RICHARD DARBY V LAKETOWN TWP
Annotate this Case
Download PDF
STATE OF MICHIGAN
COURT OF APPEALS
RICHARD DARBY,
UNPUBLISHED
January 11, 2000
Plaintiff,
v
No. 211942
Allegan Circuit Court
LC No. 96 19075 CK
LAKETOWN TOWNSHIP,
Defendant/Cross-Plaintiff/
Appellant,
and
KALAMAZOO LAKE SEWER AND WATER
AUTHORITY, VILLAGE OF DOUGLAS, CITY
OF SAUGATUCK, and ALLEGAN COUNTY
BOARD OF PUBLIC WORKS,
Defendants/Cross-Defendants/
Appellees.
Before: Zahra, P.J., and Kelly and McDonald, JJ.
PER CURIAM.
In this contract case, the parties dispute the extent of contractual rights to water and sewer
capacity granted to cross-plaintiff Laketown Township as a third party beneficiary to a contract
between cross-defendants and the State of Michigan. Cross-plaintiff appeals as of right from the trial
court’s order granting cross-defendants’ motion for summary disposition pursuant to MCR 2.116(C)(8)
as to count II, MCR 2.116(C)(10) as to count III, and MCR 2.116(C)(8) and (10) as to count IV of
cross-plaintiff’s claim. Additionally, cross-plaintiff appeals as of right from the trial court’s judgment of
no cause of action as to count I of cross-plaintiff’s claim. We affirm.
I Facts
-1
In 1976 the cities of Saugatuck and Douglas agreed to cooperate together to construct a
sewage collection and treatment system to serve their communities. In December 1976, Saugatuck and
Douglas, pursuant to MCL 124.284; MSA 5.2769(54), each signed resolutions adopting articles of
incorporation to form the water authority.
On August 5, 1977, Saugatuck and Douglas, through the water authority, entered into a
contract with Allegan County Board of Public Works (hereinafter “BPW”) whereby BPW agreed to
build the waste water collection and treatment system (hereinafter “the system”) and then lease the
system back to the water authority for forty years. At the end of the forty years, BPW agreed that
ownership would transfer to the water authority.
At the time the water authority was planning to construct the system, the State of Michigan was
building the Saugatuck Dunes Correctional Facility (hereinafter “the prison”) in Laketown Township.
During construction of the prison, the state sought permission to tie-in to the water authority’s waste
water treatment plant. However, in order for the state to hook up to the system, it was necessary for
the state and the water authority to receive Laketown’s permission to run some of the infrastructure
along county roads within Laketown. Laketown was unwilling to grant the water authority permission
unless Laketown was also granted access to the waste water treatment facility. On June 20, 1978,
Laketown’s board of trustees, representatives of the State of Michigan, and members of the water
authority met to work out an agreement that would be acceptable to all parties. After the meeting, the
state and cross-defendants believed that Laketown would approve the installation of the infrastructure
within the township if Laketown could utilize up to 10,000 gallons per day capacity which would be
surrendered from the 60,000 gallons per day committed to the state.
The negotiations between the state, the BPW, the water authority, and Laketown resulted in
what is commonly referred to as the “Dunes Contract.” Before the execution of the Dunes Contract by
the water authority, BPW, and the state (Laketown was not a signatory to the contract), Laketown
passed a resolution of its board of trustees on July 7, 1978, granting BPW permission to construct the
necessary infrastructure along Laketown roads, which states, in part:
The Laketown Township Board hereby grants its approval to the Allegan County
Board of Public Works and the Kalamazoo Lake Sewer and water authority to
proceed with the construction of a sewage transmission facility over and under the
above described streets, avenues and highways as are located within the boundaries of
Laketown Township, Allegan County, Michigan . . . provided, however, that the
residents of Laketown Township shall be permitted, notwithstanding possible earlier
expiration of any contract between the Authority and the State of Michigan, to utilize for
at least forty years, a minimum of 10,000 gallons per day of capacity in the Authority’s
treatment plant and treatment facility, and such additional per day gallonage as will not
interfere with the needs of the Michigan Dunes Correctional Facility and as are within
the capacities of said transmission main and treatment plant as determined and
approved by said Authority and Board of Public Works, through a connection point in
the vicinity of Island Lake Road and 64th Street, to be installed at the time of the original
transmission main construction.
