JAMES ELLER V MCLOUTH STEEL
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
JAMES ELLER, Individually and as
Next friend of JAMES ELLER, III, a minor,
UNPUBLISHED
June 29, 2001
Plaintiffs,
v
McLOUTH STEEL, an assumed name for
McLOUTH STEEL PRODUCTS
CORPORATION, a Michigan Corporation,
METRO INDUSTRIAL CONTRACTING, INC., a
Michigan Corporation, and POWER PROCESS
PIPING, INC., a Michigan Corporation
jointly and severally,
No. 220337
Wayne Circuit Court
LC No. 96-610379-NO
Defendants.
METRO INDUSTRIAL CONTRACTING, INC.,
a Michigan Corporation,
Third Party Plaintiff-Appellant,
v
MID-AMERICAN GUNITE, INC.,
Third Party Defendant-Appellee.
Before: Cavanagh, P.J., and Cooper and K.F. Kelly, JJ.
PER CURIAM.
Third-party plaintiff appellant, Metro Industrial Contracting, Inc. (Metro), appeals as of
right an October 10, 1997, order granting summary disposition, pursuant to MCR 2.116(C)(10),
to third-party defendant appellee, Mid-American Gunite, Inc. (Gunite). Gunite cross-appeals and
claims that the full indemnification of Metro has rendered this appeal moot. We reverse.
-1-
Metro was the general contractor for a construction project on the # 2 blast furnace at
McLouth Steel Products Corporation. Metro contracted with Power Processing Piping, Inc.
(PPP) as the prime mechanical and pipefitting subcontractor. Gunite also entered into a
subcontract with Metro on June 23, 1995. The contract stated that Gunite was hired to “supply
all labor, supervision, tools, equipment and materials to perform all brick and refractory work.”
The common procedure for relining a blast furnace requires that the new brick be applied
from the ground up, with the trades working in a “stacked” or vertical fashion. Blast furnaces
contain large coolers that must be removed in order to re-brick the furnace. While relining the
furnace with bricks from a scaffold, James Eller, an employee of Gunite, was seriously injured.
The scaffold had two levels: the first was for Eller to stand upon and the second level was to
stack bricks on and serve as a shield for falling debris.1 As Eller and the other Gunite employees
were working below, Metro and PPP were in the process of lowering the overhead coolers.
These coolers weighed approximately 225 pounds. During this procedure, one of the coolers
broke free from its safety wires and fell through the scaffold that Eller was standing upon. Eller
suffered severe injuries to his back and side.
Eller filed a law suit in circuit court on March 8, 1996, against Metro and PPP for the
injuries he sustained. Thereafter, Metro requested permission from the court to name Gunite as a
third-party defendant. On February 3, 1997, the trial court entered an order allowing Metro to
name Gunite as a third-party defendant. On April 18, 1997, Gunite filed a motion for summary
disposition pursuant to MCR 2.116(C)(10). The trial court denied this motion on May 23, 1997,
ruling that questions of fact remained concerning whether the brick scaffold was poorly
constructed by Gunite.
On September 19, 1997, after the completion of discovery, Gunite filed another motion
for summary disposition, pursuant to MCR 2.116(C)(10). On October 10, 1997, the trial court
granted Gunite’s motion for summary disposition and agreed with Gunite that no evidence was
produced to suggest that Gunite was unreasonable for working beneath PPP and Metro while the
coolers were being removed. Nor was there any evidence produced that the scaffolding was
insufficient. The trial court also concluded that Eller’s injury did not arise out of, result from, or
was in any way connected with Gunite’s work.2
On March 1, 1999, Metro filed this appeal from the trial court’s grant of summary
disposition for Gunite. Metro is seeking indemnification from Gunite for Metro’s share of the
judgment.
1
The scaffolding at issue was newly built and there was no evidence to indicate that it was
unsafe or poorly constructed. Gunite constructed the scaffold to be used as a brick reline scaffold
but it also served as a protection from falling objects. While the scaffold was sufficient to stop
falling bolts, it was not built to withstand heavy falling objects.
2
A jury later awarded Eller a $783,713.89 judgment against Metro and PPP. The fault was
allotted equally between Metro and PPP. The jury did not find contributory negligence on the
part of Eller.
-2-
Gunite argues on cross-appeal that Metro has been fully indemnified by PPP and that this
claim should be barred for mootness. However, Gunite has presented absolutely no evidence on
appeal to substantiate this argument. “A party may not merely announce a position and leave it
to the Court of Appeals to discover and rationalize the basis for the claim.” Joerger v Gordon
Food Service, Inc, 224 Mich App 167, 178; 568 NW2d 365 (1997). Therefore, we decline to
address Gunite’s claim of mootness on appeal.
