CITADEL CORP V EASTBANK ASSOC LTD PARTNERSHIP
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
CITADEL CORPORATION,
UNPUBLISHED
September 20, 2002
Plaintiff/CounterdefendantAppellee,
v
EASTBANK ASSOCIATES LIMITED
PARTNERSHIP and UNITED DEVELOPMENT
REAL ESTATE CORPORATION,
No. 223308
Kent Circuit Court
LC No. 92-076542-CH
Defendants/Cross-Defendants,
and
NATIONAL PRECAST, INC.,
Defendant/CrossPlaintiff/Counterplaintiff-Appellant.
Before: Whitbeck, C.J., and Bandstra and Talbot, JJ.
PER CURIAM.
Defendant National Precast, Inc., appeals as of right from an order granting plaintiff
Citadel Corporation’s motion for summary disposition and denying National Precast’s motion
for summary disposition. We affirm in part, reverse in part, and remand.
I. Basic Facts And Procedural History
Citadel was the general contractor for a project involving the construction of Eastbank
Waterfront Towers in Grand Rapids, a high-rise complex owned by Eastbank Associates Limited
Partnership (Eastbank). National Precast was a subcontractor. The contract between Citadel and
National Precast included a pay-when-paid clause providing that progress payments and final
payments did not become due to the subcontractor, National Precast, until the contractor, Citadel,
received payment from the owner, Eastbank. The contract itself stated:
5.1 Progress Payments will be made to Subcontractor on or about the 25th
day of each month, in an amount equal to 90 percent of the value of labor and
materials incorporated by Subcontractor in the Work and, where authorized by the
-1-
Contract Documents, of materials stored on the Project site or other location
agreed upon in writing, in a manner acceptable to Owner, Architect and
Contractor, less the aggregate of previous payments, but such Progress Payments
shall not become due Subcontractor unless and until Contractor receives payment
for such Work from the Owner.
***
6.3 In addition to any other requirements of this Subcontract and the
Contract Documents, Final Payment shall not become due unless and until the
following conditions precedent to Final Payment have been satisfied; (a) approval
and acceptance of Subcontractor’s Work by Owner, Architect and Contractor, (b)
delivery to Contractor of all manuals, “As-Built” Drawings, guarantees, and
warranties for materials and equipment furnished by Subcontractor, or any other
documents required by the Contract Documents, (c) receipt of Final Payment for
Subcontractor’s work by Contractor from Owner, (d) furnishing to Contractor of
satisfactory evidence by Subcontractor that all labor and material accounts
incurred by Subcontractor in connection with its Work have been paid in full, (e)
furnishing to Contractor a complete Affidavit, Release of Lien and Waiver of
Claim by Subcontractor as required by the Contract Documents.[1]
This suit began when Citadel sued Eastbank for payment for work done on that project.
Pursuant to the Construction Lien Act, all subcontractors, including National Precast, were
brought into the lawsuit between Citadel and Eastbank.2 National Precast filed a cross- and
counter-complaint against Eastbank and Citadel, respectively, for foreclosure of the construction
lien in early March 1993. National Precast also alleged breach of the construction contract and
sought recovery under the Builders Trust Fund Act.3 National Precast asked for costs, interest,
and attorney fees.
According to the record, National Precast made its first offer of judgment no later than
1993. Citadel rejected the offer and made a counteroffer. National Precast rejected the
counteroffer and made its own counteroffer. At some point, the parties reached an agreement,
which they placed on the record at a hearing on March 12, 1996. The attorneys made only brief
statements at this hearing. According to Citadel’s attorney, the parties agreed to settle their
primary dispute, National Precast had agreed to waive any interest or attorney fees stemming
from the offer of judgment process, but the parties had not resolved National Precast’s claim for
other attorney fees and interest, which would be decided at a later time. Citadel’s attorney did
not mention the amount of the settlement at the hearing, but representatives for Citadel and
National Precast affirmed the settlement on the record. Importantly, however, Citadel’s
November 1995 motion for summary disposition of National Precast’s request for attorney fees
and interest remained pending following this hearing.
1
Emphasis added.
2
MCL 570.1117(4).
3
MCL 570.151 et seq.
