OAKWOOD OF CAMBRIDGE LLC V JAMES KAPSA
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
OAKWOOD OF CAMBRIDGE, L.L.C.,
UNPUBLISHED
May 20, 2010
Plaintiff-Appellee,
v
No. 289590
Wayne Circuit Court
LC No. 07-702577-CK
JAMES KAPSA and VERONICA KAPSA,
Defendants-Appellants.
Before: METER, P.J., and MURRAY and BECKERING, JJ.
PER CURIAM.
Defendants appeal as of right the trial court’s orders granting plaintiff’s motion for
summary disposition, awarding damages, and denying defendants’ motion for new trial and entry
of new judgment in this breach of contract action. We affirm insofar as the court found
defendants liable under the purchase agreement, but reverse the court’s orders awarding damages
and case evaluation sanctions, and denying defendants’ motion for a new trial and new entry of
judgment, and remand for proceedings consistent with this opinion.
I. BACKGROUND
The genesis of this case is the decision of defendants, James Kapsa and Veronica Kapsa,
to move from their home in Trenton to Brownstown Township to live closer to their daughter. In
February 2005, defendants entered into a building and purchase agreement with plaintiff to
construct a 3,400 square foot Rosewood model home within a block of their daughter’s house.
The building and purchase agreement between the parties, entered into on February 1, 2005,
called for a total purchase price of $357,990 in addition to mortgage and closing costs. Included
in the total cost were five $5,000 installment payments due upon signing and at various stages of
construction. Not included in the total cost were landscaping and flooring, which totaled
$50,000 and were required for issuance of the certificate of occupancy. Pursuant to the
agreement, closing was to occur within seven days of the issuance of that certificate.
Upon defendants’ obtaining pre-approval for a $300,000 mortgage, construction on the
home commenced. Undertaking such liability was of no grave concern to defendants at the time
they obtained the pre-approval, however. Indeed, both defendants were gainfully employed,
were receiving payments from their rental property (“Oakwood house”) that they planned to later
sell along with their current home in Trenton, and had $276,000 in “liquid assets” – $85,000 of
-1-
which was in savings and the remainder was in various 401(k) accounts.1 Defendants even
owned a classic corvette worth $15,000.
During the construction phase, defendants visited the house and met with plaintiff’s
president, Damiano Randazzo, numerous times. Over the course of these visits, defendants made
25 modifications to the original construction plan–all at additional expense. While Randazzo
ensured all changes were made, he mistakenly indicated in the building permit that under
construction was a 3,200 square foot Redwood model without air conditioning, and accidentally
submitted an energy analysis report pertaining to an Aspen model home. Notwithstanding,
construction continued in accordance with defendants’ plans.
Although Randazzo had initially estimated that construction would be complete by
Thanksgiving of 2005, the house was not finished until August 2006. It was also around that
time that defendants’ financial fortunes took a turn for the worst. In July of that year, defendants
paid their daughter’s $25,000 debt to the IRS when she lost her job. The following month, as a
result of his former employer’s bankruptcy, Mr. Kapsa’s pension was reduced by $1,400 and his
health benefits were eliminated. As a result, defendants took out a health insurance policy with a
$1,925 monthly premium. Additionally, Mr. Kapsa’s current employer reduced his working
hours that same month, and defendants were unable to sell their Oakwood house, which their
tenants had vacated, thus leaving defendants with a $1,000 monthly mortgage payment.
Notwithstanding, on August 29, 2006, defendants’ lender approved their loan for $300,000.
With the closing date of September 11, 2006, fast approaching, defendants participated in
the final walk-through of the home and signed the final walk-through document dated August 23,
2006, indicating defendants “found no items of concern.” The certificate of occupancy was
issued in due course on September 8, 2006. Mrs. Kapsa, however, maintained that the final
walk-through occurred “much earlier” than that date, which did not appear on the form when she
signed it. Nevertheless, sometime after the walk-through, according to Mrs. Kapsa, defendants
informed Randazzo that they were not prepared to close due to their financial situation and
inquired about entering into a land contract with plaintiff. Mrs. Kapsa elaborated that Randazzo
suggested in response that defendants take out another loan. Closing was rescheduled for
November 13, 2006. Despite these alleged conversations with Randazzo, defendants participated
in additional walk-throughs after September 11, 2006, and even requested additional changes to
the house. In Randazzo’s words, defendants appeared to be “waffling.” Additionally, Randazzo
testified that defendants did not inform him of their financial situation until all of defendant’s
additional minor changes were completed–a time he pegged as occurring sometime between
September and November 2006.