-2
On July 11, 1978, the water authority, BPW, and the state executed the Dunes Contract. A
copy of Laketown’s resolution was attached to the Dunes Contract as “Attachment D” when the
contract was executed, and the resolution was specifically referenced within the Dunes Contract. Under
the Dunes Contract, the state agreed to pay the entire cost of installation of the water main,
administration costs, specific operational costs, and reduced customer use charges. In exchange, the
state was assured a maximum of 60,000 gallons per day capacity in the system that was previously
reserved for use by Saugatuck. The Dunes Contract, by its terms, was to terminate as of the date and
time the state ceased to own and operate the prison or forty years from the date the Dunes Contract
was executed, whichever event occurred first.
As a result of the negotiations with Laketown, the state’s allotted 60,000 gallons per day was
subject to Laketown’s right to obtain 10,000 gallons per day of capacity upon 30 days’ written notice
to the water authority and the state. Although Laketown was not a signatory to the Dunes Contract,
Laketown requested that the Dunes Contract reflect the capacity to which Laketown would be entitled.
Two paragraphs were added to the proposed agreement between the water authority and the state to
reflect the agreement which had been reached with Laketown. Paragraphs 15 and 16 of the Dunes
Contract state as follows:
15. LAKETOWN TOWNSHIP: Laketown Township residents may connect
to the transmission facility through a connection point at the vicinity of Island Lake Road
and 64th Street, which point shall be provided for in the original construction. Input
through this point shall be metered and shall be limited to not more than 10,000 gallons
per day. Rights under this paragraph must be effectuated by 30 days’ written notice
from the Laketown Township Board to the AUTHORITY and to the STATE. Upon
expiration of 30 days after such notice, any reference in this contract to 60,000 gallons
per day for the STATE shall be deemed to read “50,000 gallons per day”, provided
however, that the 10,000 gallons per day limitation may be increased to additional per
day gallonage, as is within the capacity of the transmission main and treatment plant and
as approved and determined by the AUTHORITY and the Board of Public Works, so
long as any said additional per day gallonage will not impair or interfere with the
guaranteed per day capacity granted to the STATE as hereinabove set forth. Any
request for capacity by Laketown Township above the 10,000 gallons per day
limitation shall be made in writing and must first be approved by the AUTHORITY and
the Board of Public Works after consultation with the STATE. The AUTHORITY
shall not be obligated to allocate, by virtue of such a request from Laketown Township,
any additional capacity in its treatment plant above the 60,000 gallons per day allocation
now provided for in this contract.
16. THIRD PARTY BENEFICIARIES: Laketown Township and its
residents shall be considered to be third party beneficiaries of paragraph 15. Rights
under that paragraph and this paragraph shall be preserved through the original 40 year
term of the agreement, notwithstanding earlier termination as the result of the state’s
ceasing to own and operate the Michigan Dunes Correctional Facility.
-3
In 1995, the state closed the prison and conveyed the property to Laketown. As evidenced by
a March 11,1996 letter from Laketown to the water authority, it became apparent that Laketown
believed that under paragraphs 15 and 16 of the Dunes Contract, it was entitled to the entire 60,000
gallons per day, as a matter of right and without approval of the water authority, because the state had
closed the prison and sold the property. The water authority, Saugatuck and Douglas disagreed.
II Procedural History
Plaintiff Richard Darby, a real estate developer who owned property in Laketown, commenced
this suit because his initial request to connect his property to the water authority’s system had been
denied by the water authority. Ultimately, plaintiff’s claim was dismissed by summary disposition and
plaintiff has not appealed the dismissal.
