WAFA ANTON V BRYNMAWR CONDOMINIUM ASSN
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
WAFA ANTON,
UNPUBLISHED
May 22, 2007
Plaintiff/Counter-DefendantAppellant,
No. 265828
Oakland Circuit Court
LC No. 2001-033436-CZ
v
BRYNMAWR CONDOMINIUM
ASSOCIATION,
Defendant/Counter-Plaintiff/ThirdParty Plaintiff-Appellee/CrossAppellee,
and
SIGNAL BUILDING COMPANY,
Third-Party DefendantAppellee/Cross-Appellant.
Before: Owens, P.J., and Neff and White, JJ.
PER CURIAM.
Plaintiff Wafa Anton appeals as of right the trial court’s order granting her equitable
relief instead of money damages for unsatisfactory repairs to her condominium. We affirm in
part and reverse in part. Plaintiff also appeals as of right the trial court’s award of $13,443.34 to
defendant Brynmawr Condominium Association (Brynmawr) on its counterclaim for unpaid
assessment fees. We affirm. Finally, plaintiff appeals as of right the trial court’s order
overturning its previous ruling granting her case evaluation sanctions. We reverse. On cross
appeal, defendant Signal Building Company (Signal) appeals as of right the trial court’s order
denying its motion for dismissal. Signal also appeals as of right the trial court’s findings that its
repairs of plaintiff’s condominium were substandard or defective. We affirm in both instances.
I. Facts
Plaintiff owns a condominium unit in a complex governed by Brynmawr in
West Bloomfield Township, Michigan. On May 3, 1999, plaintiff’s condominium unit was
damaged in a fire. Brynmawr held a policy insuring the condominium complex from fire
damage. Plaintiff did not have a separate insurance policy covering damage to her
-1-
condominium. Apparently, Brynmawr was reimbursed for fire damage to plaintiff’s unit and to
common elements in the complex. Brynmawr hired Signal to repair the damage.
After Signal completed the repairs, plaintiff claimed that the repair work was
substandard. On May 9, 2001, plaintiff filed a cause of action against Brynmawr to recover
approximately $22,000 in money damages, noting 49 specific instances in which she demanded
compensation for substandard work. Notably, plaintiff claimed that repairs to items located both
outside and inside her unit were substandard. Brynmawr subsequently filed a third-party claim
for indemnification against Signal.
After a bench trial, the trial court found that plaintiff established that substandard repairs
occurred in 31 specific instances and granted equitable relief in lieu of money damages. The
trial court did not determine whether each damaged item was a common element controlled by
Brynmawr or was part of the unit owned by plaintiff. The trial court also held that Signal was
liable to Brynmawr for all but four of the instances of substandard work.
In March 2001, after defendant returned plaintiff’s monthly payments on the ground that
they did not cover the entire amount owed, plaintiff ceased paying her condominium association
fees. Brynmawr recorded a lien against her unit and, on July 2, 2001, filed a counterclaim to
collect the unpaid fees.
After considering Brynmawr’s motion for summary disposition, the trial court
determined that plaintiff was liable for the unpaid condominium association fees, but concluded
that the extent of her liability was a disputed issue for trial. Although the trial court ruled on this
motion on January 23, 2002, plaintiff failed to make additional association fee payments during
the pendency of the trial. By April 7, 2003, plaintiff owed $13,443.34 in unpaid assessments,
fees, and interest. The trial court awarded Brynmawr this amount on its counterclaim.
The parties had submitted this case for evaluation on February 14, 2002. The case
evaluation valued plaintiff’s claim at $2,500 and Brynmawr’s claim at $5,000. Neither plaintiff
nor Brynmawr accepted the case evaluation. When plaintiff was awarded equitable relief in the
bench trial, the parties agreed to assign a stipulated value of at least $4,500 for this award.
Plaintiff then moved for case evaluation sanctions against Brynmawr, claiming that she
obtained a verdict that was at least ten percent more favorable to her than the case evaluation.
The parties stipulated that, on the date of the case evaluation, Brynmawr’s counterclaim was
worth $6,235.34. At the January 14, 2004, hearing on this motion, the trial court concluded that
plaintiff improved her position by more than ten percent and, pursuant to MCR 2.403(O), she
was entitled to sanctions against Brynmawr. However, the presiding judge died before signing
the order granting plaintiff’s request for sanctions. On April 14, 2005, after a new judge was
assigned to the case, the trial court signed the order granting plaintiff case evaluation sanctions
for the reasons included on the record in the January 14, 2004 hearing.
