In re Application of Columbus S. Power Co.

Annotate this Case
Justia Opinion Summary

American Electric Power operating companies (AEP) had been providing service to a pair of manufacturing customers at discounted rates. AEP had been keeping track of its delta revenue, the difference between what AEP would have collected under its tariffs and what it actually collected with the discount, and intended to collect it through a rider. In the case below, AEP filed an application seeking permission to collect its delta revenue through the rider. Industrial Energy Users-Ohio (IEU) opposed both requests. The Public Utilities Commission rejected IEU's arguments and allowed the American Electric Power operating companies (AEP) to recover the costs arising from the discounted-rate arrangements. IEU appealed. The Supreme Court affirmed, holding (1) IEU did not show that the Commission erred in modifying the phase-in of AEP's rates, and (2) IEU did not show that the Commission erred in calculating AEP's carrying charges.

Download PDF
[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Columbus S. Power Co., Slip Opinion No. 2011-Ohio-4129.] NOTICE This slip opinion is subject to formal revision before it is published in an advance sheet of the Ohio Official Reports. Readers are requested to promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65 South Front Street, Columbus, Ohio 43215, of any typographical or other formal errors in the opinion, in order that corrections may be made before the opinion is published. SLIP OPINION NO. 2011-Ohio-4129 IN RE APPLICATION OF COLUMBUS SOUTHERN POWER COMPANY ET AL. TO ADJUST THEIR ECONOMIC DEVELOPMENT COST RECOVERY RIDER; INDUSTRIAL ENERGY USERS OHIO, APPELLANT; PUBLIC UTILITIES COMMISSION ET AL., APPELLEES. [Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In re Application of Columbus S. Power Co., Slip Opinion No. 2011-Ohio-4129.] Public utilities Electricity rates Recovery of losses from discounts Carrying charges. (No. 2010-1073 Submitted June 8, 2011 Decided August 24, 2011.) APPEAL from the from the Public Utilities Commission, No. 10-154-EL-RDR. __________________ MCGEE BROWN, J. {¶ 1} In the case below, the Public Utilities Commission allowed the American Electric Power operating companies ( AEP ) to recover certain costs arising from a pair of discounted-rate arrangements. Industrial Energy Users SUPREME COURT OF OHIO Ohio ( IEU ) opposed AEP s application and now appeals. IEU fails to demonstrate reversible error, however, and we affirm. I. Factual and Procedural Background {¶ 2} As previously ordered by the commission, AEP had been providing service to a pair of manufacturing customers at discounted rates.1 [T]he difference between what AEP would have collected from [these customers] under its tariffs and what it actually collected, given the discount, is called delta revenue. In re Application of Columbus S. Power Co., ___ Ohio St.3d ___, 2011-Ohio-2638, ___ N.E.2d ___, ¶ 3. AEP had been keeping track of this delta revenue and intending to collect it through a rate mechanism called the economic development cost recovery rider. We will simply call it the rider. {¶ 3} In the case below, AEP filed an application seeking permission to collect its delta revenue through the rider. This was actually the second time that AEP had filed such an application; its first request had been granted only a month earlier. These quickly successive applications reflected the requirement that AEP update[] and reconcile[] the rider every six months. Ohio Admin.Code 4901:138-08(A)(5). {¶ 4} IEU opposed both requests, raising the same objections each time. In the first proceeding, the commission rejected IEU s arguments. IEU appealed that decision to this court, and the case was briefed; we never ruled on the dispute, however, because IEU dismissed its appeal before oral argument. {¶ 5} In the second proceeding (which is the case now on review), the commission again rejected IEU s arguments, this time on the basis that it had already ruled against IEU in the first proceeding. IEU again appealed. It did not dismiss this appeal, but did choose to submit the case on the briefs, without oral argument. AEP has intervened as an appellee. 1 We reviewed the commission s approval of these arrangements in In re Application of Ormet Primary Aluminum Corp., 129 Ohio St.3d 9, 2011-Ohio-2377, 949 N.E.2d 991. 2 January Term, 2011 II. Discussion {¶ 6} IEU initially raised four propositions of law but has since dismissed the first two. For reasons discussed below, the remaining propositions lack merit. A. IEU Has Not Shown that the Commission Erred in Modifying the Phase-in of AEP s Rates. {¶ 7} In its third proposition of law, IEU argues that the order unlawfully exempted the rider from the maximum increases permitted in AEP s electricsecurity-plan case. IEU is referring to the commission s decision in an earlier case to limit how much AEP could annually increase its customers bills; the commission acted under R.C. 4928.144, which permits the commission to authorize any just and reasonable phase-in of certain electric rates. IEU attacks the decision to exempt the rider from the rate-increase limits on two grounds: procedurally, it asserts that the commission departed from precedent; substantively, it