1
Mrs. Kapsa earned between $40,000 and $50,000 annually from ABC Warehouse, and Mr.
Kapsa earned an hourly wage at DTE Energy, in addition to his $3,500 monthly pension and
health benefits from Great Lakes Steel. Rental payments from the Oakwood house totaled
$1,000 per month.
-2-
By November 2006, defendants had discovered another house for sale in the subdivision
neighboring their daughter’s and entered into a purchase agreement for that home on November
3, 2006. Defendants applied for and received a $240,000 mortgage for that home and, after
providing a $60,000 down payment, closed on December 31, 2006. However, it was not until
Randazzo’s brother-in-law observed Mr. Kapsa coming out of the garage of the newly purchased
house, that Randazzo discovered defendants had purchased a different house. And although it is
unclear from the record when this discovery occurred, Randazzo noted that defendants failed to
attend the closing rescheduled at their request for November 13, 2006, and the second
rescheduled closing for November 22, 2006.
On January 29, 2007, plaintiff filed suit seeking specific performance or damages for
breach of contract.2 Defendants filed an answer and affirmative defenses, claiming, inter alia,
that the Rosewood house was not constructed in accordance with the purchase agreement,
impossibility precluded their performance, and plaintiff had failed to mitigate damages.
Following Randazzo’s deposition in June 2007, plaintiff eventually listed the Rosewood house
for resale in July 2007, seven months after filing the initial complaint. While the home was
listed for $319,000, it was sold to another buyer for $295,000 on August 4, 2007.
On January 25, 2008, plaintiff filed for summary disposition under MCR 2.116(C)(9)
(failure to state a valid defense) and (10) (no genuine issue of material fact), arguing that it was
entitled to damages where it had performed in compliance with the contract. Plaintiff
additionally contended that impossibility was not a viable defense to defendants’ failure to
perform since the alleged financial hardship occurred after the contract was executed, defendants
had already obtained a binding loan commitment, and the contract permitted defendants to
finance their purchase should they not qualify for a mortgage.
Defendants responded that because plaintiff failed to complete construction in accordance
with the contract, they were entitled to summary disposition under MCR 2.116(I)(2) (opposing
party entitled to summary disposition). Alternatively, defendants argued that plaintiff built the
house at its own risk since defendants failed to secure financing and the doctrine of impossibility
excused defendants’ performance.
At the summary disposition motion hearing of February 29, 2008, the parties contested
the issue of whether plaintiff, in fact, constructed the home for which the parties contracted, and
agreed that additional testimony was necessary to resolve this issue. Accordingly, the court
adjourned the proceedings for a bench trial.
Following two days of testimony, the court ruled that plaintiff had constructed the home
in accordance with the contract and that defendants’ claim of impossibility was meritless. With
respect to home construction, the court found that despite any typographical errors in the
building permit application, the floor plan as well as defendants’ inspections and walk-throughs
showed that the correct house was built. Regarding impossibility, the court initially
acknowledged the difficulty of economic downturns, but explained that defendants’ situation was
2
Plaintiff dropped its claim for specific performance after it sold the house to a different buyer.
-3-
one of inconvenience rather than impossibility given that they had sufficient funds in their
savings and retirement accounts, their income had not changed dramatically, and the purchase
price of their new home was only $50,000 or $60,000 less than the original Rosewood price.
Accordingly, the court granted plaintiff’s motion for summary disposition.
