and
  115-kv alternative.  See 30 V.S.A. § 248(b)(2) (stating that issuance of
  CPG requires finding that proposed purchase, investment or construction is
  required to meet present and future demand for service "which could not
  otherwise be provided in a more cost effective manner through energy
  conservation programs and measures and energy-efficiency and load
  management measures"); id. § 248(b)(4) (stating that CPG requires finding
  that proposal will result in economic benefit to the state and its people). 
  The Board rejected this argument, noting that, in dealing with similar
  projects, it had consistently addressed the economic and least-cost
  criteria for the projects as a whole rather than for their separate line
  and substation components.  The Board found this to be a reasonable
  approach where, as here, the applicant contends, and the evidence shows,
  that a project should be treated as a coordinated whole due to the
  interconnected nature of the system.(FN5)  With respect to the 345-kv line,
  the Board specifically found that it was an integral component of the
  Northwest Reliability Project, and therefore did not require a separate
  cost-effective analysis.  
   
       ¶  13.     Contrary to New Haven's claim, we discern nothing in the
  language of § 248 that is inconsistent with the Board's approach, or that
  specifically requires a component-by-component least-cost analysis of an
  integrated system-wide transmission upgrade.  New Haven cites to a
  provision of the statute defining a natural gas facility as including "any
  natural gas transmission line," 30 V.S.A. § 248(a)(3)(A), but this section
  does not signal a clear legislative intent to subject virtually every
  proposed gas or electric transmission line or other project component to a
  separate least-cost analysis when it is part of an otherwise integrated
  project.  As the Board's approach under § 248 was neither unreasonable nor
  contrary to the plain terms of the statute, and was well within the scope
  of its expertise, it must be upheld.  See In re Verizon New Eng. Inc., 173
  Vt. 327, 334-35, 795 A.2d 1196, 1202 (2002) (recognizing that absent
  compelling indication of error, we will not disturb Board's interpretation
  of statutes within its particular area of expertise); In re Twenty-Four Vt.
  Utils., 159 Vt. at 359, 618 A.2d  at 1307 (rejecting claim that Board
  violated § 248(b) by conducting "statewide evaluation" of hydroelectric
  energy purchase contract rather than "utility-by-utility assessment," and
  holding that Board's approach under the statute was "reasonable").  New
  Haven also challenges the Board's predicate finding that the proposed
  thirty-five-mile, 345-kv line running through the Champlain Valley from
  West Rutland to New Haven constitutes an integral and essential part of a
  coordinated project to provide reliable energy to meet Vermont's current
  and future energy load levels.  Again, however, the Board's finding was
  supported by the record evidence, and was within its area of expertise, and
  therefore must be upheld.(FN6)  In re E. Georgia, 158 Vt. at 531, 614 A.2d 
  at 803.
   
       ¶  14.     New Haven further contends the Board failed to consider
  relevant evidence, and misstated the evidence, concerning the health risks
  posed by increased EMF levels associated with the project.  The Board's
  decision contains some forty findings reviewing the extensive testimony and
  scientific literature adduced by the parties on the subject of EMF's effect
  on the public health.  This includes a 1999 report by the National
  Institute of Environmental Health Sciences, and a follow-up report in 2002,
  finding that "[t]he scientific evidence suggesting that ELF-EMF [extremely
  low frequency EMF] exposures pose any health risk is weak" and concluding
  that EMF exposure is not likely to pose any health hazard.  The Board found
  that there was no evidence of any substantial linkage between EMF exposure
  and childhood leukemia or other cancer risks, nor any recorded case of
  medical-device disruption caused by power-line EMF.  In the absence of
  evidence of any undue effect on the public health, the Board concluded that
  significant mitigation measures, such as undergrounding the line, were not
  required.  Nevertheless, consistent with the policy of "prudent avoidance"
  followed by the Department of Health and other states, the Board ordered
  VELCO to continue to identify areas of relatively high EMF levels, propose
  options to mitigate exposure in those areas, and monitor the scientific
  literature and regularly report to the Board on these efforts.
   
