Brennan Woods Limited Partnership v. Town of Williston

Annotate this Case
Brennan Woods Limited Partnership v. Town of Williston (2000-240); 
173 Vt. 468; 782 A.2d 1230

[Filed 26-Sept-2001]


                                 ENTRY ORDER

                      SUPREME COURT DOCKET NO. 2000-240

                              MARCH TERM, 2001

Brennan Woods Limited Partnership      }	APPEALED FROM:
                                       }
                                       }
     v.	                               }	Chittenden Superior Court
                                       }	
Town of Williston	               }
                                       }	DOCKET NO. S1494-98CnC

                                                Trial Judge: Edward J. Cashman

             In the above-entitled cause, the Clerk will enter:


       The Town of Williston appeals the summary judgment decision in favor
  of plaintiff Brennan  Woods Limited Partnership and grant of mandamus
  compelling the Town to allocate sewage  disposal capacity to plaintiff's
  project under the phasing schedule imposed by plaintiff's Act 250  permit. 
  The Town contends: (1) The Town Select Board acted within its discretion
  under the 1990  sewer allocation ordinance in imposing phasing requirements
  to regulate growth in accordance with  its Municipal Comprehensive Plan;
  (2) the Board is not bound by the decision of the environmental  court or
  Act 250 permit regarding the phasing schedule for the Brennan Woods
  project; and (3)  mandamus is not a proper remedy in light of the board's
  discretion.  We affirm.

       The following facts are not in dispute.  Plaintiff's predecessor filed
  a subdivision application  on May 19, 1994 (FN1) with the town planning
  commission to build 174 residential units on a 189-acre parcel on Mountain
  View Road, in Williston, Vermont.  On March 27, 1995, plaintiff's 
  predecessor applied for a sewer allocation of 39,150 gallons per day (gpd)
  to cover the entire project.  On July 27, 1995, the Board granted a partial
  sewer service allocation of 3,600 gpd for the project  to serve the initial
  fifteen homes in the development.  In May 1996, the town planning
  commission  granted subdivision approval for the project, but imposed a
  phasing requirement limiting  construction to fifteen homes a year and
  delayed construction of more houses until July 1998.   Plaintiff's
  predecessor appealed to the environmental court.  

       The issue before the environmental court was whether the planning
  commission was  authorized to impose a phasing limitation on the project. 
  The  court reviewed the zoning ordinance  which requires the planning
  commission to prepare a residential phasing policy to implement the 
  Williston Comprehensive Plan and zoning ordinance.  The court found that
  this provision of the  zoning ordinance lacked any safeguards or standards
  to which the planning commission must adhere  when creating its phasing
  policy.  Accordingly, the court held that the zoning ordinance was an 
  impermissible delegation of authority to the planning commission, and that
  therefore, the planning 

 

  commission lacked the authority to impose the phasing requirement.  In re
  Snyder Group Inc., No.E  96-099, slip op. at 2 (Vt. Env. Ct. June 19,
  1997).  The Town did not appeal the decision of the  environmental court.

       In September 1996, plaintiff's predecessor applied for an Act 250
  permit.  The Town provided  comment to the District 4 Coordinator about the
  project.  Regarding sewer and water, the Town  represented the following:

    The Williston Selectboard granted a municipal sewer allocation on
    July 27,  1995 to serve the initial 15 dwelling units of this
    development.  The  balance of the sewer allocation must be made at
    a later date.  Normally, the  Selectboard grants priority, as
    additional sewer capacity becomes  available, to a project that
    has already received a partial allocation and is  under
    construction.   Municipal water service is available to serve the 
    project.

  The Town also indicated that the project conforms to its 1995 Comprehensive
  Plan.  The District 4  Commission ultimately granted a permit to plaintiff
  that included a phasing plan commencing July 1,  1996, which allows
  build-out of the project at a rate equivalent to twenty-two housing units
  per year  over a period of eight years.  The Town did not appeal the
  District Commission's grant of an Act 250  permit and phasing condition.