argues that the commission unreasonably increased rates. Neither argument is persuasive. {¶ 8} As to the procedural argument, the order below did not violate the earlier, electric-security-plan order. It is true, as IEU argues, that the earlier order did not exempt the rider from the rate-increase limits. But the commission did not rule out further exemptions, and as a general rule, the commission has discretion to revisit earlier regulatory decisions and modify them prospectively. See, e.g., Utility Serv. Partners, Inc. v. Pub. Util. Comm., 124 Ohio St.3d 284, 2009-Ohio6764, 921 N.E.2d 1038, ¶ 18 ( Modifying a regulatory scheme is not problematic in itself. Agencies undoubtedly may change course, provided that the new regulatory course is permissible ); In re Application of Columbus S. Power Co., 128 Ohio St.3d 512, 2011-Ohio-1788, 947 N.E.2d 655, ¶ 52. IEU does not explain why the general rule should not apply here. We fail to see any procedural error. 3 SUPREME COURT OF OHIO {¶ 9} That leads to IEU s substantive argument, namely, that the commission erred by allowing current rates to become too high. This argument also lacks merit. {¶ 10} The decision that IEU attacks is a discretionary one. As noted, the commission s power to limit annual rate increases, and thus phase in AEP s rates, comes from R.C. 4928.144. That law allows the commission to authorize any just and reasonable phase-in of electric-security-plan rates as the commission considers necessary to ensure rate or price stability for consumers. (Emphasis added.) While the end product must be just and reasonable, the emphasized language entrusts the details of any phase-in how much should be collected now, how much later to the commission s discretion. {¶ 11} Discretionary decisions receive deferential review, Ohio Consumers Counsel v. Pub. Util. Comm., 117 Ohio St.3d 289, 2008-Ohio-860, 883 N.E.2d 1025, ¶ 10, and IEU has not shown an abuse of discretion. Its complaint concerns a pure matter of timing should customers pay the rider now or later? If later, the law requires that carrying charges (a kind of financing charge) be added to the deferred rates. R.C. 4928.144. IEU points to no legislative command that addresses the specifics of such a timing question, and the absence of statutory criteria leaves us ill-equipped to second-guess the commission s discretionary determinations. IEU s sense that current rates are high enough and its preference to pay the rider (plus carrying charges) later are not enough to upset the order. {¶ 12} For the foregoing reasons, we reject IEU s third proposition of law. B. IEU Has Not Shown that the Commission Erred in Calculating AEP s Carrying Charges. {¶ 13} In its fourth proposition of law, IEU argues that the commission erred in allowing AEP to use a long-term debt rate (as opposed to a short-term 4 January Term, 2011 rate) to calculate certain carrying charges. Again, however, IEU has not demonstrated reversible error. {¶ 14} IEU has preserved for appeal only a single argument concerning the calculation of AEP s carrying charges. In its application for rehearing, IEU alleged that the commission had repeated[ly] fail[ed] to at least inquire as to whether a lower carrying cost rate could be utilized. (Emphasis added.) Customers, IEU asserted, deserve at least some analysis or other review of the carrying-cost issue. IEU raised no other argument. {¶ 15} So far as IEU s rehearing application explained, the commission would have fully satisfied IEU s concerns if it inquired or provided some analysis or other review of the carrying-cost issue. But the commission did inquire and provide some analysis of that issue: it had reviewed that issue in the preceding rider case.2 And in the order below, the commission explained that very fact in response to IEU s objection. IEU did not reply with any additional challenges. In short, IEU argued only that the commission needed to make an inquiry, and the commission pointed out where it had made that inquiry. The commission fully answered IEU s concern. {¶ 16} IEU s remaining argument that the commission failed to explain the reasons for its decision is forfeited. We have jurisdiction only over arguments raised on rehearing. Ohio Consumers Counsel v. Pub. Util. Comm., 114 Ohio St.3d 340, 2007-Ohio-4276, 872 N.E.2d 269, ¶ 40. IEU did not argue on rehearing that the commission had failed to explain itself, so we cannot consider the alleged error. {¶ 17} IEU s fourth proposition of law is rejected. III. Conclusion {¶ 18} For the foregoing reasons, we affirm. 2 That order is not before us, and we offer no opinion on its merits. 5 SUPREME COURT OF OHIO Order affirmed. O CONNOR, C.J., and PFEIFER, LUNDBERG STRATTON, O DONNELL, LANZINGER, and CUPP, JJ., concur. __________________ McNees, Wallace & Nurick, L.L.C., Samuel C. Randazzo, and Joseph E. Oliker, for appellant. Michael DeWine, Attorney General, and William L. Wright, Thomas W. McNamee, Thomas G. Lindgren, and Werner L. Margard III, Assistant Attorneys General, for appellee, Public Utilities Commission of Ohio. Steven T. Nourse and Matthew J. Satterwhite, for intervening appellees, Columbus Southern Power Company and Ohio Power Company. ______________________ 6

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.