Laketown filed a five-count cross-claim against its codefendants Saugatuck, Douglas, the water
authority, and BPW. Count I alleged that under paragraphs 15 and 16 of the Dunes Contract,
Laketown is entitled to additional capacity out of the state’s contracted capacity of 50,000 gallons per
day upon written request, subject only to consultation with the state to confirm that the state will not
need such capacity, and because the state no longer owns and operates the prison, Laketown is entitled
to the full 60,000 gallons per day without approval from the water authority. Count II alleged that under
the Dunes Contract, Laketown is entitled to “step into the shoes of the State” and pay the same rate for
the 50,000 gallons per day capacity that the state paid, and that Laketown is not required to pay the
usual connection fees and other charges which are paid by nonresident customers of the system. Count
III alleged that in the alternative to an express contract under the Dunes Contract, “cross-defendants
impliedly agreed that . . . [Laketown] could use the portion of the 60,000 gallons per day contracted
capacity no longer needed by the state, at the same rates (without connection charges) under the
express terms of the 1978 [Dunes] Contract.” Count IV alleged that if cross-defendants are allowed to
deny Laketown the right to use the contracted capacity at the same rate (and without connection fees)
as provided for the state in the Dunes Contract, cross-defendants would be unjustly enriched and that it
would be inequitable for cross-defendants to retain the benefits of the Dunes Contract, which was made
possible by Laketown’s approval of installation of the transmission main in Laketown. Count V alleged
that the rates which cross-defendants were insisting were applicable to the use by Laketown violated
conditions included in state and federal grants used to construct the system.
The trial court dismissed counts II, III, IV of Laketown’s cross-claim against the water
authority, Saugatuck, and Douglas following a motion for summary disposition pursuant to MCR
2.116(C)(8) and (10), and it granted Laketown leave to amend its cross-claim as to count V because
Laketown had not attached to the pleadings the document upon which the claim was based as required
by MCR 2.113(F). In addition to curing the procedural deficiency, Laketown added the subheading
“BPW only” to counts II, III, and IV in its amended cross-claim. Following the trial court’s grant of
summary disposition as to counts II, III, and IV against the water authority, Saugatuck, and Douglas,
BPW filed a motion for summary disposition. Instead of a second hearing and ruling, a stipulation and
order was signed which disposed of Laketown’s cross-claim against BPW in accordance with the
court’s order following the summary disposition motion by the water authority, Saugatuck, and Douglas
-4
as if a motion for summary disposition had been brought by BPW at the time the motion was brought by
the other cross-defendants.
On March 2, 1998, the trial court conducted a one-day bench trial regarding count I of
Laketown’s cross-claim. Before trial, the trial court dismissed count V following a motion for summary
disposition by cross-defendants. After a day’s worth of testimony and reviewing documentary evidence,
the trial court found that Laketown has an unconditional right to access the 10,000 gallons per day
capacity, but the right to use any additional capacity is strictly governed by paragraphs 15 and 16 of the
Dunes Contract which requires Laketown to get approval from the water authority rather than an
unconditional automatic right to the unused capacity allotted to the state. Accordingly, the trial court
denied Laketown’s request for a declaratory judgment of unconditional rights to the 50,000 gallons per
day capacity.
III Analysis
A. Trial court’s dismissal of counts II, III, and IV of Laketown’s cross-claim.
Before reaching the merits of cross-plaintiff’s appeal, we note that cross-defendants argue that
cross-plaintiff abandoned its claim under counts II, III, and IV because cross-plaintiff’s second
amended cross-claim added the words “BPW only” to the subheading of counts II, III, and IV and
then cross-plaintiff did not pursue these claims against BPW at trial. We disagree. Although an
amended pleading generally supersedes any previous pleading, MCR 2.118(A)(4), in this case cross
plaintiff was simply acknowledging that the trial court had dismissed counts II, III, and IV by summary
disposition, but that cross-defendant BPW had not been a party to the motion. Additionally, counts II,
III, and IV were dismissed against BPW in a stipulation and order before trial; therefore, Lakewood did
not abandon these claims by not introducing evidence at trial as to counts II, III, and IV against BPW.