       ¶  15.     Of the Board's extensive findings in this area, New Haven
  has challenged only those concerning EMF's effect on medical devices,
  asserting that the Board ignored or misunderstood evidence that
  manufacturers routinely warn users of pacemakers, implantable cardioverter
  defibrillators, and insulin pumps that high-voltage lines may interfere
  with their devices, and consequently caution them to avoid such lines.  The
  evidence showed, however, that the manufacturers' warnings were not based
  on studies demonstrating health risks to medical-device users from EMF
  generated by power lines, or documenting any single instance of such
  interference.(FN7)  Thus, the evidence supported the Board's finding that
  EMF from power lines did not pose a tangible risk to medical-device users
  or require significant mitigation measures.  We find no merit to the claim
  that the Board ignored or misstated the evidence in this area, and no basis
  to disturb its findings.(FN8)  Id.
   
       ¶  16.     New Haven next claims that the Board failed to consider
  expert testimony recommending burial of the proposed new 115-kv line
  running from a substantially expanded New Haven substation to the point
  where it crosses Route 17 in the Town of New Haven.   The record does not
  support the claim.  Although it did not specifically mention the Route 17
  crossing, the Board considered the proposal to underground all or part of
  the new line and found that aesthetic considerations did not justify the
  cost of the underground option except in two specific locations in the Town
  of Shelburne.  The Board did, however, reject VELCO's proposed mitigation
  measures as inadequate to negate the adverse aesthetic effects from the
  expanded substation and Route 17 crossing.  Instead, it ordered VELCO to
  consider an option discussed by New Haven's expert landscape architect and
  planner, Jean Vissering, to relocate the expanded substation (at
  considerable additional cost) to allow for better screening.  Vissering
  noted, and the Board found, that relocating the substation would facilitate
  relocating the Route 17 crossing to a lower elevation, which would 
  mitigate its adverse visual impact.  Although Vissering opined that
  undergrounding the line at the Route 17 crossing represented the optimal
  approach, and the Board chair wrote separately to endorse that view, the
  expert acknowledged that-if the Board determined the costs of
  undergrounding to be unreasonable-the relocation option would remove the
  major adverse aesthetic impacts of the original proposal.  The Board's
  decision thus reveals a careful balancing of cost, aesthetic, and technical
  considerations well within its area of expertise, and well supported by the
  evidence.  Accordingly, it may not disturbed.  Id.

       ¶  17.     New Haven additionally contends the Board violated § 248 by
  approving specific locations for the proposed transmission lines.  Nothing
  in the statute, however, prevents the Board from certifying that the
  proposal to construct additional transmission lines, substations, and other
  upgrades in specific locations serves the public good.  The decisions on
  which New Haven relies,  Vt. Elec. Power Co. v. Bandel, 135 Vt. 141, 145,
  375 A.2d 975, 978 (1977), Auclair v. Vt. Elec. Power Co., 133 Vt. 22, 28,
  329 A.2d 641, 645 (1974), and In re Vt. Elec. Power Co., 131 Vt. 427,
  434-435, 306 A.2d 687, 691-92 (1973), held merely that the Board may
  certify a general rather than a specific transmission corridor and retain
  jurisdiction to review more detailed plans through a post-certification
  procedure.  They do not hold that this approach is required.   Accordingly,
  the claim lacks merit.  
   
       ¶  18.     In a related argument, New Haven asserts that, by approving
  certain specific routes, the Board improperly precluded individual
  landowners from challenging the necessity of constructing the lines in
  later condemnation proceedings under 30 V.S.A. §§ 110-112.  As we have
  explained, however, a § 248 certification proceeding "is a planning and
  policy determining [process] which forecloses no individual rights" and
  involves "no predetermination of the issue of necessity of condemnation for
  any particular route."  Auclair, 133 Vt. at 26-27, 329 A.2d  at 644-45.  
  Accordingly, the claim lacks merit.  Lastly, New Haven asserts that the
  Board's certification order violates the principle that findings should
  contain clear statements of fact and identify their basis in the record,
  rather than merely recite testimony or refer to unspecified portions of the
  record.  As our previous discussion suggests, however, the Board's numerous
  and detailed factual findings were extensively supported by specific
  citations to the record evidence.  Thus, we find no error.