Concerning damages, the parties disputed whether the purchase agreement limited
damages to the amount plaintiff had collected under the contract, which amounted only to one
$5,000 installment payment. The court found that after the certificate of occupancy was issued,
defendants refused to participate in closing despite Randazzo’s efforts, and interpreting the
contract in light of Schneider v Levy, 256 Mich 184; 239 NW 326 (1931), the court ruled that
since enforcement of the liquidated damages clause was enforceable at plaintiff’s discretion,
plaintiff was permitted to pursue actual damages. Thus, the court awarded plaintiff $85,215 for
the difference between the contract price owed by defendants and the actual resale price and
$10,688.21 for the modifications made to sell the home.3
Defendants subsequently filed a motion for a new trial to amend the findings and for
entry of a new judgment on the grounds that the correct measure for damages was the difference
between the contract price and the market value of the land at the time of breach. The court
denied this motion on August 12, 2008, ruling that the actual resale price of the home was the
proper benchmark for damages given that there was no evidence of market value for the date of
the breach. The court also noted that defendants effectively forestalled breaching the contract
and that plaintiff was forced to sell under deteriorating market conditions. In addition, the court
awarded case evaluation sanctions to plaintiff in the amount of $13,520. An order was entered
reflecting this ruling on December 15, 2008. The instant appeal ensued.
II. ANALYSIS
A. IMPOSSIBILITY AND BREACH OF CONTRACT
Defendants contend that the court erred in not finding that the change in their financial
circumstances rendered their performance impossible as a matter of law and in finding that
plaintiff did not breach the purchase agreement. At the outset, we note that the trial court ruled
on these issues by way of granting plaintiff’s motion for summary disposition following a bench
trial. Regarding this procedural irregularity, MCR 2.116(I)(3) does permit an immediate trial to
resolve any disputed issues of fact in a motion for summary disposition provided the grounds
asserted in support of summary disposition are based on subrules (C)(1) through (7). The
relevant bases of plaintiff’s motion, however, were subrules (C)(9) and (10). Notwithstanding,
both parties agreed to proceed with a bench trial at the conclusion of the summary disposition
motion hearing, and importantly, the order granting summary disposition under subrule (C)(10)
was entered only after the trial court made findings of fact integral to granting that order. Given
3
The court, however, rejected plaintiff’s request for additional damages (including utilities,
maintenance fees, insurance, and interest) because it was not until defense counsel urged plaintiff
to mitigate damages at his deposition several months after litigation commenced that plaintiff
sought a new buyer for the home.
-4-
these circumstances, it is appropriate for this Court to review this case under the standard
appropriate for a bench trial. Beach v Lima Twp, 283 Mich App 504, 524 n 7; 770 NW2d 386
(2009). Therefore, we review the trial court’s findings of fact for clear error and its conclusions
of law de novo. Alan Custom Homes, Inc v Krol, 256 Mich App 505, 512; 667 NW2d 379
(2003), citing MCR 2.613(C).
1. IMPOSSIBILITY
The doctrine of impossibility may extinguish a party’s liability under a contract if
performance of the party’s promise becomes objectively impossible. Roberts v Farmers Ins
Exch, 275 Mich App 58, 73; 737 NW2d 332 (2007). Courts have classified impossibility into
two categories: original and supervening. Rogers, Plaza, Inc v SS Kresge Co, 32 Mich App 724,
743; 189 NW2d 346 (1971). Original impossibility exists when performance is promised that
was impossible at the time of the contract’s inception, whereas supervening impossibility
develops sometime after the parties entered into their contractual agreement. Id. In either event,
“absolute impossibility is not required,” however, “there must be a showing of impracticability
because of extreme and unreasonable difficulty, expense, injury or loss involved.” Roberts, 275
Mich App at 74. In this case, defendants only raise the issue of supervening impossibility.
Contrary to defendants’ argument, the facts of this case are legally insufficient to invoke
the doctrine of supervening impossibility. Indeed, despite the fact that defendants faced a
reduction in their monthly income and were unable to sell their Oakbrook home, it was
undisputed that their “liquid assets” of $276,000 were sufficient to supplement their mortgage
payments on the Rosewood home.4 And while a supervening event’s lack of foreseeability may
produce an impossibility sufficient to extinguish liability, Vergote v K Mart Corp (After
Remand), 158 Mich App 96, 110; 404 NW2d 711 (1987), under Michigan law “[s]ubsequent
events which in the nature of things do not render performance impossible, but only render it
more difficult, burdensome, or expensive, will not operate to relieve [a party of its contractual
obligations.]” Chase v Clinton Co, 241 Mich 478, 484; 217 NW 565 (1928).