-2-
In July 1996, Citadel and National Precast placed their partial settlement agreement on
the record. The parties agreed to settle their dispute under the contract for $54,500, but reserved
interest and attorney fees as issues to settle later. Citadel moved again for summary disposition
on these issues, arguing that National Precast was not entitled to any interest at all, but if it were
entitled to interest, the interest should be computed from “the time that Citadel got paid by
Eastbank.” In support for this argument, Citadel cited the “pay-when-paid” clause in its
subcontract with National Precast and Berkel v Christman Co,4 which held that these clauses are
enforceable.5 Citadel also argued that the subcontract with National Precast did not address
attorney fees, which meant that it was not entitled to the fees.
National Precast responded that its claims fell under the Construction Lien Act,6 the
subcontract, and the Builder’s Trust Fund Act,7 while Citadel’s arguments only implicated the
contract claim. National Precast claimed that it was entitled to attorney fees under its separate
Construction Lien Act claim. Further, it contended, attorney fees are part of the lien, not part of
money damages. National Precast distinguished Berkel on the basis that, in Berkel, a
construction lien act claim was settled and Berkel received payment,8 so the case before this
Court involved only a contract with a pay-when-paid clause, which this Court held was
enforceable. National Precast argued that a decision on interest by the trial court in this case was
premature until the trial court could determine (1) which party prevailed, and (2) under which
claim the amounts would be paid.
The trial court concluded that the Berkel case controlled National Precast’s construction
lien claim, so it summarily disposed of that claim and simply stated, “There is no interest or
attorney fees here and that the claim by National Precast is premature.” National Precast’s
attorney, who had argued in briefs that National Precast was entitled to the full measure of
interest and attorney fees available under the relevant statutes, attempted to minimize the trial
court’s ruling, saying, “Your Honor, one point of clarification. Is the Court also awarding no
interest or attorney fees for the period from the time . . . Citadel received payment and the time
this matter came to trial [sic]?” Citadel’s attorney responded that it was his “understanding that
we [Citadel] were going to pay them [National Precast] interest from the date that Citadel got
payment until it [National Precast] was paid.” The trial court evidently agreed to this alternative
compromise on interest, but stated that it saw “no provision here by statute or by contract that
would allow attorney fees.”
In August 1996, National Precast moved for entry of judgment. The proposed judgment
National Precast submitted with its motion would have: (1) awarded National Precast $54,500,
but acknowledged that Citadel had already paid that amount on an undisclosed date; (2) denied
National Precast attorney fees; (3) awarded National Precast the twelve-percent money judgment
interest rate calculated from the date Eastbank paid Citadel until Citadel paid any remaining
4
Berkel v Christman Co, 210 Mich App 416; 533 NW2d 838 (1995).
5
Id. at 418-420.
6
MCL 570.1101 et seq.
7
MCL 570.151 et seq.
8
This is not factually correct. See Berkel, supra at 418.
-3-
amounts; and (4) awarded an undetermined amount of taxable costs, including costs “assessed
for the special mediation process ordered in the case.” Citadel, however, filed an objection to the
proposed judgment. According to Citadel, the parties had agreed to $54,500 as the amount of
settlement, but had not agreed to a judgment entered on that amount. Citadel submitted a
proposed order, which the trial court eventually signed with a single modification. That order
stated:
IT IS HEREBY ORDERED as follows:
1. For the reasons set forth in this Court’s oral opinion given from the Bench on
July 29, 1996, Citadel’s Motion for Summary Disposition is granted and National
Precast’s Motion for Summary Disposition is denied.
2. National Precast is awarded no attorney fees.
3. National Precast is awarded interest at the applicable statutory rate in Michigan
from the date Citadel was paid by East Bank [sic] (April 24, 1995), until Citadel
paid National Precast (March 28, 1996), on the $54,500.00 settlement amount
paid to National Precast to Citadel, for a total interest amount of $3,898.49.
[inserted by hand:]
4. No costs awarded.
Subsequently, the trial court denied National Precast’s motion for reconsideration.
II. Standard Of Review
All the issues presented in this case are questions of law, which this Court reviews de
novo.9
III. Contract Claim
According to National Precast, the trial court erred in dismissing its contract claim not
only because this case is distinguishable from Berkel, but also because public policy bars the
pay-when-paid clause in the contract. This case differs from the facts in Berkel in some respects.