                                     II.

       ¶  19.     We turn next to Shelburne's claims.  Shelburne raises four
  issues on appeal.  First, in an inversion of New Haven's earlier argument,
  Shelburne asserts that the Board's findings improperly fail to identify a
  specific route for a portion of the new transmission line through the Town. 
  VELCO's original proposal was to replace approximately 5.6 miles of
  existing 34.5-kv transmission line within the Town with a new 115-kv
  transmission line to be constructed in the existing corridor, and to
  upgrade the existing substation.  The southerly 2.4-mile segment of the
  line runs from the Charlotte border to the substation, passing a
  residential neighborhood known as Davis Park.  The northern segment runs
  from the substation approximately 3.2 miles north.  In response to concerns
  about the impact of larger transmission structures on the Davis Park
  neighborhood, VELCO filed an alternative proposal to shift a portion of the
  southerly route to the west, away from the neighborhood and onto the lands
  of the Meach Cove Trust.  This reroute proposal raised additional
  environmental and aesthetic concerns, which resulted in at least one
  additional reroute proposal, a variation on the second, that also affected
  the Meach Cove Trust property.
   
       ¶  20.     Shelburne asserts that the Board's findings concerning this
  portion of the southern segment are inadequate because, while it is clear
  that the Board implicitly rejected the original route, it is allegedly
  "difficult to determine" which of the alternative routes the Board
  approved.  We find no error.  As Shelburne acknowledges, references in the
  Board's findings to expert testimony concerning the potential aesthetic
  impacts of the line and the mitigation measures necessary to address those
  impacts leave no doubt that the Board chose the alternatives offered by
  VELCO over the original proposal.  The Board's findings also suggest that
  the final location for this portion of the line was to be reserved for the
  post-certification process, as indicated in the following finding: 

       This section of the 115 kv line is sufficiently sensitive
       that it must be planned on paper at a design detail level,
       and then confirmed in the field by a method of testing actual
       proposed pole locations to ensure that existing screening is
       used to the greatest effect possible. . . . 


       VELCO must include the Town and affected landowners in this
       process, including the Meach Cove Real Estate Trust.  

  Pursuant to the post-certification process outlined in the Board's
  decision, the Board will review final design and construction plans
  submitted by VELCO showing specific locations for each transmission
  structure and outlining associated environmental mitigation measures.  The
  Board will also conduct site visits as necessary, and afford Shelburne and
  other parties the opportunity to comment on the final plans, request a
  hearing, and submit additional evidence. 
  
       ¶  21.     As previously discussed, we have long upheld the Board's
  authority to approve a general route for a proposed transmission line in a
  § 248 proceeding, reserving the resolution of difficult aesthetic and
  environmental considerations underlying the more specific decision to a
  post-certification procedure.  In re Vt. Elec. Power Co., 131 Vt. at
  434-35, 306 A.2d  at 691-92.  We find  nothing in the Board's decision here
  that is inconsistent with this approach or objectionable under the statute.  
  Hence, there was no error warranting a reversal and remand.
   
       ¶  22.     Shelburne next contends the Board's findings fail to
  adequately address the aesthetic impacts of the proposed 115-kv
  transmission line along the one-mile section between Bostwick Road and
  Harbor Road, and the half-mile segment from the Bostwick Road Bridge to the
  Meach Cove Trust property.  The Board addressed the aesthetic effects of
  the 115-kv line, both generally and on a section-by-section basis, under
  the Quechee test referred to above.  The Board noted that for most of its
  length the 115-kv line will replace existing lines and will be constructed
  in existing transmission corridors, although wider rights-of-way will be
  required.  The Board also noted the possibility of increased visibility
  resulting from the taller pole heights generally required by the new line. 
  With respect to the Bostwick-Road-to-Harbor-Road section, however, the
  Board found that the use of shorter poles will mitigate the visual impacts
  on the Shelburne Museum and Shelburne Farms.  As noted, the Board also
  observed that the final decision concerning proper pole placement and
  screening for this "sensitive" segment of the line would require more
  detailed planning and field testing.  With respect to the half-mile segment
  from Bostwick Road Bridge to the Meach Cove Trust property, the Board found
  that the adverse aesthetic impacts resulting from the new line would be
  mitigated by a variety of measures, including the use of shorter poles,
  careful pole placement, retention of buffering trees, and the placement of
  additional vegetative screening. 
   
