ALLEN LANGFORD V JENKINS CONSTRUCTION INC
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
ALLEN LANGFORD, as Next Friend for
PATRINA LANGFORD, a Minor,
UNPUBLISHED
June 23, 2009
Plaintiff,
v
JENKINS CONSTRUCTION, INC., TMP
ASSOCIATES, GEORGE COHEN, DETROIT
PUBLIC SCHOOLS, CASS TECHNICAL HIGH
SCHOOL, DETROIT PUBLIC SCHOOLS
PROGRAM MANAGER, L.L.C., QUICK
GREEN, B & L LANDSCAPING, and BECKETT
& RAEDER, INC.,
No. 285915
Wayne Circuit Court
LC No. 06-604007-NO
Defendants,
and
ABC PAVING COMPANY, INC.,
Defendant/Third-Party PlaintiffAppellant/Cross-Appellee,
v
INDUSTRIAL FENCE & LANDSCAPE,
Third-Party DefendantAppellee/Cross-Appellant.
Before: Fitzgerald, P.J., and Talbot and Shapiro, JJ.
PER CURIAM.
Defendant/Third-Party Plaintiff, ABC Paving Company, Inc. (“ABC”) appeals as of right
the trial court’s grant of summary disposition in favor of Third-Party Defendant, Industrial Fence
& Landscape (“Industrial”) in this contract dispute regarding the applicability of an
-1-
indemnification provision. Industrial cross-appeals contending its contract with ABC is void
based on fraud. We vacate in part, affirm in part and remand to the trial court.
This litigation arises from an injury incurred by the minor plaintiff, Patrina Langford,
while performing as a cheerleader for Cass Technical High School at a game on their football
field. Patrina was injured when her hand slipped into a depression in the field resulting in her
falling and injuring her arm. Plaintiff sued the school and related entities in addition to the
contractors and subcontractors involved in construction of the school and its football field
asserting defects in its construction, design and inspection.
At the outset, it is necessary to delineate the relationship between the pertinent
contractors and subcontractors. Jenkins Construction, Inc. (“Jenkins”) served as the general
contractor and construction manager for the Cass Technical High School project. Jenkins
subcontracted construction of the football field (referred to as Bid Package 14 – Category I) to
ABC. ABC was responsible for laying out the field and placement of topsoil for later installation
of sod. In turn, ABC subcontracted the installation of the sod to Industrial. Subsequently,
Industrial subcontracted installation of the sod to Quick Green, which then subcontracted the job
to B & L Landscaping (“B & L”).
The contract between Jenkins and ABC required, in pertinent part, that ABC “furnish all
labor, equipment, tools, supervision, materials and appurtenances as necessary to properly
furnish and install the work described in Bid Package 14 category I – Athletic Fields.” The
contract was amended to provide for the furnishing and installation of sod for the football field
rather than hydroseeding. In late 2004, Jenkins contacted ABC regarding issues involving the
acceptability of the soil provided by ABC for the football field. Purportedly, Beckett & Raeder,
Inc. tested the topsoil used by ABC and determined that it was not up to specification. ABC
asserts it could not have breached any soil specifications because they were not delineated in the
bid package. Although ABC contends the dispute with Jenkins regarding the quality and
placement of the topsoil was resolved before ABC subcontracted with Industrial for installation
of the sod, questions pertaining to Jenkins actual acceptance of the product provided by ABC is
challenged by Industrial in its assertion of a fraud claim for failure to disclose this dispute on
cross appeal.
A subcontract dated May 2, 2005, was drafted between Industrial and ABC for
installation of sod on the football field. For a total payment of $40,000, Industrial was to
“[p]rovide all labor, equipment, tools, materials, transportation, supervision and all else
necessary for the complete sod installation on the above referenced project per plans &
specifications.” The pertinent indemnification language, which is the subject of this appeal,
provided:
The Subcontractor agrees to hold harmless and protect the Prime Contractor and
the Owner against all suits and claims for all damages or injuries to any persons
or property arising out of any of his work, materials, supplies, subcontracts,
employees or any other source.
Industrial contends, from the outset, it was understood that it would not actually install the sod
because ABC had previously selected Quick Green to perform this task. Industrial asserts its
subcontract with ABC constituted a mere formality to meet ABC’s need to have a minority or
-2-
female-owned business involved in the project and that there was never an intention to have
Industrial perform any work pursuant to the subcontract. The subcontract between Industrial and
Quick Green for sod installation is dated May 19, 2005.
On October 17, 2007, Quick Green brought a motion seeking summary disposition
asserting the absence of a duty to plaintiff and lack of a genuine issue of material fact
establishing their negligence was a proximate cause of plaintiff’s injury. The trial court granted
Quick Green’s motion dismissing plaintiff’s claims against it in their entirety. On October 25,
2007, the trial court denied Industrial’s motion for summary disposition asserting fraud in the
inducement, which was premised on disputes between ABC and Jenkins regarding the
acceptability of the topsoil provided by ABC for the football field. Subsequently, the trial court
granted Industrial’s motion for summary disposition of the third-party complaint based, in part,
on its prior determination that Quick Green was not liable and their dismissal from the case. On
May 19, 2008, the trial court entered a stipulated order disposing of all pending claims between
the remaining parties.