However, the pertinent aspect of Berkel is the pay-when-paid clause at issue in that case, which
is substantially the same as the pay-when-paid clause in this case.10 Thus, we see no reason to
refrain from applying Berkel’s holding that a pay-when-paid clause is valid and enforceable in
this case. Nor is there any merit in National Precast’s public policy argument. Even the
Construction Lien Act, MCL 570.1115(5), recognizes circumstances under which it is proper to
reserve payment until a condition precedent occurs. As the analysis in Berkel suggested, the law
generally favors allowing the parties to a contract to agree on the terms of their legal
9
See Kelly v Builders Square, Inc, 465 Mich 29, 34; 632 NW2d 912 (2001).
10
See Berkel, supra at 418.
-4-
relationship, including payment.11 Accordingly, we conclude that it is not against the public
policy of this state to permit the parties to set payment terms, including requiring payment from a
third-party as a condition precedent to payment to a subcontractor.12 Therefore, the trial court
did not err when it determined that Berkel controlled its decision with respect to the contract
claim and mandated summary disposition for this claim.
IV. Construction Lien Claim
Whether Berkel properly supported the trial court’s decision to dispose of National
Precast’s claim under the Construction Lien Act13 presents a completely separate question.14 The
Construction Lien Act15 is remedial legislation16 that sets forth a comprehensive scheme aimed at
securing payment for the individuals and businesses that perform construction work through
equitable actions.17 The act does so by granting, in relevant part, “each” subcontractor “who
provides an improvement to real property” a “construction lien upon the interest of the owner or
lessee who contracted for the improvement to the real property.”18 Further, the act permits and
defines the proceedings to enforce the lien, stating in MCL 570.1117:
(1) Proceedings for the enforcement of a construction lien and the
foreclosure of any interests subject to the construction lien shall not be brought
later than 1 year after the date the claim of lien was recorded.
***
(4) Each person who, at the time of filing the action, has an interest in the
real property involved in the action which would be divested or otherwise
impaired by the foreclosure of the lien, shall be made a party to the action.
(5) In connection with an action for foreclosure of a construction lien, the
lien claimant also may maintain an action on any contract from which the lien
arose.
(6) Except as otherwise provided in subsection (1), a lien claimant who
has been made a party to an action for foreclosure of a construction lien may
11
See id. at 419-420 (enforcing the terms of the contract by which the parties had agreed to
abide).
12
See Skutt v City of Grand Rapids, 275 Mich 258, 264; 266 NW 344 (1936).
13
MCL 570.1101 et seq.
14
See Old Kent Bank of Kalamazoo v Whitaker Construction Co, 222 Mich App 436, 438-441;
566 NW2d 1 (1997) (a construction contract claim is separate and distinct from a claim under the
Construction Lien Act).
15
MCL 570.1101 et seq.
16
See MCL 570.1302(1).
17
See MCL 570.1118(1).
18
MCL 570.1107(1).
-5-
enforce his or her own construction lien in the action by a cross-claim or
counterclaim, and the owner or lessee may timely join other or potential lien
claimants in the action.
MCL 570.1302(1) requires courts interpreting and applying the act to do so “liberally,” in order
“to secure the beneficial results, intents, and purposes of this act.” To that end, MCL
570.1302(2) bars court from construing the act “to prevent a lien claimant from maintaining a
separate action on a contract.” Clearly, in light of this statutory scheme, National Precast’s
settlement with Citadel concerning its contract claim did not extinguish its claim under the
Construction Lien Act.19 Once National Precast became a party to this case pursuant to MCL
570.1117(4), it was entitled to file a timely cross-claim under the Construction Lien Act, which it
did.20 Thus, we conclude that the trial court erred when it summarily disposed of National
Precast’s lien claim on the basis of Berkel.21
IV. Interest
A. Overview
National Precast also argues that it is entitled to interest on its contract claim. It contends
that the trial court’s judgment on the parties’ settlement constitutes a money judgment because it
ordered “the payment of a sum of money, as distinguished from an order directing an act to be
done or property to be restored or transferred.”22 Therefore, National Precast asserts, the
prejudgment interest statute, MCL 600.6013, applies to this judgment. MCL 600.6013(5), the
applicable subsection states:
Except as provided in subsection (6), for a complaint filed on or after
January 1, 1987, but before July 1, 2002, if a judgment is rendered on a written
instrument, interest is calculated from the date of filing the complaint to the date
of satisfaction of the judgment at the rate of 12% per year compounded annually,
unless the instrument has a higher rate of interest. In that case, interest shall be
calculated at the rate specified in the instrument if the rate was legal at the time
the instrument was executed. The rate shall not exceed 13% per year
compounded annually after the date judgment is entered.[23]
B. Money Judgments
The written instrument at issue in this case is the construction contract with its pay-whenpaid clause. Though National Precast was unsuccessful in having the pay-when-paid clause
19
See also Old Kent Bank, supra.