Consistent with Chase, comment b to § 261 of the Restatement 2d of Contracts5
elaborates: “The continuation of existing market conditions and of the financial situation of the
4
Besides the approximate $85,000 difference in cost between the Rosewood house and the house
defendants actually purchased, defendants were also liable to plaintiff for $50,000 in flooring
and landscaping costs.
5
Restatement Contracts, 2d § 261 states:
Discharge of Supervening Impracticability
Where, after a contract is made, a party's performance is made impracticable
without his fault by the occurrence of an event the non-occurrence of which was a
basic assumption on which the contract was made, his duty to render that
performance is discharged, unless the language or the circumstances indicate the
contrary.
-5-
parties are ordinarily not such assumptions, so that mere market shifts or financial inability do
not usually effect discharge under the rule stated in this section.” Thus, although a nearretirement age couple tapping into their savings or retirement account prematurely is certainly
lamentable, it is not sufficient to relieve defendants of their contractual obligation to plaintiff
under these circumstances. The court, after making factual findings supported in the record, did
not err in ruling that there was no supervening impossibility as a matter of law.6
Defendants counter that they faced a “dramatic decrease in income” given that Mr. Kapsa
not only lost his pension and faced a reduction in his work hours, but also because they were
forced to purchase their own health insurance when his former employer went bankrupt. Despite
these difficulties, however, we would be remiss if we did not highlight that defendants–during
and after the onset of these problems–continued to request minor improvements to the Rosewood
home, voluntarily undertook their daughter’s $25,000 tax debt to the IRS, and purchased a new
home with a purchase price that was approximately $85,000 less than the home plaintiff
constructed. Given that defendants’ liquid assets totaled $275,000–a sum more than sufficient to
cover the difference in cost between the house they purchased and the Rosewood home with the
additional improvements–defendants’ claim of supervening impossibility is rendered entirely
untenable as a matter of law. Impossibility does not extinguish liability in this case.
2. BREACH OF CONTRACT
Alternatively, defendants argue that plaintiff’s action for breach of contract is
unsustainable where plaintiff was the first party to breach the contract. See Able Demolition, Inc
v City of Pontiac, 275 Mich App 577, 585; 739 NW2d 696 (2007) (a party who first breaches a
contract may not maintain an action against the other contracting party for his subsequent breach
provided the first breach was substantial).7 Specifically, defendants invoke the “first breach
rule” on two grounds: (1) the Township assessor measured the square footage of the home to be
3,088 square feet despite the parties’ agreement that the home be 3,400 square feet, and (2)
plaintiff obtained a certificate of occupancy whose validity rested upon plaintiff’s filing an
energy report pertaining to a different home. Defendants cannot prevail on either ground.
First, regarding the square footage of the home, plaintiff maintains that the area of the
house as constructed was actually around 3,480 square feet (a number that included plaintiff’s 25
modifications to the original building plan), and that the house, therefore, was built in conformity
with the agreement. The reason for the incongruity between the assessor’s measurement and the
agreed upon size of the home, plaintiff argues, is that the assessor’s measurement accounts only
6
Defendants incorrectly claim that one of the primary grounds for the court’s ruling was that
defendants had obtained a mortgage commitment for the Rosewood home. But while the court
did observe that that mortgage commitment suggested that defendants’ income had effectively
remained stable, the crux of the court’s ruling was that defendants’ finding a better deal and
refusal to withdraw from their savings and retirement accounts did not constitute an
impossibility.
7
Defendants concede on appeal that the trial court correctly ruled that plaintiff constructed a
Rosewood model home as called for in the purchase agreement.
-6-
for the floor area of the home–an area that necessarily excludes such features as bay windows
and interior walls. While the testimony in the record confirms that the assessor’s measurement
pertained only to floor area, plaintiff fails to cite–nor can we find–any evidence in the record
supporting plaintiff’s explanation of the incongruous measurements. This omission is in clear
violation of MCR 7.212(C)(7), which requires that “[f]acts stated must be supported by specific
page references to the transcript, the pleadings, or other document or paper filed with the trial
court.” What is more, plaintiff may not place the onus on this Court to scour the record to
factually support its claim. Derderian v Genesys Health Care Sys, 263 Mich App 364, 388; 689
NW2d 145 (2004).