Metro asserts that the trial court erred in granting Gunite’s motion for summary
disposition. Instead, Metro claims that the evidence established that Eller’s injury arose out of or
in connection with Gunite’s performance of its contract. Therefore, Metro argues that it is
entitled to contractual indemnification as a matter of law. We agree.
A trial court’s grant or denial of summary disposition is subject to de novo review on
appeal. Spiek v Dep't of Transportation, 456 Mich 331, 337; 572 NW2d 201 (1998). Summary
disposition is only appropriate when no genuine issue of material fact exists and the moving
party is entitled to judgment as a matter of law. MCR 2.116(C)(10); Auto-Owners Ins Co v
Allied Adjusters & Appraisers, Inc, 238 Mich App 394, 397; 605 NW2d 685 (1999). A trial
court must consider the pleadings, affidavits, depositions, admissions, and other documentary
evidence submitted in the light most favorable to the nonmoving party. Maiden v Rozwood, 461
Mich 109, 119-120; 597 NW2d 817, reh den 461 Mich 1205 (1999).
An indemnity contract is generally construed in the same fashion as a contract. Zurich
Ins Co v CCR & Co (On Rehearing), 226 Mich App 599, 603; 576 NW2d 392 (1997). The
primary goal in contract construction is to ascertain and give effect to the intent of the parties.
MSI Construction Managers, Inc v Corvo Iron Works, Inc, 208 Mich App 340, 343; 527 NW2d
79 (1995). The intent of the parties is revealed “by considering the language of the contract, the
situation of the parties, and the circumstances surrounding the making of the contract.” Triple E
Produce Corp v Mastronardi Produce, Ltd, 209 Mich App 165, 172; 530 NW2d 772 (1995).
Ambiguities in an indemnity contract are to be strictly construed against the drafter of the
contract and the party who was the indemnitee. Id. at 172. “A provision which seeks to
indemnify a promisee against liability for its own negligence is valid in the case of concurrent
negligence by multiple tortfeasors.”3 MSI Construction, supra at 343. This Court should
interpret the indemnify clause so as to provide a reasonable meaning to all its terms. Id.
The indemnification contract between Metro and Gunite provided in pertinent part that
Gunite would:
3
Michigan law also states that an indemnity contract which purports to require indemnification
for the sole negligence of the indemnitee is against public policy and void. MCL 691.991;
Sherman v DeMaria Building Co, Inc, 203 Mich App 593, 600; 513 NW2d 187 (1994);.
However, this is not an issue in this case because both PPP and Metro were declared negligent.
“[A]s long as the injury was not caused by the indemnitee’s negligence alone, indemnification
was valid.” Sherman, supra at 600.
-3-
indemnify, protect, defend and save harmless Company [Metro] from and against
all liability for injuries, including death, to any and all persons whomsoever and
for any and all property damage arising out of or resulting from or in any way
connected with the work covered by this Subcontract or the operations or acts of
commission or omission of the Subcontractor [Gunite], his subcontractors, agents
and employees. [Emphasis added.]
Thus, Gunite would owe indemnity to Metro if: (1) the injury arose out of work covered by
Gunite’s contract; (2) the injury resulted from work covered by Gunite’s contract; or (3) the
injury was in any way connected with the work covered by Gunite’s contract. Additionally,
indemnity would arise if an injury occurred under Gunite’s operations or acts of commission or
omission.
We believe that given the circumstances and a reasonable interpretation of the contractual
terms, the indemnity clause provided broad indemnity whether Gunite was at fault or the injury
was in any way connected to Gunite’s work. Several Michigan cases support the proposition that
indemnity requires only a link between the work and the injury, regardless of the existence of
fault. See Fischbach-Natkin Co v Power Process Piping, Inc, 157 Mich App 448; 403 NW2d
569 (1987); Sherman, supra; Walbridge Aldinger Co v Walcon Corp, 207 Mich App 566; 525
NW2d 489 (1995). We further note that Eller was, in fact, injured while performing the
contracted work because he was in the process of re-bricking the blast furnace.
In Fischbach-Natkin, supra, the contract required indemnification for “any and all
persons whomsoever and for any and all property damage arising out of or resulting from or in
any way connected with the work covered by this subcontract or the operations or acts of
commission or omission of the Subcontractor, his subcontractors, agents and employees.” Id. at
451 (Emphasis added.). In that case, the subcontractor’s employee was injured due to the
negligence of the general contractor’s employees, when a heavy hydraulic machine tipped over
on him during installation. Id. The Court held that indemnification from the general contractor’s
own negligence was intended in the contract as seen from the parties’ situation and their
surrounding circumstances. Id. at 453-454.