20
See MCL 570.1117(6) and MCL 570.1118(1).
21
Note that if National Precast prevails on its construction lien claim, MCL 570.1118(2) allows
the trial court to award reasonable attorney fees.
22
In re Forfeiture of $176,598, 465 Mich 382, 386; 633 NW2d 367 (2001).
23
Emphasis added.
-6-
invalidated, it nevertheless recovered the amount it was due under the contract, hence the
$54,500 settlement. The critical question that determines whether a judgment is a money
judgment subject to this interest rate is whether the judgment “at issue calls for the payment of
money, rather than the doing of an act, such as the return of a specific item of personal
property.”24 We conclude that there is no merit to Citadel’s argument that the order in this case
falls outside the scope of a money judgment because it is analogous to an in rem or equitable
order. Though, as Citadel notes, the Construction Lien Act is “equitable,” it is also irrelevant to
the money judgment interest statute in the Revised Judicature Act at issue in this appeal.
C. Orders Versus Judgments
We have also considered the fact that the trial court entered an “order” rather than a
“judgment.” MCR 2.116 makes the connection between summary disposition and judgment,
indicating that a motion for summary disposition can result in judgment on a claim.25 The order
also fits the definition of a judgment as
[t]he official and authentic decision of a court of justice upon the respective rights
and claims of the parties to an action or suit therein litigated and submitted to its
determination. The final decision of the court resolving the dispute and
determining the rights and obligations of the parties. The law’s last word in a
judicial controversy, it being the final determination by a court of the rights of the
parties upon matters submitted to it in an action or proceeding.[26]
Given the liberal construction of MCL 600.6013, there is no reason to decline to apply
this statute merely because the trial court labeled its final disposition of this case an “order”
rather than a “judgment.” To deny National Precast interest in this case on the basis that the trial
court did not enter a formal “judgment” would place Citadel, which has not cross-appealed or
argued this issue, in a better position than it occupied at the conclusion of the trial court
proceedings. Thus, in our view, National Precast is not at risk of losing the interest the trial court
actually awarded in this case.
D. Calculation Of Interest
The final issue with respect to interest concerns its calculation. As we noted above,
National Precast filed its cross- and counter-complaint against Eastbank and Citadel for
foreclosure of the construction lien in early March 1993. At that time, National Precast also
alleged breach of the construction contract and sought recovery under the Builders Trust Fund
Act. However, the trial court awarded National Precast interest from the date Eastbank paid
Citadel, April 24, 1995, until Citadel paid National Precast, March 28, 1996. The question is,
therefore, whether Citadel owes interest to National Precast from March 1993 through April
1995.
24
People v $176,598 US Currency, 242 Mich App 342, 348; 618 NW2d 922 (2000).
25
See, e.g., MCR 2.116(B)(1), G)(4).
26
Black’s Law Dictionary (6th ed, 1990), pp 841-842.
-7-
Under MCL 600.6013(5), the calculation of interest begins with “the date of filing the
complaint.” In this case, that date would be the date in March 1993 when National Precast filed
its counter-complaint against Citadel.27 We are, however, mindful of Citadel’s argument that,
under the pay-when-paid provisions of the construction contract, National Precast would have
had no cause of action against Citadel on that date, because Eastbank had not then paid Citadel.
