Northeast Restoration Corp. v T.A. Ahern Contrs. Corp.

Annotate this Case
Northeast Restoration Corp. v T.A. Ahern Contrs. Corp. 2015 NY Slip Op 07746 Decided on October 22, 2015 Appellate Division, First Department Published by New York State Law Reporting Bureau pursuant to Judiciary Law ยง 431. This opinion is uncorrected and subject to revision before publication in the Official Reports.

Decided on October 22, 2015
Tom, J.P., Andrias, Moskowitz, Kapnick, JJ.
20679/10 15926A 15926

[*1] Northeast Restoration Corp., Plaintiff-Respondent,

v

T.A. Ahern Contractors Corp., et al., Defendants-Appellants, New York City School Construction Authority, et al., Defendants.



Westermann Sheehy Keenan Samaan & Aydelott, LLP, Uniondale (Robert J. Fryman of counsel), for appellants.

BahnMulter LLP, New York (Martin I. Gold of counsel), for respondent.



Judgment, Supreme Court, Bronx County (Barry Salman, J.), entered April 18, 2014, after a nonjury trial, awarding plaintiff damages as against defendants T.A. Ahern Contractors Corp. and Safeco Insurance Company of America, unanimously affirmed, with costs. Appeal from order, same court and Justice, entered on or about April 15, 2014, unanimously dismissed, without costs, as subsumed in the appeal from the aforesaid judgment.

There is no basis for disturbing the trial court's finding in favor of plaintiff on its claim for unpaid change orders and work completed but not billed before the termination date of its contract with defendant Ahern (see generally Nagel v Nagel, 85 AD3d 559 [1st Dept 2011]). Contrary to defendants' contention, plaintiff was justified in refusing to continue performing work that it deemed outside the scope of the contract, absent a Notice of Direction (NOD) from Ahern, which would have protected its right to claim additional compensation for that work (compare Kalisch-Jarcho, Inc. v City of New York, 72 NY2d 727 [1988] [contractor was permitted to file a written protest to preserve its right to claim compensation for disputed work]). The testimony of defendants' witness that the contract did not require an NOD under the circumstances was contradicted by the language of the contract, and was effectively an improper expert opinion as to a legal conclusion (see Colon v Rent-A-Center, 276 AD2d 58, 61 [1st Dept 2000]).

Plaintiff's evidence of its damages, including the work it performed from the last billing cycle to the termination, was sufficient. Further, the calculation used to determine the value of that work, i.e., the percentage of completion of the total contract price, was proper (see e.g. Schultz Constr. v Franbilt, Inc., 285 AD2d 936 [3d Dept 2001]).

The dismissal of Ahern's counterclaims is supported by evidence that plaintiff neither caused the claimed damages nor was responsible for them under the contract.

We have considered defendants' remaining contentions and find them unavailing.

THIS CONSTITUTES THE DECISION AND ORDER

OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.

ENTERED: OCTOBER 22, 2015

CLERK



Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.