In any event, defendants participated in numerous walk-throughs of the Rosewood home,
and while each minor problem they addressed was remedied, not once did defendants challenge
the size of the home. Moreover, even though Mrs. Kapsa disputed the date that she signed the
final walk-through document, defendants do not dispute their actual execution of that document,
which plainly indicated that defendants “found no items of concern.” In view of this, we
conclude that defendants waived any argument based upon a discrepancy in the square footage of
the home as constructed, and therefore defendants are without the refuge they seek at this
juncture. H J Tucker and Assoc, Inc v Allied Chucker & Engineering Co, 234 Mich App 550,
564; 595 NW2d 176 (1999), quoting Fitzgerald v Hubert Herman, Inc, 23 Mich App 716, 718719; 179 NW2d 252 (1970) (“A waiver may be shown by proof of express language of
agreement or inferably established by such declaration, act, and conduct of the party against
whom it is claimed as are inconsistent with a purpose to exact strict performance.”).
Second, with respect to the energy report and certificate of occupancy, while it is true that
Randazzo admitted to filing the wrong energy report when applying for the necessary building
permits, the certificate of occupancy was issued only after Brownstown Township inspectors
determined, after looking at every aspect of the Rosewood home’s construction, that the
construction complied with the state building codes. And defendants have failed to cite any
evidence in the record in support of their contention that the home was found compliant based on
the submission of the wrong energy report. Thus, reliance on the “first breach rule” is
unfounded.
B. DAMAGES
As their final assignment of error, defendants claim that the trial court incorrectly
calculated damages as the difference between the contract price and the price at which the house
eventually sold in August 2007. Defendants did not raise this issue on the grounds asserted on
appeal until their motion for new trial to amend the findings and for entry of a new judgment.8
We review a trial court’s denial of a motion for new trial for an abuse of discretion, which occurs
when the court’s decision falls outside the range of reasonable and principled outcomes.
McManamon v Redford Charter Twp, 273 Mich App 131, 138; 730 NW2d 757 (2006). To the
8
Defendants based their initial challenge to plaintiff’s claim for damages on the so-called
liquidated damages clause, which provided plaintiff the option to (1) retain the deposit for actual
costs incurred and render the agreement null and void or (2) to extend financing.
-7-
extent the court’s decision involved an issue of law or concerned its findings of fact, our review
is de novo or for clear error, respectively. Alan Custom Homes, Inc, 256 Mich App at 513.
“[W]here a vendor seeks to recover damages from the vendee pursuant to a contract for
the transfer of real property, the measure of damages is the difference between the contract price
and the market value of the land.” In re Day Estate, 70 Mich App 242, 246; 245 NW2d 582
(1976), citing Calamari and Perillo, Contracts, § 231, p 365. Market value means the market
value as of the date of breach as opposed to the price the vendor later obtained on resale. Id. at
246-247. “Where there is some evidence of the market value of the property around the time of
the breach, the fact finder should weigh all the evidence in an effort to make a reasonable
determination of market value and, hence, damages.” McNeal v Tuori, 107 Mich App 141, 147;
309 NW2d 588 (1981). However, if “evidence of resale price is the only evidence of market
value, the plaintiff has the burden of establishing that resale occurred within a reasonable time, at
the highest price obtainable, under terms as favorable as the original contract, and that there has
not been a decline in market value.” Id.
Here, while plaintiff presented evidence of the damages it sustained, the trial court
seemed to indicate that no evidence was presented establishing the market value of the house at
the date of the breach other than the price at which the home actually sold.9 In setting the market
value at the resale price, however, the trial court failed to consider whether plaintiff bargained
for the highest price obtainable under terms as favorable as the original contract. Moreover,
while the court noted that plaintiff attempted to resell the house shortly after discovering that
defendants had reneged on the purchase agreement, such a finding contradicts its prior decision
denying plaintiff’s request for additional damages on the grounds that plaintiff failed to
adequately mitigate damages. As the court explained at the damages hearing:
[T]he court is not going to allow any of [plaintiff’s additional] damages . .
