City of New York v Greenwich Ins. Co.

Annotate this Case
City of New York v Greenwich Ins. Co. 2012 NY Slip Op 04096 Decided on May 29, 2012 Appellate Division, First Department Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. This opinion is uncorrected and subject to revision before publication in the Official Reports.

Decided on May 29, 2012
Friedman, J.P., Sweeny, Renwick, Freedman, Abdus-Salaam, JJ.
7770 111104/09

[*1]The City of New York, et al., Plaintiffs-Appellants,

v

Greenwich Insurance Company, et al., Defendants-Respondents,




Ahmuty Demers & McManus, Albertson (Glenn A. Kaminska
of counsel), for appellants.
Law Offices of Todd M. McCauley, LLC, New York (David
Tavella of counsel), for respondents.

Order, Supreme Court, New York County (Jeffrey K. Oing, J.), entered April 19, 2011, which denied plaintiffs' cross motion for summary judgment declaring that defendant has a duty to defend and indemnify plaintiffs, and denied defendants' motion for summary judgment dismissing the complaint, unanimously modified, on the law, to grant the cross motion and declare that defendant insurer has a duty to defend and indemnify plaintiffs in the underlying personal injury action, and otherwise affirmed, without costs.

Under Insurance Law § 3420(d)(2), an insurer wishing to deny coverage for death or bodily injury must "give written notice as soon as is reasonably possible of such disclaimer of liability or denial of coverage." "When an insurer fails to do so, it is precluded from disclaiming coverage based upon late notice, even where the insured has in the first instance failed to provide the insurer with timely notice of the accident" (Hunter Roberts Constr. Group, LLC v Arch Ins. Co., 75 AD3d 404, 408-409 [2010]). Although the timeliness of such a disclaimer generally presents a question of fact, where the basis for the disclaimer was, or should have been, readily apparent before the onset of the delay, any explanation by the insurer for its delay will be insufficient as a matter of law (see First Fin. Ins. Co. v Jetco Contr. Corp., 1 NY3d 64, 69 [2003]).

Even assuming that some investigation was necessary, as plaintiffs' May 17, 2007 notice of claim letter contained only the date of loss and did not indicate when plaintiffs first learned of the subject accident, Greenwich's investigation did not even begin until June 21, 2007, more than 31 days after receipt of the May 17, 2007 letter, and continued for approximately five and one half months. Despite the fact that the dates on which plaintiffs responded to Greenwich are disputed, insurers have a duty to "expedite" the disclaimer process (First Fin. Ins. Co., 1 NY3d at 68), and Greenwich does not explain, given the facts made known by Temco's May 17, 2007 [*2]submission, "why anything beyond a cursory investigation" was necessary to determine whether plaintiffs had timely notified it of the claim (Hunter Roberts Constr. Group, 75 AD3d at 409). Accordingly, the 5 1/2-month delay in disclaiming on this ground
was unreasonable as a matter of law.

THIS CONSTITUTES THE DECISION AND ORDER
OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.

ENTERED: MAY 29, 2012

CLERK

Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.