-2-
Brynmawr moved for reconsideration of this order. The trial court granted this motion,
finding that a “net evaluation” method should have been used to determine whether the verdict
was more favorable than the case evaluation.1 The trial court subtracted $4,500 as the stipulated
value of plaintiff’s award of equitable relief from the $13,443.34 award on the counterclaim to
calculate a net verdict of $8,943.34 in favor of Brynmawr. Because the net verdict exceeded the
$2,500 net evaluation award for Brynmawr, the trial court concluded, plaintiff was not entitled to
case evaluation sanctions.
II. Appropriateness of Relief Granted
First, plaintiff claims that the trial court erroneously granted equitable relief for her claim
of defective repairs when she requested relief in the form of damages. We agree in part.
Pursuant to the terms of the association’s bylaws, plaintiff should have received money damages
to compensate for defective repairs to her condominium unit. However, equitable relief was
appropriate to address defective repairs to the common elements of the condominium project.
A condominium is “[a] single real-estate unit in a multi-unit development in which a
person has both separate ownership of a unit and a common interest, along with the
development’s other owners, in the common areas.” Black’s Law Dictionary (8th ed). The coowner of a condominium “has an exclusive right to his condominium unit and has such rights to
share with other co-owners the common elements of the condominium project as are designated
by the master deed.”2 MCL 559.163. A “condominium unit” is “that portion of the
condominium project designed and intended for separate ownership and use, as described in the
master deed . . . .” MCL 559.104(3). The “common elements” consist of “the portions of the
condominium project other than the condominium units.” MCL 559.103(6).
Co-owners are required to comply with the terms of the master deed and the association
bylaws. MCL 559.165. Pursuant to MCL 559.156(c), the bylaws may contain provisions “[f]or
insuring the co-owners against risks affecting the condominium project, without prejudice to the
right of each co-owner to insure his condominium unit or condominium units on his own account
and for his own benefit.”
A copy of the master deed for plaintiff’s condominium unit is not included with the trial
court record. However, the trial court admitted a copy of Brynmawr’s bylaws in evidence. The
bylaws indicate that Brynmawr is responsible for the management, maintenance, operation, and
administration of the common elements in accordance with the terms of the bylaws and the
master deed. Specifically, Brynmawr is responsible for “rebuild[ing] improvements after
casualty, subject to the terms” of the bylaws.
1
The trial court defined “net evaluation” as “the difference between an award on a party’s claim
and the counterclaim against that party.”
2
In the Condominium Act, MCL 559.101 et seq, a “co-owner” refers to the owner of a
condominium unit within a condominium project. MCL 559.106(1).
-3-
Further, the bylaws require Brynmawr to insure the common elements of the complex
against fire. Article IV, Section 1, Subsection B of the bylaws provides as follows:
All Common Elements of the Condominium shall be insured against fire
and other perils covered by a standard extended coverage endorsement, in an
amount equal to the maximum insurable replacement value, excluding foundation
and excavation costs, as determined annually by the Board of Directors of the
Association in consultation with its appropriate professional advisors. Such
coverage may also include interior walls within any Unit and the pipes, wires,
conduits and ducts contained therein and shall further include all fixtures,
equipment, doors and trim within a Unit which were furnished with the Unit as
standard items, in accord with the plans and specifications for the Project on file
with the Township of West Bloomfield, or such replacements thereof as do not
exceed the cost of such standard items. Such fixtures, equipment and trim are to
consist of standard bathroom and kitchen fixtures, countertops and cabinets, but
shall specifically exclude appliances, water heaters, heating and air conditioning
equipment, wallcovering and floor covering. Any improvements or items
installed in addition to such standard items, regardless of by whom installed, shall
be covered by insurance obtained by and at the expense of the individual Coowners . . . .
The parties do not dispute that Brynmawr insured the common elements of the condominium
project from fire damage, or that Brynmawr was reimbursed for damage caused by the fire.
Article IV, Section 1, Subsection D of the bylaws governs the distribution of policy
proceeds. This subsection states:
Proceeds of all insurance policies owned by the Association shall be
received by the Association, held in a separate account and distributed to the
Association, the Co-owners and their mortgagees as their interests may appear;
provided, however, whenever repair or reconstruction of the Condominium shall
be required as provided in Article V of these bylaws, the proceeds of any
insurance received by the Association as a result of any loss requiring repair or
reconstruction shall be applied for such repair or reconstruction, and in no event
shall hazard insurance proceeds be used for any purpose other than for repair,
replacement or reconstruction of the Condominium unless all of the institutional
holders of first mortgages or Units in the Condominium have given their prior
written approval.