       ¶  23.     Despite these findings, Shelburne contends that the Board's
  analysis was deficient under the Quechee test.  We see no such shortcoming. 
  As noted, the Quechee analysis requires the Board to determine whether a
  project will have an adverse aesthetic impact, and, if so, whether that
  impact is undue, i.e., whether it violates a clear community standard, it
  offends the sensibilities of the average person, or the applicant has
  failed to take reasonably available mitigating measures to improve the
  harmony of the project with its surroundings.  In re Halnon, 174 Vt. at
  515, 811 A.2d  at 163.  Shelburne argues that the Board failed to
  specifically address local community standards dedicated to the protection
  of viewsheds in these areas, but the Board's findings demonstrate that it
  considered the project's impact on views to be a critical concern, and
  further demonstrate that it was satisfied that the prescribed mitigation
  measures would effectively ameliorate these impacts.  Shelburne also faults
  the Board for failing to address the line's effect on views from points
  other than the Shelburne Museum and Shelburne Farms, but the record shows
  that Shelburne's own experts focused principally on these vantage points. 
  Accordingly, we find no error.

       ¶  24.     Finally, Shelburne contends the Board mischaracterized the
  testimony of an expert landscape architect, David Raphael, in concluding
  that the adverse impacts along the segment of the line from Bostwick Road
  Bridge to the Meach Cove Trust property could be effectively mitigated. 
  The expert's testimony fully supports the Board's finding.(FN9)  Shelburne
  notes that the expert later qualified his testimony by acknowledging that
  "sufficient mitigation can be provided if all of those elements [pole
  placement, tree retention, additional screening] are explored to their
  fullest extent," and that this would remain uncertain until more detailed
  plans were in place.  This does not, however, undermine the Board's
  finding, but rather is consistent with its conclusion that final approval
  must await a post-certification review of detailed site-specific plans for
  the location of transmission structures and associated mitigation measures.  
   
       ¶  25.     Shelburne next asserts that the Board misinterpreted its
  statutory obligation to find that any new construction of an in-state
  facility "will not unduly interfere with the orderly development of the
  region with due consideration having been given to the recommendations of
  the municipal and regional planning commissions, the recommendations of the
  municipal legislative bodies, and the land conservation measures contained
  in the plan of any affected municipality."  30 V.S.A. § 248(b)(1).  As the
  Board observed, this Court has construed the phrase "due consideration" in
  § 248(b)(1) to "at least impliedly postulate[] that municipal enactments,
  in the specific area, are advisory rather than controlling," City of S.
  Burlington v. Vt. Elec. Power Co., 133 Vt. 438, 447, 344 A.2d 19, 25
  (1975), and Shelburne takes no issue with this interpretation.  Shelburne
  challenges the Board's corollary conclusion, however, that "land
  conservation measures" must be interpreted to mean measures specifically
  "directed toward land conservation, and not general policy statements that
  apply indiscriminately throughout the municipality."  The Board relied, in
  this regard, on our decisions holding that the Act 250 requirement of
  "conformance with any duly adopted local or regional plan," 10 V.S.A. §
  6086(a)(10), requires a "specific" municipal policy rather than "broad
  goals lacking in specific policies or standards."  In re John A. Russell
  Corp., 2003 VT 93, ¶¶ 16, 19, 176 Vt. 520, 838 A.2d 906 (mem.); accord In
  re Kisiel, 172 Vt. 124, 130, 772 A.2d 135, 140 (2000); In re Molgano, 163
  Vt. 25, 31, 653 A.2d 772, 775 (1994).
   
