Howard Frank v Mazs Group, LLC

Annotate this Case
Frank v Mazs Group, LLC 2006 NY Slip Op 04383 [19 AD3d 1186] Decided on June 6, 2006 Appellate Division, Second Department Published by New York State Law Reporting Bureau pursuant to Judiciary Law ยง 431. This opinion is uncorrected and subject to revision before publication in the Official Reports.

Decided on June 6, 2006
SUPREME COURT OF THE STATE OF NEW YORKAPPELLATE DIVISION : SECOND JUDICIAL DEPARTMENT
STEPHEN G. CRANE, J.P.
REINALDO E. RIVERA
PETER B. SKELOS
MARK C. DILLON, JJ.
2005-08140 DECISION & ORDER

[*1]Howard Frank, et al., respondents,

v

Mazs Group, LLC, defendant, Lawrence H. Pinner, d/b/a Pinner Associates, appellant. (Index No. 23247/04)




Wilson, Elser, Moskowitz, Edelman & Dicker, LLP, New
York, N.Y. (Glenn J. Fuerth, Richard E. Lerner, and Frank T.
Santoro of counsel), for appellant.
Gary M. Darche, Kew Gardens, N.Y., for respondents.

In a consolidated action, inter alia, to recover damages for professional malpractice, the defendant Lawrence H. Pinner, d/b/a Pinner Associates, appeals, as limited by his brief, from so much of an order of the Supreme Court, Queens County (Dorsa, J.), dated July 11, 2005, as denied that branch of his motion which was pursuant to CPLR 3211(a)(5) and 214(6) to dismiss the complaint insofar as asserted against him as time barred.

ORDERED that the order is affirmed insofar as appealed from, with costs.

A cause of action to recover damages for professional malpractice against an architect for defective design or construction accrues upon the actual completion of the work to be performed and the consequent termination of the professional relationship (see Brushton-Moira Cent. School Dist. v Thomas Assoc., 91 NY2d 256, 261; County of Rockland v Kaeyer, Garment & Davidson Architects, 309 AD2d 891; IFD Constr. Corp. v Corddry Carpenter Dietz & Zack, 253 AD2d 89, 92; Board of Mgrs. of Yardarm Beach Condominium v Vector Yardarm Corp., 109 AD2d 684, 686; N. R. S. Constr. Corp. v Board of Educ., 82 AD2d 876). The completion of an architect's obligations must be viewed in light of the particular circumstances of the case (see Board of Educ. of Tri-Va. Cent. School Distr. at Grahamsville v Celotex Corp., 88 AD2d 713, 714, affd 58 NY2d 684). Here, the appellant, the architect who designed the plaintiffs' one-family home, was obligated to obtain [*2]a certificate of occupancy (see Board of Mgrs. of Yardarm Beach Condominium v Vector Yardarm Corp., supra; cf. Parsons Brinckerhoff Quade & Douglas v EnergyPro Constr. Partners, 271 AD2d 233, 234; Matter of Kohn Pederson Fox Assoc., P.C., 189 AD2d 557, 558). Moreover, the record demonstrates that the appellant applied for the certificate of occupancy after construction was completed and thereafter made a supplemental submission in support of the application. Under the circumstances of this case, the plaintiffs' claims against the appellant did not begin to accrue for statute of limitations purposes until the issuance of the certificate of occupancy on December 20, 2001. Accordingly, the Supreme Court properly determined that the claims which were asserted against the appellant on October 14, 2004, were not time barred pursuant to CPLR 214(6) .

The appellant's remaining contentions are without merit.
CRANE, J.P., RIVERA, SKELOS and DILLON, JJ., concur.

ENTER:

James Edward Pelzer

Clerk of the Court

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.