To ascertain the intent of the parties, the Court in Fischbach-Natkin looked to the Paquin
v Harnischfeger Corp, 113 Mich App 43; 317 NW2d 279 (1982), decision. Fischbach-Natkin,
supra at 454. Given the surrounding circumstances and the understanding “that all the work
connected with installing the machine would not be performed by defendant, and that the
employees of plaintiff and other subcontractors would be present at the common work area[,]”
the possibility that injuries could result from plaintiff’s negligence was apparent at the time the
indemnification contract was enacted. Id. In light of the indemnification contract’s broad
provisions and the parties’ situation, the Court concluded that there was a clear intent to
indemnify plaintiff for his own negligence. Id. at 455.
-4-
Michigan caselaw clearly supports the conclusion that a general contractor can be
indemnified for its own negligence without a specific contractual clause to that effect.4
Fischback-Natkin, supra at 452-453. Additionally, to give effect to the intentions of the parties,
Michigan courts “must consider the language used in the contract as well as the situation of the
parties and circumstances surrounding the contract.” MSI Construction, supra at 343. Thus, in
the construction situations discussed, our Courts have continually found that the possibility of
injury or damage from other subcontractors or the general contractor was readily apparent at the
time the indemnification contracts were signed. See Fischback-Natkin, supra at 454; Sherman,
supra at 599; Paquin, supra at 53.
In the case at bar, the indemnification language was identical to that used in FischbackNatkin. Id. at 451. While the factual situation in Fischback-Natkin differs somewhat from the
case at bar, in that the employee was clearly injured in the process of performing the
subcontractor’s work, the injury was still due to the negligence of the general contractor. Id. at
450-451. In Fischback-Natkin, the circumstances surrounding the contract indicated that the
subcontractor knew several other people would be working with their employees in the same
area. Id. at 454. Consequently, the Court decided that it was apparent to the subcontractor, when
he entered into the contract, that an injury could occur due to the general contractor’s or another
party’s negligence. Id. at 455.
Gunite argues that the real question is whether the injury arose out of or in connection
with the work Gunite was hired to do under the contract. The contested contract states that
Gunite was hired to perform all the brick and refractory work and provide all the necessary
equipment and materials. Gunite maintains that Eller’s injury was unrelated to Gunite’s
subcontracted work because it arose out of and was connected with the work of Metro and PPP.
To support their argument Gunite urges us to rely on Texas law.5 However, Texas
caselaw is not binding authority on this Court. Moreover, we find that existing Michigan
caselaw clearly requires us to ascertain the parties’ intention in an indemnification contract by
looking to their surrounding circumstances.
In the case at bar, there is no dispute that Eller was injured while he was in the process of
re-bricking the blast furnace. In fact, the re-bricking was the work that Gunite contracted to do
and it was the work covered under the indemnity contract. The facts indicate that Eller was not
injured from re-bricking, but instead by a cooler that was dropped by employees of Metro and
PPP. However, since Eller was injured while performing the contracted work, it appears that the
injury was received in connection with the work covered under the subcontract.
4
This position is contrary to earlier Michigan cases which required an express agreement to
indemnify for a general contractor’s own negligence. See Geurink v Herlihy Mid-Continent Co,
5 Mich App 154, 158-159; 146 NW2d 111 (1966) (“The indemnifying language in the purchase
order does not insulate the appellant from the consequences of his own negligent conduct unless
it is clearly shown that the parties expressly agreed to this type of indemnification.”)
5
See Brown & Root, Inc v Service Painting Co of Beaumont, Inc, 437 SW2d 630 (1969);
Westinghouse Electric Corp v Childs-Bellows, 352 SW2d 806 (1962).
-5-
Michigan is replete with caselaw stating that specific language indemnifying the general
contractor for its own negligence is not required, and that the intent of the parties should be based
on the surrounding circumstances and the situation of the parties. Fischback-Natkin, supra; MSI
Construction, supra. Using the surrounding circumstances it appears that Gunite was aware of
the working conditions in a blast furnace, with the trades working in a “stacked” fashion, and the
possibility of injury from falling objects.6 Moreover, neither party has argued that they were in
an inferior position during the making of the contract or that they misunderstood its terms. See
Sherman, supra at 597-598. The fact that Eller was injured while performing the contracted
work, coupled with Gunite’s awareness of the working conditions, leads this Court to conclude
that Gunite initially intended to indemnify Metro for the type of injury sustained by Eller. Given
the facts of this case and the broad language of the contract, we find that Metro is entitled to
indemnification from Gunite.
We reverse.
/s/ Mark J. Cavanagh
/s/ Jessica R. Cooper
/s/ Kirsten Frank Kelly
6
Deposition testimony established that the blast furnace’s design makes it common practice for
the trades to work above each other, in a “stacked” fashion, during the re-bricking process.
-6-
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.