       ¶  26.      Shelburne argues that while the requirement of
  "conformity" under Act 250 may warrant specificity in local plans, the fact
  that land conservation measures in a § 248 proceeding are only advisory
  suggests that the Board should consider a municipal plan's broad "vision"
  for development rather than apply the more exacting standard under Act 250. 
  VELCO and the Public Service Department argue, in response, that this Court
  generally defers to the Board's interpretation of an enabling statute
  within its particular expertise, and that Shelburne has identified no 
  "compelling indication of error" in the Board's approach.  In re Vt. Yankee
  Nuclear Power Station, 2003 VT 53, ¶ 5, 175 Vt. 368, 829 A.2d 1284. 
  Although the issue is well framed and significant, we find that there is no
  need to address it here.  While Shelburne takes issue with the Board's
  narrow definition of "land conservation measures," it does not argue that
  it was prejudiced by the Board's interpretation, or explain how, if at all,
  a broader approach would have changed the result.  See Mellin v. Flood
  Brook Union Sch. Dist., 173 Vt. 202, 216, 790 A.2d 408, 421 (2001) (holding
  that we need not overturn trial court ruling where it did not harm the
  plaintiff and its resolution would not alter the outcome).   

       ¶  27.     We note, furthermore, that despite its ruling the Board did
  effectively address the Shelburne town plan and found no evidence that the
  replacement line in Shelburne-to be constructed almost entirely within the
  existing utility corridor-would cause or prevent additional development not
  in conformity with the Town's bylaws, and Shelburne has not challenged this
  finding.  The Board also expressly found that nearly all of the general
  goals and objectives in Shelburne's town plan dealing with land
  conservation, aesthetics, and visually significant areas had been addressed
  by the Board in its analyses of the various other criteria of § 248.  Thus,
  we find no basis to disturb the Board's ruling.   
   
       ¶  28.     Finally, Shelburne contends the Board abused its discretion
  in authorizing VELCO to seek reconsideration of its decision requiring the
  utility to underground a segment of the line along the Bay Road.  The Board
  found that the area, located near Lake Champlain, was aesthetically
  sensitive, and that, although the line would be located in an existing
  transmission corridor, the taller poles would be difficult to screen and
  would be out of character with the lakeshore and its surrounding
  residential neighborhoods.  Accordingly, it concluded that placing the line
  underground for approximately 1.3 miles of this segment was reasonable and
  necessary.  The Board also recognized, however, that the undergrounding
  option entailed significant additional costs, and observed "that there may
  be as-yet unknown issues, such as archaeological resources, that would
  create some problems in placing the line underground in this  area." 
  Therefore, it determined that VELCO could request the Board to reconsider
  its decision and allowed VELCO the opportunity to "develop a significantly
  more creative alternative design for an overhead line than has been
  previously submitted that addresses our concerns."

       ¶  29.     Shelburne claims that the Board's decision subverts the
  normal Rules of Civil Procedure and principles of finality and collateral
  estoppel by providing VELCO with an open-ended authorization to seek
  reconsideration of the Board's ruling.   We read the Board's decision more
  narrowly, however, as simply authorizing VELCO to revisit the ruling if,
  during the post-certification process of preparing and implementing
  feasibility studies and final design plans for location of the transmission
  structures, previously-unexplored problems or solutions present themselves
  at this particular location.  As noted, we have authorized such a two-step
  approach for the certification process, In re Vt. Elec. Power Co., 131 Vt.
  at 434-35, 306 A.2d  at 691-92, and we find no infirmity in its application
  here.   

                                    III.

       ¶  30.     Meach Cove raises four arguments on appeal.  The first
  three all restate claims,  previously discussed, that the Board  exceeded
  its authority under § 248 in approving a specific route for the proposed
  transmission line, and that as a result the Board improperly prejudged
  issues more properly left to a post-certification condemnation proceeding
  under 30 V.S.A. §§ 110 and 112.  As explained above, the arguments lack
  merit.  Supra, ¶¶ 17-18.
   