Accordingly, Lakewood has not abandoned the issue of the trial court’s dismissal of counts II, III, and
IV as to all cross-defendants.
This Court reviews the trial court’s grant of summary disposition de novo. Pinckney
Community Schools v Continental Casualty Co, 213 Mich App 521, 525; 540 NW2d 748 (1995).
Therefore, this Court must review the record in the same manner as the trial court to determine whether
the movant was entitled to a judgment as a matter of law. Phillips v Deihm, 213 Mich App 389, 398;
541 NW2d 566 (1995).
First, cross-plaintiff argues that the trial court erred when it dismissed cross-plaintiff’s breach of
contract claim regarding the applicable rates to be charged by the water authority pursuant to MCR
2.116(C)(8). A motion under MCR 2.116(C)(8) tests the legal sufficiency of a claim by the pleadings
alone. Simko v Blake, 448 Mich 648, 654; 532 NW2d 842 (1995); Patterson v Kleiman, 447 Mich
429, 432; 526 NW2d 879 (1994). All factual allegations in support of the claim are accepted as true,
as well as any reasonable inferences or conclusions that can be drawn from the facts, and construed in
the light most favorable to the nonmoving party. Smith v Stolberg, 231 Mich App 256, 258; 586
NW2d 103 (1998). However, a mere statement of a pleader's conclusions, unsupported by allegations
-5
of fact, will not suffice to state a cause of action. ETT Ambulance Service Corp v Rockford
Ambulance, Inc, 204 Mich App 392, 395; 516 NW2d 498 (1994).
In the instant case, cross-plaintiff has alleged that it is entitled to “step into the shoes of the
State” and pay the same rate for the 50,000 gallons per day capacity that the state paid, and that cross
plaintiff is not required to pay the usual connection fees and other charges which are usually paid by
nonresident customers of the system. “‘For a plaintiff to sue on a contract to which he is not a party, it
must be determined that the plaintiff was an intended third-party beneficiary of the contract which suit is
brought on.’” Krass v Joliet, Inc, 233 Mich App 661, 665; 593 NW2d 578 (1999). “The contract
itself reveals the party’s intentions.” Frick v Patrick, 165 Mich App 689, 694; 419 NW2d 55
(1988). The Dunes Contract expressly states in paragraph 16 that the water authority and the state
intended cross-plaintiff to be a third-party beneficiary under paragraph 15 only. However, paragraph
15 does not address rates and connection fees. The rates agreed upon for the state to pay are set forth
in paragraph 6, and in its cross-claim, Laketown pleaded no facts that indicate that the water authority
intended the rates for the state to apply to cross-plaintiff. Accordingly, the trial court properly granted
summary disposition as to count II of cross-plaintiff’s claim.
Second, cross-plaintiff argues that the trial court erred when it dismissed Laketown’s claim for
breach of implied contract pursuant to MCR 2.116(C)(10) because it did not acknowledge the
evidence that the water authority and the state intended to confer a benefit on Laketown as a third-party
beneficiary, and Laketown’s approval of the construction of the infrastructure was a prerequisite to the
Dunes Contract. A motion for summary disposition under MCR 2.116(C)(10) tests whether there is
factual support for a claim. Spiek v Dep’t of Transportation, 456 Mich 331, 337; 572 NW2d 201
(1998). When reviewing a motion granted under MCR 2.116(C)(10), this Court must consider the
pleadings, affidavits, depositions, admissions, and documentary evidence filed or submitted by the
parties. MCR 2.116(G)(5).
