Behrins v Campanella 2016 NY Slip Op 02602 Decided on April 6, 2016 Appellate Division, Second Department Published by New York State Law Reporting Bureau pursuant to Judiciary Law ยง 431. This opinion is uncorrected and subject to revision before publication in the Official Reports.

Decided on April 6, 2016 SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
RANDALL T. ENG, P.J.
JOHN M. LEVENTHAL
ROBERT J. MILLER
HECTOR D. LASALLE, JJ.
2014-05585
(Index No. 100590/12)

[*1]Jonathan B. Behrins, et al., appellants,

v

Keith Campanella, et al., respondents.



Behrins Law Firm, PLLC, Staten Island, NY (Jonathan B. Behrins pro se and Bruce G. Behrins of counsel), appellant pro se, and for appellant Jonathan B. Behrins.

Dealy Silberstein & Braverman, LLP, New York, NY (Milo Silberstein of counsel), for respondents.



DECISION & ORDER

In an action, inter alia, to recover damages for fraud and breach of contract, the plaintiffs appeal, as limited by their brief, from so much of an order of the Supreme Court, Richmond County (Dollard, J.), dated April 14, 2014, as granted those branches of the defendants' motion which were for summary judgment dismissing the complaint and for summary judgment on their counterclaim.

ORDERED that the order is affirmed insofar as appealed from, with costs.

The plaintiffs leased office space pursuant to a five-year lease which provided that the term of the lease would commence upon completion of certain work to be performed by the landlord, Gardens Office I, LLC. The landlord hired the defendant Campa Construction Corp. (hereinafter Campa) to perform the work specified in the contract. The plaintiffs also hired Campa to perform additional work not called for in the lease pursuant to two change orders. The plaintiffs allege, inter alia, that Campa and its principal, the defendant Keith Campanella, agreed to complete the work by November 26, 2011, and that the defendants breached the terms of the parties' agreement by failing to complete the work by that date.

Contrary to the plaintiffs' contention, the defendants established their prima facie entitlement to judgment as a matter of law dismissing the cause of action to recover damages for breach of contract by demonstrating that they never agreed to complete the work by November 26, 2011 (see Miranco Contr., Inc., v Perel, 29 AD3d 873, 874). In opposition, the plaintiffs failed to raise a triable issue of fact.

The plaintiffs' remaining contentions are without merit.

Accordingly, the Supreme Court properly granted those branches of the defendants' motion which were for summary judgment dismissing the complaint and for summary judgment on their counterclaim, which seeks payment of the balance due for their work.

ENG, P.J., LEVENTHAL, MILLER and LASALLE, JJ., concur.

ENTER:

Aprilanne Agostino

Clerk of the Court



Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.