LEININGER v. WARD

Annotate this Case

LEININGER v. WARD
1927 OK 241
258 P. 863
126 Okla. 114
Case Number: 18423
Decided: 08/02/1927
Supreme Court of Oklahoma

LEININGER et al.
v.
WARD et al.

Syllabus

¶0 1. Highways--State Highway Commission--Powers and Discretion in Conformity With Law. By chapter 48, S. L. 1923-4, the State Highway Commission is created, and vested with powers and duties necessary to fully and effectively carry out all of the objects of the act, but the exercise of its powers and discretion and the enforcement of its rules and regulations must not be inconsistent with such act, or other laws of the state.
2. Same--Contracts--Construction of Statute--Lowest Responsible Bidder." Section 12 of said act provides: "All contracts for construction work upon the state highway system shall be let to the lowest responsible bidder, or bidders. * * *" Held, this language contemplates and implies competitive bidding.
3. Same--"Competitive Bidding."The term "competitive bidding" means bidding upon the same undertaking, upon the same material items in the subject-matter, upon the same thing.
4. Same--Prescribed Time for Completion of Work as Essential Element in Bids. By the provisions of said act, the time for completion of a contract for road construction is made an essential element in the proposals or bids upon the work to be done. A rule requiring each bidder to name his own time and permitting each bidder to name a different time for completion of a given project is not consistent with the provisions and intendments of said act.
5. Same--Injunction Against Consummating Contract Sustained Where Bidder Named Own Time. Where a proposal or bid wherein the bidder was authorized and required to name his own time for completion of the work, but where no contract has been entered into and no services rendered to the state for which the bidder would be entitled to compensation from the state, an injunction granted by the trial court, enjoining the Highway Commission from entering into and consummating such contract, will be sustained.

Edwin Dabney, Atty Gen., and W. L. Murphy, Asst. Atty. Gen., for plaintiffs in error.
Owen, Armstrong, Short & Looney, for defendants in error.

HARRISON, J.

¶1 This appeal is to reverse a judgment of the district court, wherein the State Highway Commission was enjoined from entering into a contract with a firm known as McGuire & Cavender for the construction of a highway project designated as Federal Aid Project 139. The proceedings were begun by Green-Boots Construction Company, alleged competitive bidders for the construction work in question, but defendants in error, who were also alleged competitive bidders, were allowed to intervene, and the cause was tried upon the issues presented in their cross-petition, the issue being whether, under the statutes, time for the completion of the project is an essential item to be considered in determining the lowest bid.

¶2 Under the form of proposals or bids furnished by the Commission, each bidder is required to name the time in which he will complete the proposed work and each bidder is authorized to name a different time for completion. Upon the project in question, viz, the construction of 18 miles of hard-surfaced road in Logan county, only three bids were submitted, to wit: Ward-Beekman & Brooks and H. L. Canady Company proposed to complete the project in four months for $ 483,617.03; Green-Boots Construction Company proposed to complete it in six months for $ 452,918.10 (this was rejected because of some defect in the proposal); and McGuire & Cavender proposed to complete it in twelve months for $ 444,776.50.

¶3 This last bid was accepted as the best bid, and this suit was brought to enjoin the Commission from awarding the contract to McGuire & Cavender on the grounds and with the result above stated. The only question presented is whether the Commission should have named the time for completion and required each bidder to bid upon the same time as well as upon the same specification in other regards. This identical question was before us and definitely passed upon in cause No. 18405, Flynn Construction Co. v. Leininger,

¶4 We note, however, that the record herein contains testimony intending to show that more competition and better results are obtained by requiring each bidder to name his own time than by requiring all bidders to bid upon the same time for completion. It may be a fact that more bids and better bids are now obtained than were obtained in former years, when all bidders were required to bid upon the same time, but the record is by no means conclusive that the better results are due to the change in the form of bids. In fact, it tends to refute the correctness of such contention, especially when we consider the manifold increase in road construction and corresponding increase in number of contractors. Besides, when we take into consideration the expense of maintaining a detour, which in the present case is 20 miles, the interest paid by the counties on outstanding bonds while they are doing without the roads, and the inconvenience and expense to the counties and also to the general public in doing without roads already paid for, we are not sure that the bid of $ 444,776.50 in 12 months is a better bargain to the public than the one for $ 483,617.03 in four months. And we cannot sustain the contention that the convenience of the public is immaterial. The public highways are built and maintained by the public and for the public, and when the public by paying automobile and gasoline taxes has contributed the money to build a road--in other words, when it has already paid for a road--it is entitled to have that road as soon as it can be built consistent with good business principles; hence the convenience of the public is a material matter and time of completion becomes an essential element in the matter, and the Legislature has provided accordingly. So if it were true that more bids could be obtained by disregarding the element of time and allowing each bidder to take his own time, then such fact should be presented to the Legislature rather than to the courts. Both the existing conditions and the Legislature have made time an essential element and the courts are not authorized to change the law.

¶5 While the bid in this case has been accepted as the lowest responsible bid, still no contract has been entered into, no work has been done nor material furnished for which the state should be obligated to pay, as was true in the Flynn Case, supra. No substantial detriment can result from a readvertisement for bids in conformity with the statutes. The judgment is therefore affirmed.

¶6 BRANSON, C. J., and MASON, CLARK, and RILEY, JJ., concur. HUNT and HEFNER, JJ., dissent. DISSENTBY: HUNT

HUNT, J. (dissenting).

¶1 I dissent for two reasons:

First. I did not agree and do not now agree with that part of the Flynn Case holding that the time limit within which a road project is to be completed must be fixed by the Highway Commission and included in the advertisement for bids so that all contractors bid on the same time. The law, of course, places some discretion in the Highway Commission, and in my judgment a fair and liberal construction of that portion of the law providing that contracts should be let to the lowest responsible bidder and that the work should be completed in the shortest time possible consistent with good business management would require that the matter of fixing the time limit within which a project should be completed be left discretionary with the Commission. In other words, in some projects it might be advisable to fix the time limit within which the work must be completed, and in others not, this to be determined by the Commission in each particular instance in the exercise of its sound discretion. I concede, however, that this proposition is settled by the majority opinion in the Flynn Case.

¶2 Second. The record in this case shows that the bids on this project were opened by the State Highway Commission on April 12, 1927, and the contract was awarded to the successful bidder, McGuire & Cavender, on April 14, 1927. It further appears that this work was advertised and contract awarded by the State Highway Commission under the same rules and regulations and in the same manner as the contract involved in Flynn Construction Co. v. State Highway Commission,

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.