       On May 28, 1998, the State approved an upgrade to the sewage plant the
  Town owns with  Essex and Essex Junction.  The upgrade added 250,000 gpd to
  the Town's share of uncommitted  reserve capacity.  The allocation of sewer
  service is controlled by the Town sewer allocation  ordinance.  The
  ordinance provides a list of allocation priorities under which existing
  facilities which  must be connected, but are not, and emergency pollution
  abatements are afforded first priority.   "Development projects within the
  sewer service area which has [sic] been granted allocation in prior  years
  will have second priority."  On June 18,1998, responding to the expanded
  capacity in the tri-town sewage plant, the Board adopted Attachment A to
  the sewer allocation ordinance allocating  52,510 gpd to residential
  projects with existing partial sewer allocations.  At that time,
  plaintiff's  project was one of four residential projects with existing
  partial sewer allocations.  On October 27,  1998, the Board adopted a
  resolution to allocate 39,240 gpd (FN2) to plaintiff subject to the 
  following phasing requirement:

    The allocation for Brennan Woods shall be for 5 single family
    dwellings  and 4 carriage homes (2130 gpd) in year 1998-1999, 15
    single family  dwellings (3750 gpd) in 1999-2000, 22 single family
    dwellings (5500 gpd)  in year 2000-2001, and a mix of single
    family dwellings and carriage  homes not exceeding 22 units in
    each subsequent year through 2006-2007 


 

    (annual allocations not exceeding 5,500 gpd).  Total allocation
    over the  entire development period shall be 39,240 gpd.

       Plaintiff appealed the allocation phasing requirement to the superior
  court pursuant to  V.R.C.P. 76.  Plaintiff and the Town filed motions for
  summary judgment.  Plaintiff argued that the  October 1998 resolution was
  not authorized by the applicable sewer ordinance and that the Board  failed
  to carry out its non-discretionary duty to release committed disposal
  capacity to Brennan  Woods.  The Court granted summary judgment in favor of
  plaintiff reasoning that the sewer  allocation ordinance did not contain
  any objective criteria or procedures for independently  implementing growth
  control policies beyond a standard of available sewer capacity, and
  therefore,  does not authorize the Board to impose phasing conditions.  The
  court also held that the phasing  schedule imposed by the Act 250 permit
  had become the only enforceable limitation on the rate at  which the
  project could be built.  The Town appeals.

       The Town contends it was authorized under the 1990 sewer allocation
  ordinance to grant  plaintiff its sewer allocation subject to the
  Town-imposed phasing schedule.  The Town maintains  the phasing schedule
  imposed by the October 27, 1998 resolution was intended to control the
  growth  and density of the Town's population as directed by the ordinance
  and Comprehensive Plan, and was,  therefore, authorized.  The Town also
  argues that the court erred in ruling that the only valid phasing 
  requirement was that imposed by the Act 250 permit.  Finally, the Town
  contends that mandamus  was an improper remedy.

       The superior court's decision with respect to the legality of the
  phasing requirement rests on  two conclusions: (1) the Town had limited
  power to use the sewer allocation ordinance as a growth-control measure,
  and its actions went beyond that limited power; and (2) through Appendix A,
  the  Town allocated the necessary sewer allocation to plaintiff, and it had
  no power to undo that  allocation in imposing conditions on the permit.  We
  examine the first conclusion in light of the  Town's first contention that
  the sewer allocation ordinance authorized the Board to make sewer 
  allocation decisions and impose conditions based on the goals of the
  Municipal Comprehensive Plan. 

       "[A] municipality has only those powers and functions expressly
  granted to it by the  legislature, such additional functions as may be
  incident, subordinate or necessary to the exercise  thereof, and such
  powers as are essential to the declared objects and purposes of the
  municipality."   Robes v. Town of Hartford, 161 Vt. 187, 190, 636 A.2d 342,
  345 (1993).  The Board acting as the  board of sewage disposal
  commissioners are "charged with the responsibility, among other things, to 
  construct, maintain, operate and repair sewer systems and sewage disposal
  facilities."  Bryant v.  Town of Essex, 152 Vt. 29, 36, 564 A.2d 1052,
  1055-56 (1989) (citing 24 V.S.A.   3401-3508 and  3601-3618)(internal
  quotations omitted).  In construing a municipal act, we will resolve all
  doubts  concerning a municipality's authority against the municipality. 
  Robes, 161 Vt. at 190, 636 A.2d  at  345.  