On appeal, ABC asserts the trial court erred in granting summary disposition in favor of
Industrial, misinterpreting the applicability of the indemnity provision in the subcontract with
ABC. This Court reviews de novo a trial court’s decision to grant or deny summary disposition.
Maiden v Rozwood, 461 Mich 109, 118; 597NW2d 817 (1999). This Court also reviews de novo
the interpretation of a contract as a question of law, including whether the contractual language is
ambiguous and necessitates resolution by the trier of fact. Mahick v Bell Co, 256 Mich App 154,
159; 662 NW2d 830 (2003). A contract that is not ambiguous must be enforced in accordance
with its terms. Wilkie v Auto-Owners Ins Co, 469 Mich 41, 51-52; 664 NW2d 776 (2003).
The subcontract between ABC and Industrial contained an express provision for
indemnification. “Where parties have expressly contracted with respect to the duty to indemnify,
the extent of the duty must be determined from the language of the contract.” Grand Trunk
Western R, Inc v Auto Warehousing Co, 262 Mich App 345, 353; 686NW2d 756 (2004). “An
indemnity contract is construed in the same manner as other contracts.” DaimlerChrysler Corp v
G-Tech Professional Staffing, Inc, 260 Mich App 183, 185; 678 NW2d 647 (2003). In general,
an indemnification provision or contract is strictly construed against the drafting party and the
indemnitee. Triple E Produce Corp v Mastronardi Product, Ltd, 209 Mich App 165, 172; 530
NW2d 772 (1995). However, as with other types of contracts, the principle of construing an
indemnification contract against the drafter only applies when (a) there exists an ambiguity and
(2) all other means of construing the ambiguity have been exhausted. See Klapp v United Ins,
468 Mich 459, 470-474; 663 NW2d 447 (2003). Hence, “[a]n unambiguous written indemnity
contract must be enforced according to the plain and ordering meaning of the words used in the
instrument.” DaimlerChrysler, supra at 185. On appeal, this Court interprets an indemnification
provision in a manner that will serve to provide a reasonable meaning to all of the terms
contained therein. MSI Construction Mgrs, Inc v Corvo Iron Works, Inc, 208 Mich App 340,
343; 527 NW2d 79 (1995). In essence, an indemnification provision is to be construed to
effectuate the intentions of the parties to the contract. The parties’ intent is determined through
review of the contract language, the parties’ situation and circumstances involved in the initiation
of the contract. Triple E Produce Corp, supra at 172.
The indemnification provision in the subcontract between ABC and Industrial provides:
-3-
The Subcontractor agrees to hold harmless and protect the Prime Contractor and
the Owner against all suits and claims for all damages or injuries to any persons
or property arising out of any of his work, materials, supplies, subcontracts,
employees or any other source.
Contrary to the implication of the trial court’s ruling, the indemnification language is very broad
in that it permits indemnification for “all suits and claims for all damages or injuries” and does
not require proof of actual negligence for the provision to take effect.1 Clearly, plaintiff’s
complaint alleges, in several different paragraphs, that her injury is in part related to defects in
the sod or its installation on the subject football field. Consequently, ABC is correct in asserting
that the trial court’s determination of negligence with regard to Quick Green is irrelevant in
construing or applying this provision. All that is required, pursuant to the plain language of the
indemnification provision is that the claim or suit arises from the work performed, but does not
require that such work be done in a negligent manner.
Further, in determining whether the indemnification provision is implicated, assertions
pertaining to ABC’s negligence are also irrelevant as the contract language specifies that liability
arise “out of any of his work, materials, supplies, subcontracts, employees or any other source.”
Clearly, the “his” referenced is Industrial. Although it is undisputed that Industrial did not
perform or provide any “materials, supplies” or “employees” with regard to the installation of the
sod that is not dispositive with regard to application of the provision. Industrial did have a
“subcontract” with Quick Green, which would cause the provision to be effectuated.
Because of deficiencies pertaining to the content of the lower court record, it cannot be
definitively ascertained whether Quick Green actually performed any work with regard to the
sod installation or merely subcontracted the entire job to B & L. However, whether any work
performed by Quick Green was negligent is irrelevant. Hence, this Court finds that the trial
court’s grant of summary disposition in favor of Industrial regarding the application of the
indemnity provision was premature until a determination was definitively made regarding Quick
Green’s acts in conformance with its subcontract with Industrial giving rise to plaintiff’s claims
and the implementation of the indemnification provision. In the alternative, it may be assumed
that the trial court’s grant of summary disposition in favor of Quick Green based, presumably, on
the absence of any negligence, is indicative that Quick Green did perform certain acts or services
in furtherance of the sod installation and, thus, is sufficient for implementation of the
indemnification provision as arising from its subcontract of Industrial. Under either scenario,
this matter requires remand back to the trial court.