Elements required to establish an implied contract include: (1) parties being competent to
contract, (2) proper subject matter, (3) consideration, (4) mutuality of agreement, and (5) mutuality of
obligation. Mallory v Detroit, 181 Mich App 121, 127; 449 NW2d 115 (1989). In the instant case,
cross-plaintiff produced no evidence that would indicate that the water authority intended to confer on
cross-plaintiff the benefits cross-plaintiff alleges it is entitled to. To the contrary, the Dunes Contract
expressly states that cross-defendants intended to limit cross-plaintiff to the benefits set forth in
paragraph 15. It is fundamental that a contract will be implied only if there is no express contract
covering the same subject matter. Johnson v Michigan Mutual Ins Co, 183 Mich App 277, 280; 454
NW2d 128 (1989).
Cross-plaintiff argues that “the Dunes Contract is silent insofar as it does not establish any other
rate applicable to the state’s 60,000 gallons per day capacity in the event that a portion of that capacity
is used by Laketown [;therefore,] it must follow that the state and/or the Authority intended to allow
Laketown to access a portion of the state’s capacity at the rates established for the state by the Dunes
Contract.” However, as previously discussed, paragraph 16 of the Dunes Contract evidences that the
parties did contemplate the extent of cross-plaintiff’s rights as a third-party beneficiary, and the parties
-6
expressly and unambiguously limited cross-plaintiff’s rights to the capacity allotment set forth in
paragraph 15.
Next, cross-plaintiff argues that the trial court erred when it dismissed its claim of unjust
enrichment pursuant to MCR 2.116(C)(8) and (10) because there is evidence that the water authority
had been unjustly enriched at cross-plaintiff’s expense. Specifically, if the water authority is allowed to
refuse Laketown the benefit set forth in the Dunes Contract and Laketown’s resolution, i.e., a minimum
of 10,000 gallons per day at the rates established for the state, the water authority will be unjustly
enriched at the expense of Laketown.
The doctrine of unjust enrichment operates to imply a contract where a defendant has received
a benefit from a plaintiff and an inequity would otherwise result at the plaintiff’s expense because of the
retention of the benefit by the defendant. Barber v SMH (US), Inc, 202 Mich App 366, 375; 509
NW2d 791 (1993) (citing Dumas v Auto Club Ins Ass'n, 437 Mich 521, 546; 473 NW2d 652
(1991)). “However, a contract will be implied only if there is no express contract covering the same
subject matter.” Id. (citing Campbell v City of Troy, 42 Mich App 534, 537; 202 NW2d 547
(1972). As discussed above, the Dunes Contract named cross-plaintiff as a third-party beneficiary and
paragraph 16 expressly limited cross-plaintiff’s rights to those set out in paragraph 15. Accordingly, this
Court will not imply a contract under the doctrine of unjust enrichment and create additional rights to
cross-plaintiff’s benefit that go beyond the express terms of the Dunes Contract. The trial court
properly granted defendant’s motion for summary disposition of this claim.
B. Trial court’s judgment of no cause of action as to count I of Laketown’s cross-claim.
Count I of cross-plaintiff’s claim alleged that under the Dunes Contract and the Laketown
Resolution of July 7, 1978, Laketown is entitled to additional capacity out of the state’s contracted
capacity upon written request subject only to consultation with the state to confirm that the state will not
need such capacity, and because the state no longer owns and operates the prison, cross-plaintiff is
entitled to the full 60,000 gallons per day capacity without approval from the water authority.
Cross-plaintiff argues that the trial court erred when it discounted the facial inconsistency
between the Laketown resolution and the language of paragraph 15 and rendered a judgment of no
cause of action against cross-plaintiff. “The primary goal in the construction or interpretation of any
contract is to honor the intent of the parties.” Rasheed v Chrysler Corp, 445 Mich 109, 127, n 28;
517 NW2d 19 (1994). If the meaning of an agreement is ambiguous or unclear, the trier of fact is to
determine the intent of the parties. Chrysler Corp v Brencal Contractors, Inc, 146 Mich App 766,
775; 381 NW2d 814 (1985). A contract is ambiguous if “its words may reasonably be understood in
different ways.” Raska v Farm Bureau Ins Co, 412 Mich 355, 362; 314 NW2d 440 (1982). In this
case, the trial court determined that the conflicting terms between Laketown’s resolution and paragraph
15 of the Dunes Contract made it necessary to examine extrinsic evidence to discern the intent of the
parties involved.