       The parties agree that the controlling, applicable law is in Bryant v.
  Town of Essex, but  disagree on the force of that decision.  Bryant held
  that a town could use a sewer allocation ordinance  to control growth
  generally, but only if it acted under its zoning authority and the policy
  was adopted 

 

  under the procedures required to adopt a zoning ordinance.  Bryant, 152 Vt.
  at 36, 564 A.2d  at 1055.  The Town does not claim it adopted its sewer
  allocation ordinance under procedures applicable to  zoning ordinances so
  it can not claim this power.

       Alternatively, Bryant holds that a sewer allocation ordinance can
  "control population density  and growth specifically with regard to the
  sewer core area, that is with regard to the load on the  sewer and sewage
  disposal system."  Id., 564 A.2d  at 1056.   We held that "[t]o the extent
  that the  population density and growth controlled by the [sewer
  allocation] Policy are related to the load on  the sewer and sewage
  disposal system, the Town may allocate capacity of that system through the 
  Policy, as a power incidental to managing the sewage system."  Id.  Only
  where decisions are based  on the load to the sewer system, therefore, may
  the sewer allocation ordinance be used to control  population density and
  growth.

       The superior court held that the Board was not responding "to the load
  on the sewer and  sewage disposal system" in imposing its phasing schedule. 
  This conclusion is supported by the  undisputed facts that the Town had
  excess capacity as a result of the plant upgrade, it could easily  meet all
  second priority requests before moving on to lower priorities, and the
  Board imposed  exactly the same phasing schedule as had been adopted by the
  planning commission and reversed, as  unauthorized, by the environmental
  court.  The superior court's decision is fully consistent with  Bryant.

       In reaching this conclusion, we are not persuaded by the Town's claim
  that  4(B)(ii) of the  sewer allocation ordinance provides an objective
  standard for making sewer allocations based on the  Town's growth policy. 
  The section provides that "[t]he Board shall designate a portion of said 
  reserve capacity to be available for the fiscal year, may assign specific
  capacities to zoning districts  or user classifications or may establish
  other conditions for assignment of capacity, which allocations  and
  conditions shall be in accordance with the goals of the Municipal
  Comprehensive Plan."  The  superior court construed the language as
  controlling growth only with respect to available sewage  capacity.  The
  alternative interpretation, that the section allows decisions based on
  growth limits in  the town plan, conflicts with Bryant's holding that a
  sewage allocation ordinance, not issued under  the zoning power, can not
  impose growth limits except in relation to the load on the sewer and 
  sewage disposal system. 

       We also reject the Town's attack on the second ground of the superior
  court decision - that the  Town had already allocated the sewage capacity
  when it imposed the restrictive phasing  requirements.  The court found
  that the Town committed to allocating 37,290 gpd to Brennan Woods  in
  Attachment A, attached to the minutes of a Board meeting.  The Town
  contends that because the  Brennan Woods project was not identified in
  Attachment A, the attachment cannot serve as a  commitment of sewer
  capacity to Brennan Woods.  The internal memorandum containing the 
  recommendation for Attachment A belies this claim.  The memorandum
  recommends that the Town  "clean-up" all previous commitments before
  determining how to allocate the available balance.  The  ordinance required
  exactly this approach.  As recommended, the Board allocated 52,510 gpd to
  this  category, a number that can be reached only by including the Brennan
  Woods allocation.  The Town  admitted as much in its answer to plaintiff's
  complaint.  

 

       The Town also contends that the June 1995 partial allocation was not a
  preliminary connection  approval so that Brennan Woods was not entitled to
  a second priority under the sewer allocation  ordinance and could not have
  been part of the four authorized projects in that priority.  Again, the 
  court found against the Town on this point, and its holding is supported by
  the undisputed facts in the  record.  Under the sewer allocation policy, a
  preliminary connection approval "shall be a binding  commitment of capacity
  to the project contingent on compliance with any conditions attached to the 
  preliminary approval and the subsequent issuance of a final connection
  approval." As demonstrated  by the Town's representations to the District 4
  Commission, the June 1995 partial allocation was a  preliminary connection
  approval.  The Town represented to the District 4 Environmental  Commission
  that it had granted a sewer allocation to serve the initial fifteen
  dwellings of the 174  unit project.  The Town conceded that projects that
  have received a partial allocation receive priority  as additional sewer
  capacity becomes available.  The Town also pledged that the balance of the 
  requested allocation must be made at a later date.  The only limitation or
  qualification to the Town's  commitment to allocate the necessary sewer
  connections to the project, therefore, was the availability  of additional
  sewer capacity.  This limitation was eliminated with the 1998 tri-town
  facility upgrade.