. based on the testimony that plaintiff really took no affirmative action in
attempting to mitigate damages until [Randazzo] was forewarned about mitigation
or apprised to mitigation by defense counsel during a deposition, some seven or
eight months after institution of this litigation. And within two weeks of actively
trying to secure a buyer in this property, the property was, in fact, sold, albeit at a
reduced price . . . .10
So those damages are all a result of the delay in the sale from the time of
the original closing until it was ultimately sold, which . . . in this court’s opinion,
are due to the failure to mitigate appropriately in this matter. [Footnote supplied.]
9
We note that defendants attached an appraisal of the Rosewood house, dated September 6,
2006, to their motion for new trial and asserted that was sufficient evidence of market value as of
the date of breach. However, defendants could have submitted the appraisal at trial, and
therefore, the court did not err in failing to consider it. MCR 2.611(A)(1)(f).
10
At Randazzo’s deposition of June 14, 2007, defense counsel inquired into whether Randazzo
had attempted to mitigate damages.
-8-
The trial court’s finding in this respect is significant because it is inconsistent with (1) its
later finding at the hearing on defendants’ motion for a new trial that plaintiff placed the house
back on the market shortly after discovering defendants would not purchase the Rosewood house
and (2) the showing required under McNeal that the resale occurred within a reasonable time.
When this inconsistency is considered in conjunction with the court’s failure to consider the
other required showings noted previously, we cannot conclude that the court’s denial of
defendants’ motion for a new trial fell within the range of reasonable and principled outcomes.
Additionally, it is unclear that no evidence existed to establish fair market value other
than the resale price as the trial court seemed to indicate. Of particular note on this point is that
the court made no finding on whether the house purchased was comparable to the Rosewood
house. Indeed, if that were the case, the court’s findings that defendants took advantage of a
“slumping” housing market and that plaintiff was forced to sell the home in deteriorating market
conditions, considered in conjunction with the sale price of the purchased house and the resale
price of the Rosewood house, would be good indicators of the fair market value of the Rosewood
house as of the date of breach.11 And of course in that event, the resale price would not be the
only evidence of fair market value as the court seemed to indicate. Without a finding with
respect to the comparability of the homes, however, the court’s findings regarding defendants’
opportunism and a deteriorating market would be insufficient in and of themselves because any
determination of fair market value would be merely speculative.
Finally, we note that the court’s finding as to the exact date of breach is unclear. In
particular, the court only indicated that there was “a strong argument that suggest[s] the breach
occurred in November or December when [defendants] failed to appear for that last closing [of
November 22, 2006].” But the court never made a specific finding of the breach date. In re Day
Estate, 70 Mich App at 246-247. In light of the foregoing, we conclude the court’s denial of the
motion for a new trial was an abuse of discretion.
III. CONCLUSION
We affirm the court’s order finding defendants liable under the purchase agreement.
However, in light of the court’s contradictory and incomplete findings underlying its
determination that the resale price was the fair market value at the time of the breach, we reverse
the court’s award of damages and case evaluation sanctions as well as the order denying
defendants’ motion for new trial and entry of new judgment, and remand for reconsideration and
specific findings of fact on the issue of damages in light of this opinion. In remanding this case,
we are of the same mind as the McNeal Court, and “intimate no view regarding the conclusion to
be drawn by the circuit court after weighing all the evidence, that is, the trial judge must still
determine which, if any, evidence is credible in establishing market value, [and] whether the
market value of the property at the time of breach exceeded, equalled, or fell short of the contract
11
While evidence existed on this point, the court failed to address the issue. Specifically,
Randazzo testified that the two houses were essentially comparable and noted that the house
purchased was in foreclosure. However, he also testified that he had not been inside the house
purchased and was unaware of whether the house had comparable flooring or landscaping.
-9-
price.” McNeal, 107 Mich App at 148. We leave it to the trial court as to whether additional
evidence is necessary to decide the damages issue.
We do not retain jurisdiction.
No costs, neither party having prevailed in full. MCR 7.219(A).
/s/ Christopher M. Murray
/s/ Patrick M. Meter
/s/ Jane M. Beckering
-10-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.