According to these terms, when Brynmawr receives proceeds from a policy, it is responsible for
distributing the proceeds to the proper party. Notably, the bylaws require that the insurance
proceeds recovered by Brynmawr as the result of a loss requiring repair or reconstruction shall
be used to repair or reconstruct the damaged item.
However, Brynmawr is not directly responsible for repairing and reconstructing
everything in the complex. Article V, Section 3, Subsection A of the bylaws specifies the
following:
-4-
If the damage is only to a part of a Unit or common elements which are
the responsibility of a Co-owner to maintain and repair and/or insure, it shall be
the responsibility of the Co-owner to repair such damage in accordance with
Subsection B hereof. In all other cases, the responsibility for reconstruction and
repair, although not necessarily the costs thereof, shall be that of the Association.
Accordingly, the responsibility for repairing and reconstructing damage in the complex is
divided between Brynmawr and the co-owners. Article V, Section 3, Subsection B of the bylaws
identifies as follows the items for which a co-owner is responsible for repairing:
Regardless of the cause or nature of any damage or deterioration, each Coowner shall be responsible for the reconstruction and repair of the interior of the
Co-owner’s Unit and all personal property, including, but not limited to, floor
coverings, window shades, draperies, interior walls (but not any Common
Elements therein), wall coverings, interior trim, furniture, light fixtures, all
appliances, whether freestanding or built-in. In the event damage to interior walls
within a Co-owner’s Unit or to pipes, wires, conduits, ducts or other Common
Elements therein is covered by insurance held by the Association, then the
reconstruction or repair shall be the responsibility of the Association in
accordance with Section 4 of [Article V], although the responsibility for costs
thereof shall be allocated in accordance with the provisions of this Section and
Section 4. In no event shall the Association be responsible for restoration of more
than finished, unpainted drywall in the case of damage to ceilings and walls which
are the responsibility of the Association under this Article. If any other interior
portion of a Unit is covered by insurance held by the Association for the benefit
of the Co-owner, the Co-owner shall be entitled to receive the proceeds of
insurance relative thereto, (but the Co-owner shall be responsible for any
deductible amount), and if there is a mortgagee endorsement, the products shall be
payable to the Co-owner and the mortgagee jointly. In the event of substantial
damage to or destruction of any Unit or any part of the Common Elements, the
Association promptly shall so notify each institutional holder of a first mortgage
lien on any Unit in the Condominium.
Article V, Section 4 of the bylaws identifies as follows the items for which Brynmawr is
responsible for repairing:
Subject to the responsibility of the individual Co-owners as outlined in
[Article V, Section 3], and other provisions of these Bylaws or the Amended and
Restated Master Deed applicable to such situations, the Association shall be
responsible for the reconstruction and repair of the Common Elements. In no
event shall the Association be responsible for any damage to the contents of a
Unit and/or any personal property of any Co-owner or Limited Common
Elements for which the Co-owner has responsibility. Immediately after a casualty
causing damage to property for which the Association has the responsibility of
repair and reconstruction, the Association shall obtain reliable and detailed
estimates of the cost to replace the damaged property in a condition as good as
that existing before the damage.
-5-
These bylaws indicate that Brynmawr is primarily responsible for repairing and
reconstructing damaged common elements and, presumably, may receive insurance proceeds to
cover the costs of these repairs. Conversely, if covered, the bylaws require Brynmawr to
distribute insurance proceeds to a co-owner to cover the cost of repairs and reconstruction for
which the co-owner is responsible. Therefore, Brynmawr properly used insurance proceeds to
repair common elements damaged in the fire. To the extent that the repairs to the common
elements were substandard, plaintiff is not entitled to money damages. Instead, an award
granting equitable relief, by specifically requiring Brynmawr to address and fix lingering
deficiencies to the common elements caused by the fire is appropriate.
However, plaintiff was entitled to receive the insurance proceeds covering items and
repairs for which she had responsibility pursuant to the bylaws. Instead of directly repairing
damage for which she was responsible, Brynmawr should have distributed insurance proceeds to
plaintiff to cover these repairs. Because Brynmawr was not required to directly repair damage
for which plaintiff was responsible, Brynmawr is also not required to repair lingering
deficiencies to these items. However, Brynmawr must reimburse plaintiff for these substandard
repairs. Accordingly, plaintiff is entitled to receive money damages to address deficiencies in
portions of the condominium that she is responsible for repairing and reconstructing.