A bench trial was conducted on March 2, 1998 to determine the intent of the parties to the
Dunes Contract in light of the apparently conflicting language in the Dunes Contract and the Laketown
-7
resolution. Where the contract language is unclear or susceptible to multiple meanings, interpretation
becomes a question of fact. Port Huron Ed Ass'n v Port Huron Area School Dist, 452 Mich 309,
323; 550 NW2d 228 (1996). The trial court heard a day’s worth of testimony and reviewed eighteen
trial exhibits which were jointly submitted by the parties. The trial court’s findings of fact may not be set
aside unless clearly erroneous. MCR 2.613(C).
Cross-plaintiff argues that the trial court erred when it discounted the facial inconsistency
between the resolution and the language of paragraph 15. However, the trial court addressed what
appeared to be conflicting language in the Laketown resolution, and after reviewing extrinsic evidence,
held that the resolution and paragraph 15 of the Dunes Contract can be read together. The trial court
found that the resolution and paragraph 15 of the Dunes Contract grant cross-plaintiff access up to
60,000 gallons per day capacity, of which 10,000 gallons per day is guaranteed and the additional
50,000 is subject to approval by the water authority.
The trial court’s findings are supported by the record. Testimony by Allegan District Judge
Stephen Sheridan, who represented the water authority in 1978, and by the manager of the water
authority, who signed the Dunes Contract on behalf of the water authority, established that it was never
the understanding of the water authority that, under the Dunes Contract, cross-plaintiff would
automatically be entitled to one-hundred percent of the state’s capacity if the prison closed. Written
communication between parties indicates that the understanding was that Laketown would be entitled to
capacity up to 10,000 gallons per day. Finally, the attorney who represented Laketown during
negotiations for the Dunes Contract testified that he believes that at one point Laketown’s board may
have agreed to accept a 10,000 gallons per day maximum, but that the board changed its mind after
consulting with its attorney. However, there is no evidence that the change in position was
communicated to cross-defendants, nor is there any evidence which indicates that Laketown objected
to the language in paragraphs 15 and 16 of the Dunes Contract. Accordingly, the trial court’s findings
of fact and its interpretation of the Dunes Contract were not clearly erroneous.
IV Conclusion
The circuit court’s grant of summary disposition as to counts II, III, and IV of cross-plaintiff’s
claim was proper because cross-defendants were entitled to judgment as a matter of law under MCR
2.116(C)(8) & (10). Cross-plaintiff set forth no facts from which the trial court could conclude that
cross-defendants intended cross-plaintiff’s rights as a third-party beneficiary to the Dunes Contract to
extend beyond the rights set forth in paragraph 15 of the contract. Furthermore, a contract cannot be
implied if an express contract exists regarding the subject matter. Here, the Dunes Contract expressly
states cross-plaintiff’s rights to capacity in the water treatment and sewer system.
Facially, the Dunes Contract and the attached resolution appear to conflict and the intent of the
parties is ambiguous. Where the contract language is unclear or susceptible to multiple meanings,
interpretation becomes a question of fact. Findings of fact by the trial court may not be set aside unless
clearly erroneous. The trial court’s interpretation of the Dunes Contract and its opinion as to the intent
of the parties at the time the Dunes Contract was executed are supported by the record. Therefore, the
trial court’s findings are not clearly erroneous.
-8
Affirmed.
/s/ Brian K. Zahra
/s/ Michael J. Kelly
/s/ Gary R. McDonald
-9
Some case metadata and case summaries were written with the help of AI, which can produce inaccuracies. You should read the full case before relying on it for legal research purposes.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.