In Phinney v Perlmutter,28 this Court considered a somewhat similar issue. There,
Carolyn Phinney, a former researcher at the University of Michigan, filed her complaint against
Marion Perlmutter on October 1, 1990.29 However, the original complaint did not include a
claim for “fraud and misrepresentation, the theory upon which Phinney ultimately recovered.”30
Indeed, only when Phinney filed her fourth amended complaint on March 11, 1992, did she
claim fraud and misrepresentation.31 Whether Phinney asked for interest calculated from the
date she filed the first complaint is not clear. However, the trial court ruled that the prejudgment
interest should be calculated32 from the date Phinney filed the fourth amended complaint.33
Phinney then cross-appealed the trial court’s decision regarding interest.34 In analyzing
the issue, this Court first noted that “the purpose of prejudgment interest is to compensate the
prevailing party for expenses incurred in bring actions for money damages, and for any delay in
receiving such damages.”35 However, this Court then cited Justice Riley’s opinion in
Rittenhouse v Erhart,36 for the proposition that the purpose of prejudgment interest statute “is not
furthered by allowing interest for periods during which no claim existed against the defendant.”37
This Court also acknowledged that “[a] court may disallow prejudgment interest for periods of
delay where the delay was not the fault of, or caused by, the debtor,” and suggested that Phinney
caused some delay by waiting more than a year to amend her complaint to include this additional
27
See Goodwin, Inc v Coe (On Remand), 62 Mich App 405; 233 NW2d 598 (1975).
28
Phinney v Perlmutter, 222 Mich App 513; 564 NW2d 532 (1997).
29
Id. at 520, 539.
30
Id. at 540.
31
Id.
32
The trial court in Phinney relied on MCL 600.6013(6) and (8), not subsection (5), because the
case did not involve judgment on a written instrument. See Phinney, supra at 540. Notably,
however, subsection (8) also requires prejudgment interest to be calculated from “the filing of
the complaint.” Compare MCL 600.6013(5) and MCL 600.6013(8). Thus, there is no reason to
distinguish Phinney from this case on the basis of the statutory subsection at issue.
33
Phinney, supra at 540.
34
Id. at 539-540.
35
Id. at 541, citing Hadfield v Oakland Co Drain Comm’r, 218 Mich App 351, 356; 554 NW2d
43 (1996) and Paulitch v Detroit Edison Co, 208 Mich App 6456, 663, n 2; 528 NW2d 200
(1995).
36
Rittenhouse v Erhart, 424 Mich 166, 218; 380 NW2d 440 (1995).
37
Phinney, supra at 542 (emphasis added).
-8-
theory of recovery.38 Nevertheless, the Court returned to the statute’s remedial purpose and
liberal interpretation, holding that “prejudgment interest was awardable from the date that a
complaint was filed against Perlmutter.”39 Thus, the Court reversed and remanded the interest
issue to the trial court.40
In this case, given the contract’s pay-when-paid provision, it is certainly arguable that
National Precast suffered no compensable loss until Eastbank paid Citadel in April 1995.
Nevertheless, National Precast’s claim against Citadel did exist at the time it filed its countercomplaint in March 1993. That claim, even if premature, was never dismissed. While it would
not seem to further the purpose of MCL 600.6013(5) to award prejudgment interest for a period
when a claim was not yet compensable, Phinney makes clear that the language in the statute
must be construed liberally in National Precast’s favor. This is certainly a literal – perhaps even
wooden – reading of the statute, but it does comport with the statute’s plain and unambiguous
meaning. There is nothing in our judicial charters, nor should there be, that gives us the power to
amend the plain and unambiguous meaning of a statute, even if we encounter absurd results from
the statutory language.41 The Legislature, alone, has the power to amend statutes, and perhaps
that body should consider exercising its power to amend this particular statutory provision.
However, regardless of any future legislative action, the trial court in this case erred when it
refused to award prejudment interest on the $54,000 judgment from the date National Precast
filed its claim in its counter-complaint. Whether the pay-when-paid clause would have allowed
Citadel to argue that National Precast’s contract claim was not viable at the time it filed the
counter-complaint because Citadel had yet to receive payment has no effect, we conclude, on the
statutory language as it currently exists.
Affirmed in part, reversed in part, and remanded for further proceedings consistent with
this opinion. We do not retain jurisdiction.
/s/ William C. Whitbeck
/s/ Richard A. Bandstra
/s/ Michael J. Talbot
38
Id. at 541.
39
Id. at 541-542.
40
Id. at 564.
41
The Supreme Court has warned that the “absurd result” method of interpreting statutes plays
no role when the statutory meaning is clear. See People v McIntire, 461 Mich 147; 599 NW2d
102 (1999).
-9-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.