The bylaws do not identify the common elements of the complex or describe the
individual property rights held by each co-owner. Instead, the bylaws indicate that the
provisions of the amended and restated master deed govern the meanings and identifications of
these terms. Because a copy of the master deed is not included in the trial court record, we are
unable to determine whether Brynmawr or plaintiff is responsible for repairing each of the
31 instances in which the trial court concluded that repairs were substandard. Accordingly, we
remand to the trial court to determine, based on the terms of the master deed and the bylaws,
whether plaintiff should receive equitable relief (specifically, specific performance to address
lingering deficiencies) or money damages in each of the 31 identified instances in which the
repairs in question were substandard.3
III. Liability for Unpaid Assessments
Next, plaintiff argues that the trial court clearly erred when it ordered her to pay
Brynmawr $13,443.34 in unpaid association assessments, late fees, and interest, and that she
should only be ordered to pay $10,496 in unpaid assessments and fees. Specifically, plaintiff
argues that she was not responsible for an August 1, 2000, assessment for $600 because the
association never provided her with justification or explanation for it. Further, plaintiff argues
that the association forfeited any right to collect late fees on the assessment payments when it
refused to accept her monthly payments and returned her checks to her. We disagree.
We review a trial court’s factual findings for clear error. Christiansen v Gerrish Twp,
239 Mich App 380, 387; 608 NW2d 83 (2000). “‘A finding is clearly erroneous when, although
3
We note that the question whether the court should award money damages or equitable relief
was not raised until after the proofs had been completed.
-6-
there is evidence to support it, the reviewing court on the entire record is left with a definite and
firm conviction that a mistake has been committed.’” Id. at 387, quoting Vivian v Roscommon
Co Bd of Comm’rs, 164 Mich App 234, 238-239; 416 NW2d 394 (1987), aff’d 433 Mich 511
(1989).
The trial court did not clearly err when it included the disputed late fees and assessments
in its calculations and awarded Brynmawr $13,443.34 in unpaid assessments and fees. First, the
bylaws authorize Brynmawr to impose additional assessments at its discretion. Brynmawr
established the legitimacy of the disputed $600 additional assessment through authenticated
business records. An agent of Brynmawr also testified that the additional assessment was levied
against co-owners in the association. Plaintiff is obligated to pay this assessment.
Plaintiff is also obligated to pay the disputed late fees. If a condominium association is
successful in an action arising from the alleged default of a co-owner, the association may
recover costs and reasonable attorney fees associated with that action, to the extent provided by
the association’s bylaws. MCL 559.206(b); Windemere Commons I Ass’n v O’Brien, 269
Mich App 681, 683; 713 NW2d 814 (2006). Brynmawr’s bylaws provide that the association
may collect late fees and interest for unpaid assessments. Plaintiff admitted at trial that she owed
assessments dating from March 2001. Brynmawr had a right to refuse partial payment of the
amount due, and plaintiff failed to make payment in full at her own peril. Because the payments
were indeed owing, the assessment of late charges and attorney fees was proper. Based on this
evidence, the trial court did not clearly err when it found plaintiff liable for the late fees incurred
on the unpaid assessments.
IV. Case Evaluation Sanctions
Finally, plaintiff argues that the trial court erroneously compared her case evaluation
against the $13,443.34 trial court award to determine if she was entitled to case evaluation
sanctions. Instead, she argues, the trial court should have upheld its original order awarding her
sanctions because it had properly compared her case evaluation against the value of the award in
favor of Brynmawr on the date of the case evaluation to determine if she was entitled to
sanctions. We agree. The parties presented the court with a stipulation of facts that included the
following:
3. That the portion of the award in this matter of $13,443.34 that was applicable
on February 14, 2002, the date of case evaluation, was $6,235.34.
4. That Defendant’s costs to repair Plaintiff’s residence, pursuant to the August 5,
2003, Order Granting Equitable Relief, are at least $4,500.00. [Emphasis added.]
Plaintiff and Brynmawr disagree regarding the significance and meaning of this stipulation.
Brynmawr asserts that the stipulation simply supplied the amount of attorney fees and costs
should the court determine that plaintiff improved her position by ten percent, but did not
represent an agreement that $6,235 was the figure to be used in making that determination.
Plaintiff takes the opposite position. Although the stipulation is ambiguous, it is significant that
Brynmawr did not file a response to “Plaintiff’s Motion for Determination that She Improved
Her Position by 10% for Purposes of Case Evaluation Sanctions.” And, when the parties
appeared before the court to argue the motion, Brynmawr never asserted that $13,443.34 was the
-7-
correct figure to be used under the court rule. Rather, it argued that it should be deemed to have
accepted the case evaluation because the award of $2,500 was a pass-through from Signal to
plaintiff, and Brynmawr really had no role in accepting or rejecting that evaluation.