       ¶  31.     Meach Cove's final contention is that the Board erred in
  approving VELCO's alternative proposal to route a portion of the southerly
  segment of the line in Shelburne over Meach Cove lands rather than
  approving the original route through Davis Park.  Meach Cove claims that,
  having determined that the alternative proposals would have certain adverse
  aesthetic impacts, the Board was obligated to consider the original route
  and explain why it was unacceptable, and it failed to do so.  This claim is
  not supported by the record, which reveals that the parties adduced
  substantial evidence of adverse aesthetic impacts resulting from the
  original  proposal.(FN10)  The Board also concluded that the adverse effects
  from the Meach Cove rerouting proposal could be mitigated, although, as
  noted, it also reserved for the post-certification process final approval
  of detailed construction, placement, and mitigation plans.  Thus, we find
  no error. 

       Affirmed.

       FOR THE COURT:



       _______________________________________
       Associate Justice



------------------------------------------------------------------------------
                                  Footnotes

FN1.  For ease of reference, we refer to these three parties collectively
  as "New Haven" throughout this decision.

FN2.  Meach Cove, representing landowners affected when VELCO submitted a
  modification to the petition to reroute a portion of the line through
  Shelburne, was granted permissive intervention after the initial series of
  public and technical hearings.  The Board held supplementary public and
  evidentiary hearings in response to the rerouting proposal in which Meach
  Cove was a participant. 

FN3.  The Board noted its concern, however, that deficiencies in VELCO's
  planning process and lack of long-term focused attention on efficiency
  efforts had narrowed the Board's options in considering alternatives to the
  project proposal.  The Board announced, in response, that it planned to
  open a separate investigation into VELCO's forecasting abilities and to
  explore ways to ensure that cost-effective, nontransmission alternatives
  are adequately considered and implemented in the future. 

FN4.  Although its argument is not separately captioned, New Haven appears
  to argue that therewas no evidence to support the Board's finding that the
  addition of a second 115-kv line from Williamstown to Middlesex would have
  negative environmental effects, but Thomas Dunn, a VELCO project manager,
  testified specifically that this option "has additional environmental
  impacts because the right-of-way in the [Williamstown] to Middlesex
  corridor would likely need to be widened, and/or some present 34.5 kv lines
  would have to be moved or replaced."

FN5.  VELCO's experts described the Northwest Reliability  Project as "a
  coordinated series of improvements to the VELCO transmission system
  designed to provide reliable transmission service to the [S]tate of
  Vermont," and as a combination of upgrades designed to "work together to
  supply" Vermont's projected peak energy needs.

FN6.   VELCO experts testified, for example, that all of the proposed
  upgrades, including the 345-kv line, were designed to "work together as one
  project to meet" Vermont's energy needs, and singled out the 345-kv line as
  "the single most important element in strengthening the system feeding
  northwest Vermont."

FN7.  Dr. Peter Valberg, an expert in this area, stated in this regard that 

       [d]espite the ubiquitous nature of public exposure to EMF
       from high-voltage transmission lines, no recorded cases of
       medical-device disruption by power-line EMF were identified
       either in the manufacturers' websites or in our analysis of
       available data.  There are no FDA-issued safety alerts,
       public health advisories, [or] notices addressing potential
       medical device interference from power frequency EMF.

FN8.  New Haven notes one inaccurate finding in the Board's decision
  concerning non-health-based standards for EMF exposure.  The Board
  corrected the finding in response to New Haven's motion to alter.  The
  corrected finding provides no basis to disturb the decision. 

FN9.  In his prefiled testimony, Mr. Raphael analyzed the proposed
  mitigation measures  for this segment as follows: 

       While the upgrade as proposed will result in an adverse
       impact, mitigation measures such as careful pole placement,
       lower pole heights, retention of as much vegetation at the
       edge of [the] corridor as possible,  presence of background
       vegetation and other landscape elements in the corridor, as
       well as proposed plantings, provide sufficient mitigation to
       avoid an undue adverse impact in this section. 

FN10.  Landscape architect David Raphael testified, for example, that the
  original corridor "is located in a densely developed area with many
  residences, a school, a park, open space and other land uses," and that
  serious adverse impacts would accrue from higher poles and wider rights of
  way that would be offensive to a reasonable person.



Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.