       We turn now to the Town's argument that the superior court misused the
  Act 250 permit and  the environmental court decision.  The Town argues that
  it is not bound by the phasing schedule  imposed by the Act 250 permit
  because it did not participate or appear at the hearing.  Although we 
  disagree with the argument because the Town was a party to the Act 250
  proceeding, see 10 V.S.A.  6085 (c)(1), we find it largely irrelevant. 
  The Act 250 phasing schedule controls because the more  restrictive
  schedule imposed by the Town is invalid and not because the Town was a
  party to the Act  250 proceeding.

       Next, the Town argues that the court's reliance on the decision of the
  environmental court to  further buttress its conclusion that the Act 250
  permit is the only valid phasing requirement is  misplaced.  As discussed
  above, the main significance of the environmental court decision is that it 
  struck down the identical phasing requirements when they were imposed by
  the planning  commission.  The superior court's decision does not hold that
  the environmental court has appellate  jurisdiction over actions of the
  Board. 

       As its third and final main argument, the Town contends that mandamus
  was improper because  the decision to grant a final connection approval for
  the project is discretionary under Bryant.  See  Bryant, 152 Vt. at 40, 564 A.2d  at 1057-58.  The requested relief and authority of the Board in 
  Bryant, however, are distinguishable from the issues in the present action. 
  In Bryant, we found that  mandamus would be an improper remedy because the
  decision to extend the sewer system is  discretionary under the statutory
  authority of the Town or Board to construct and operate a sewage  plant and
  system.  Id.  In contrast, we have held here that controlling growth is not
  incident to the  statutory power of the Board to manage the sewer system
  where growth control is not tied to the load  on the sewer capacity. 
  Lacking the authority to control population density and growth in the
  manner  it did, the Board's decision to achieve this purpose through
  implementing phasing conditions is not  discretionary.

 

       Where the decision-making is compelled by statute or other authority
  beyond the Board,  mandamus is a proper remedy.  See Corcoran v.
  Bennington, 128 Vt. 482, 490, 266 A.2d 457, 463  (1970).  Here, the sewer
  allocation ordinance imposed upon the Board the duty to issue a final sewer 
  connection approval permit once all conditions of the preliminary
  connection approval and final  connection approval had been met.  The only
  condition suggested by the preliminary connection  approval was that the
  Town obtain additional sewer capacity.  That condition was met with the
  tri-town upgrade.  The ordinance outlines three conditions for final
  connection approval: (1) the  applicant must secure applicable local, state
  and federal permits for the project; (2) all fees related to  the
  connection have been paid; and (3) the plans and specifications for
  connection to the municipal  sewers are approved by the Board.  Once these
  conditions have been satisfied, the Board "shall issue  the final
  connection approval permit."  Plaintiff has obtained all permits and paid
  all fees.  After the  sewer upgrade, the additional sewer allocation was
  approved through Attachment A.  

       All conditions for the final connection approval having been met,
  plaintiff had a right to final  connection approval for the project, and
  the Board had a duty to grant this approval.  Mandamus,  therefore, was
  proper. See id. at 490, 266 A.2d  at 463 (mandamus will lie to compel
  performance of  duty where the  right to be enforced becomes certain);
  Garzo v. Stowe Bd. of Adjustment, 144 Vt.  298, 300, 476 A.2d 125, 126
  (1984) (mandamus granted where party requesting relief has a clear  legal
  right to the performance of duty and the law affords no other remedy).

       Affirmed.  


                                       BY THE COURT:


                                       _______________________________________
                                       Jeffrey L. Amestoy, Chief Justice

                                       _______________________________________
                                       John A. Dooley, Associate Justice

                                       _______________________________________
                                       James L. Morse, Associate Justice

                                       _______________________________________
                                       Denise R. Johnson, Associate Justice

                                       _______________________________________
                                       Marilyn S. Skoglund, Associate Justice



------------------------------------------------------------------------------
                                  Footnotes


FN1.  Plaintiff is the successor in interest to all permits and approvals
  regarding the project.

FN2.  There is a discrepancy between the initial allocation number of 37,290
  gpd and the final  allocation number of 39,240 gpd.  The discrepancy is not
  relevant to any appeal issue.


Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.