There also appeared to be a dispute regarding whether the evaluation contemplated that
plaintiff receive $2,500 or pay $2,500. The court rejected Brynmawr’s arguments, and
Brynmawr’s counsel then stated, “Your Honor, we’ve agreed to all the numbers so we’ll present
a judgment.” An order was entered, and four months later (almost seven months after the
hearing on plaintiff’s motion), Brynmawr argued for the first time that the $13,443.34 figure
should have been used in ruling on plaintiff’s motion. We conclude that Brynmawr’s conduct is
wholly consistent with plaintiff’s position and is inconsistent with Brynmawr’s. Further, the
stipulation clearly stated that the cost of the repairs was at least $4,500, indicating that the parties
agreed that this figure had some significance in relation to the calculations. If the $13,443.34
had been regarded as relevant to the calculation under the court rule, the parties would no doubt
have either stipulated to an exact figure or sought a determination of the actual cost.4
Accordingly, the trial court abused its discretion when it ignored this stipulated value and
compared plaintiff’s case evaluation to the judgment that Brynmawr was awarded at trial to
determine if she was entitled to case evaluation sanctions.
V. Motion for Dismissal
On cross appeal, Signal claims that the trial court erroneously denied its
MCR 2.504(B)(2) motion for dismissal. Specifically, Signal argues that the evidence presented
at trial failed to establish that it breached its contractual duties to Brynmawr or that it owed
plaintiff a separate and distinct duty from the duty it owned to Brynmawr. We do not agree. We
review the trial court’s factual findings in a bench trial for clear error and review questions of
law de novo. Sands Appliance Services, Inc v Wilson, 463 Mich 231, 238; 615 NW2d 241
(2000).
A trial court may grant a defendant’s motion for involuntary dismissal in a bench trial
after the plaintiff presents her evidence if the court determines that, on the facts and the law, the
plaintiff failed to establish a right to relief. MCR 2.504(B)(2). “[A] motion for involuntary
dismissal calls upon the trial judge to exercise his function as a trier of fact, weigh the evidence,
pass upon the credibility of witnesses and select between conflicting inferences.” Marderosian v
Stroh Brewery Co, 123 Mich App 719, 724; 333 NW2d 341 (1983). The trial court is under no
obligation to view and interpret the evidence in a manner that is most favorable to the plaintiff.
Id.
Signal’s motion was premature. When Signal moved for involuntary dismissal,
Brynmawr, a third-party plaintiff to the indemnification claim, had not yet had the opportunity to
offer evidence regarding the terms of its contract with Signal or indicating whether Signal was
4
Even were we to conclude that the court properly used the $13,443.34 figure, we would still
reverse because the court erred in using the $4,500 figure when the stipulation stated that the cost
of the repairs was at least this much.
-8-
liable for indemnification to Brynmawr. Further, Signal failed to move for involuntary dismissal
after Brynmawr presented its proofs. Because Signal only moved for dismissal before
Brynmawr presented its proofs, Signal’s motion failed to meet the requirements of
MCR 2.504(B)(2) and its motion was properly denied.
Signal’s reliance on Fultz v Union-Commerce Assoc, 470 Mich 460, 467, 469-470; 683
NW2d 587 (2004), is misplaced. Plaintiff alleged in her complaint that Brynmawr violated its
duty to repair her condominium pursuant to the terms of the association’s bylaws. Plaintiff did
not have the burden to establish the terms of Signal’s contractual duty to Brynmawr or to
demonstrate that Signal owned her a “separate and distinct” duty from the duty found in the
underlying contractual obligation. At the time Signal moved for dismissal, the trial court could
not fully evaluate Signal’s liability under the third-party claim. Accordingly, the trial court
properly denied Signal’s motion.
V. Trial Court’s Findings of Substandard/Defective Repairs
Next, Signal argues that the trial court clearly erred when it found that the quality of its
repair work was substandard. We disagree. Again, we review the trial court’s findings of fact in
a bench trial for clear error. Sands Appliance Services, supra at 238.
Although Brynmawr defended the quality of Signal’s work and plaintiff was not privy to
the terms of the contract between Brynmawr and Signal, the trial court still had sufficient
evidence to conclude that Brynmawr was responsible for the work performed by Signal and that
Signal’s work was objectively substandard. At trial, Signal identified areas of the condominium
that it contracted with Brynmawr to repair. Photographs of these areas admitted in evidence
supported the court’s conclusion that the repair work was shoddy and that replacement parts
were poorly installed. The trial court did not clearly err when it concluded that the quality of
Signal’s repair work in the identified instances was substandard.
Affirmed in part and reversed in part. Remanded for further proceedings consistent with
this opinion. We do not retain jurisdiction.
/s/ Donald S. Owens
/s/ Janet T. Neff
/s/ Helene N. White