We further note that in its appellate brief, Industrial also contends that its subcontract
should be rescinded or deemed unenforceable based on a lack or failure of consideration. ABC
replies that the subcontract was a “pay when paid” agreement and that because ABC did not
receive payment from Jenkins, ABC was not required to remit payment to Industrial. A review
of the lower court record does not disclose any rulings by the trial court regarding either the
1
In addition, the wording that liability for claims or suits can arise from “any other sources”
related to Industrial is indicative of the broad scope or nature of this language.
-4-
factual assertions of the parties or their legal position. Thus, the record is insufficient for this
Court’s review.
On cross-appeal, Industrial contends that its subcontract with ABC, along with the
indemnification provision contained therein, should be rescinded or voided based on either fraud
in the inducement or material misrepresentations related to the failure of ABC to disclose
concerns and ongoing disputes pertaining to the quality of the topsoil provided on the football
field prior to the sod installation. To prove fraudulent misrepresentation it must be
demonstrated:
(1) the defendant made a material misrepresentation; (2) the representation was
false; (3) when the defendant made the representation, the defendant knew that it
was false, or made it recklessly, without knowledge of its truth or falsity, and as a
positive assertion; (4) the defendant made the representation with the intention
that the plaintiff would act on it; (5) the plaintiff acted in reliance on the
representation; and (6) the plaintiff suffered damage. [Campbell v Sullins, 257
Mich App 179, 195; 667 NW2d 887 (2003).]
Based on the pleadings, Industrial’s claim must fail. At no point does Industrial ever allege that
ABC affirmatively represented or made any statement to indicate the quality of the topsoil. In
fact, the basis for Industrial’s complaint is clearly that ABC failed to disclose the dispute
pertaining to the topsoil, not that it affirmatively misrepresented its quality or condition.
This Court, in Rooyakker & Sitz, PLLC v Plante & Moran, PLLC, 276 Mich App 146,
161-162; 742 NW2d 409 (2007), citing Custom Data Solutions, Inc v Preferred Capital, Inc, 274
Mich App 239, 242-243; 733 NW2d 102 (2006), discussed the requirements for establishment of
a fraud in the inducement claim:
“[I]n general, actionable fraud must be predicated on a statement relating to a past
or an existing fact.” Samuel D Begola Services, Inc v Wild Bros, 210 Mich App
636, 639; 534 NW2d 217 (1995). However, “Michigan also recognizes fraud in
the inducement . . . [which] occurs where a party materially misrepresents future
conduct under circumstances in which the assertions may reasonably be expected
to be relied upon and are relied upon.” Id. To establish . . . fraud in the
inducement, a party must show that
“(1) the defendant made a material representation; (2) the representation was
false; (3) when the defendant made the representation, the defendant knew that is
was false, or made it recklessly, without knowledge of its truth and as a positive
assertion; (4) the defendant made the representation with the intention that the
plaintiff would act upon it; (5) the plaintiff acted in reliance upon it; and (6) the
plaintiff suffered damage.” [Belle Isle Grill Corp v Detroit, 256 Mich App 463,
477; 666 NW2d 271 (2003) (citation omitted).]
In addition, “‘fraud in the inducement to enter a contract renders the contract voidable at the
option of the defrauded party.’” Rooyakker, supra at 162, citing Custom Data Solutions, supra
at 243, quoting Samuel D Begola Services, supra at 640. As with Industrial’s companion claim,
its assertion of fraud in the inducement cannot be sustained based again on the absence of any
-5-
actual misrepresentation. Further, Industrial contracted to install sod on topsoil provided by
ABC and, hence, was reliant on the quality and appropriateness of that topsoil for the success of
its own performance under the subcontract. As such, any purported reliance on ABC’s silence
regarding the topsoil is patently unreasonable, particularly given that each party to the
subcontract was a sophisticated business entity and it is assumed each had previously performed
similar contractual obligations and were aware of the risk involved.
In actuality, Industrial’s claim is more consistent with an assertion of silent fraud. To
establish a claim for silent fraud, Industrial must demonstrate that ABC suppressed a material
fact, which it had a legal or equitable duty to disclose. M & D, Inc v McConkey, 231 Mich App
22, 28-29; 585 NW2d 33 (1998). Further, “there must be some type of misrepresentation, either
by words or by action.” Id. at 36. Again, Industrial merely asserts the existence of the duty to
disclose but fails to elucidate any misrepresentation made spontaneously by ABC or in response
to questioning by Industrial. As such, Industrial’s cross-appeal cannot be sustained.
We affirm the trial court’s denial of summary disposition regarding Industrial’s claims of
fraud. We vacate the trial court’s ruling granting summary disposition in favor of Industrial and
remand to the trial court for further proceedings consistent with this opinion. We do not retain
jurisdiction.
/s/ E. Thomas Fitzgerald
/s/ Michael J. Talbot
-6-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.